=Text=
=Text=
{{#Wiki_filter:TSTF Number                                                             TSTF Title                                   Adoption (Approvals Submittals TSTF-358, Rev. 6   Missed Surveillance Requirements                                                                       100%
{{#Wiki_filter:TSTF Number TSTF Title Adoption (Approvals Submittals TSTF-358, Rev. 6 Missed Surveillance Requirements 100%
TSTF-369, Rev. 1   Removal of Monthly Operating Report and Occupational Radiation Exposure Report                         100%
TSTF-369, Rev. 1 Removal of Monthly Operating Report and Occupational Radiation Exposure Report 100%
TSTF-413, Rev. 0   Elimination of Requirements for a Post Accident Sampling System (PASS) (NEDO-3299)                     100%
TSTF-413, Rev. 0 Elimination of Requirements for a Post Accident Sampling System (PASS) (NEDO-3299) 100%
TSTF-442, Rev. 0   Elimination of Requirements for a Post Accident Sampling System (PASS)                                 100%
TSTF-442, Rev. 0 Elimination of Requirements for a Post Accident Sampling System (PASS) 100%
TSTF-449, Rev. 4   Steam Generator Tube Integrity                                                                         100%
TSTF-449, Rev. 4 Steam Generator Tube Integrity 100%
TSTF-479, Rev, 0   Changes to Reflect Revision of 10CFR50.55a                                                             100%
TSTF-479, Rev, 0 Changes to Reflect Revision of 10CFR50.55a 100%
TSTF-497, Rev, 0   Limit Inservice Testing Program SR 3.0.2 Application to Frequencies of 2 Years or Less                 100%
TSTF-497, Rev, 0 Limit Inservice Testing Program SR 3.0.2 Application to Frequencies of 2 Years or Less 100%
TSTF-448, Rev. 3   Control Room Habitability                                                                               98%
TSTF-448, Rev. 3 Control Room Habitability 98%
TSTF-366, Rev. 0   Elimination of Requirements for a Post Accident Sampling System (PASS)                                 97%
TSTF-366, Rev. 0 Elimination of Requirements for a Post Accident Sampling System (PASS) 97%
TSTF-447, Rev. 1   Elimination of Hydrogen Recombiners and Change to Hydrogen and Oxygen Monitors                         97%
TSTF-447, Rev. 1 Elimination of Hydrogen Recombiners and Change to Hydrogen and Oxygen Monitors 97%
TSTF-535, Rev. 0   Revise Shutdown Margin Definition to Address Advanced Fuel Designs                                     92%
TSTF-535, Rev. 0 Revise Shutdown Margin Definition to Address Advanced Fuel Designs 92%
TSTF-404, Rev. 0   SDV Actions                                                                                             92%
TSTF-404, Rev. 0 SDV Actions 92%
TSTF-460, Rev. 0   Control Rod Scram Time Testing Frequency                                                                 88%
TSTF-460, Rev. 0 Control Rod Scram Time Testing Frequency 88%
TSTF-542,Rev. 2   Reactor Pressure Vessel Water Inventory Control                                                         88%
TSTF-542,Rev. 2 Reactor Pressure Vessel Water Inventory Control 88%
TSTF-359, Rev. 9   Increase Flexibility in MODE Restraints                                                                 84%
TSTF-359, Rev. 9 Increase Flexibility in MODE Restraints 84%
TSTF-425, Rev. 3   Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b                           84%
TSTF-425, Rev. 3 Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b 84%
TSTF-511, Rev. 0   Eliminate Working Hour Restrictions from TS 5.2.2 to Support Compliance with 10 CFR Part 2             83%
TSTF-511, Rev. 0 Eliminate Working Hour Restrictions from TS 5.2.2 to Support Compliance with 10 CFR Part 2 83%
TSTF-510-A, Rev. 2 Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection                   80%
TSTF-510-A, Rev. 2 Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection 80%
TSTF-484, Rev. 0   Use of TS 3.10.1 for Scram Time Testing Activities.                                                     79%
TSTF-484, Rev. 0 Use of TS 3.10.1 for Scram Time Testing Activities.
TSTF-426, Rev. 5   Revise or Add Actions to Preclude Entry into LCO 3.0.3 - RITSTF Initiatives 6b & 6c                     71%
79%
TSTF-421, Rev. 0   Revision to RCP Flywheel Inspection Program (WCAP-15666)                                                 69%
TSTF-426, Rev. 5 Revise or Add Actions to Preclude Entry into LCO 3.0.3 - RITSTF Initiatives 6b & 6c 71%
TSTF-545, Rev. 3   TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing         69%
TSTF-421, Rev. 0 Revision to RCP Flywheel Inspection Program (WCAP-15666) 69%
TSTF-523-A, Rev. 2 Generic Letter 2008-01, Managing Gas Accumulation                                                       63%
TSTF-545, Rev. 3 TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing 69%
TSTF-372, Rev. 4   Addition of LCO 3.0.8, Inoperability of Snubbers                                                         60%
TSTF-523-A, Rev. 2 Generic Letter 2008-01, Managing Gas Accumulation 63%
TSTF-370, Rev. 0   Increase accumulator Completion Time from 1 hour to 24 hours (WCAP-15049)                               60%
TSTF-372, Rev. 4 Addition of LCO 3.0.8, Inoperability of Snubbers 60%
TSTF-522, Rev. 0   Revise Ventilation System Surveillance Requirements to Operate for 10 hours per Month                   59%
TSTF-370, Rev. 0 Increase accumulator Completion Time from 1 hour to 24 hours (WCAP-15049) 60%
TSTF-490, Rev. 0   Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec                           58%
TSTF-522, Rev. 0 Revise Ventilation System Surveillance Requirements to Operate for 10 hours per Month 59%
N/A               Elimination of Typical License Condition Requiring Reporting of Violations of Section 2.C               56%
TSTF-490, Rev. 0 Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec 58%
TSTF-476, Rev. 1   Improved BPWS Control Rod Insertion Process (NEDO-33091)                                                 54%
N/A Elimination of Typical License Condition Requiring Reporting of Violations of Section 2.C 56%
TSTF-477, Rev. 3   Add Action for Two Inoperable Control Room AC Subsystems                                                 50%
TSTF-476, Rev. 1 Improved BPWS Control Rod Insertion Process (NEDO-33091) 54%
TSTF-423, Rev. 1   Technical Specifications End States, NEDC-32988-A                                                       46%
TSTF-477, Rev. 3 Add Action for Two Inoperable Control Room AC Subsystems 50%
TSTF-514, Rev. 3   Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation                         46%
TSTF-423, Rev. 1 Technical Specifications End States, NEDC-32988-A 46%
TSTF-374, Rev. 0   Revision to TS 5.5.13 and associated TS Bases for Diesel Fuel Oil                                       45%
TSTF-514, Rev. 3 Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation 46%
TSTF-486, Rev. 2   Revise MTC Surveillance for Startup Test Activity Reduction (STAR) Program (WCAP-16011)                 43%
TSTF-374, Rev. 0 Revision to TS 5.5.13 and associated TS Bases for Diesel Fuel Oil 45%
TSTF-551, Rev. 3   Revise Secondary Containment Surveillance Requirements                                                   42%
TSTF-486, Rev. 2 Revise MTC Surveillance for Startup Test Activity Reduction (STAR) Program (WCAP-16011) 43%
TSTF-513, Rev. 3   Revise PWR Operability Requirements and Actions for RCS Leakage Instrumentation                         40%
TSTF-551, Rev. 3 Revise Secondary Containment Surveillance Requirements 42%
TSTF-529, Rev. 4   Clarify Use and Application Rules                                                                       38%
TSTF-513, Rev. 3 Revise PWR Operability Requirements and Actions for RCS Leakage Instrumentation 40%
TSTF-427, Rev. 2   Allowance for Non Technical Specification Barrier Degradation on Supported System OPERABIL             38%
TSTF-529, Rev. 4 Clarify Use and Application Rules 38%
TSTF-475, Rev. 1   Control Rod Notch Testing Frequency and SRM Insert Control Rod Action                                   38%
TSTF-427, Rev. 2 Allowance for Non Technical Specification Barrier Degradation on Supported System OPERABIL 38%
TSTF-491, Rev. 2   Removal of Main Steam and Main Feedwater Valve Isolation Times From Technical Specificatio             38%
TSTF-475, Rev. 1 Control Rod Notch Testing Frequency and SRM Insert Control Rod Action 38%
TSTF-422, Rev. 2   Change in Technical Specifications End States (CE NPSD-1186)                                             29%
TSTF-491, Rev. 2 Removal of Main Steam and Main Feedwater Valve Isolation Times From Technical Specificatio 38%
TSTF-487, Rev. 1   Relocate DNB Parameters to the COLR                                                                     29%
TSTF-422, Rev. 2 Change in Technical Specifications End States (CE NPSD-1186) 29%
TSTF-501, Rev. 1   Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control                                 28%
TSTF-487, Rev. 1 Relocate DNB Parameters to the COLR 29%
TSTF-547, Rev. 1   Clarification of Rod Position Requirements                                                               28%
TSTF-501, Rev. 1 Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control 28%
TSTF-412, Rev. 3   Provide Actions for One Steam Supply to Turbine Driven AFW/EFW Pump Inoperable                         26%
TSTF-547, Rev. 1 Clarification of Rod Position Requirements 28%
TSTF-430, Rev. 0   AOT Extension to 7 Days for LPI and Containment Spray (BAW-2295-A, Rev. 1)                               25%
TSTF-412, Rev. 3 Provide Actions for One Steam Supply to Turbine Driven AFW/EFW Pump Inoperable 26%
TSTF-431, Rev. 3   Change in Technical Specifications End States (BAW-2441)                                                 25%
TSTF-430, Rev. 0 AOT Extension to 7 Days for LPI and Containment Spray (BAW-2295-A, Rev. 1) 25%
TSTF-432, Rev.1   Change in Technical Specifications End States (WCAP-16294)                                               21%
TSTF-431, Rev. 3 Change in Technical Specifications End States (BAW-2441) 25%
TSTF-500-A, Rev. 2 DC Electrical Rewrite - Update to TSTF-360                                                               20%
TSTF-432, Rev.1 Change in Technical Specifications End States (WCAP-16294) 21%
TSTF-493, Rev. 4   Clarify Application of Setpoint Methodology for LSSS Functions                                         16%
TSTF-500-A, Rev. 2 DC Electrical Rewrite - Update to TSTF-360 20%
TSTF-478, Rev. 2   BWR Technical Specification Changes that Implement the Revised Rule for Combustible Gas Co             13%
TSTF-493, Rev. 4 Clarify Application of Setpoint Methodology for LSSS Functions 16%
TSTF-505-A, Rev. 1 Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b                                   9%
TSTF-478, Rev. 2 BWR Technical Specification Changes that Implement the Revised Rule for Combustible Gas Co 13%
TSTF-446, Rev. 3   Risk Informed Evaluation of Extensions to Containment Isolation Valve Completion Times (WCAP-15791)       7%
TSTF-505-A, Rev. 1 Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b 9%
TSTF-546, Rev. 0   Revise APRM Channel Adjustment Surveillance Requirement                                                   4%
TSTF-446, Rev. 3 Risk Informed Evaluation of Extensions to Containment Isolation Valve Completion Times (WCAP-15791) 7%
TSTF-409, Rev. 2   Containment Spray System Completion Time Extension (CE NPSD-1045-A)                                       0%
TSTF-546, Rev. 0 Revise APRM Channel Adjustment Surveillance Requirement 4%
TSTF-454, Rev. 1   Increase PCIV Completion Times from 4 hours, 24 hours, and 72 hours to 7 days (NEDC-33046)               0%
TSTF-409, Rev. 2 Containment Spray System Completion Time Extension (CE NPSD-1045-A) 0%
TSTF-498, Rev. 1   Risk-Informed Containment Isolation Valve Completion Times (BAW-2461)                                     0%
TSTF-454, Rev. 1 Increase PCIV Completion Times from 4 hours, 24 hours, and 72 hours to 7 days (NEDC-33046) 0%
TSTF-498, Rev. 1 Risk-Informed Containment Isolation Valve Completion Times (BAW-2461) 0%
Green Underline - Risk Informed Red Underline - NRC Initiated or Requirement
Green Underline - Risk Informed Red Underline - NRC Initiated or Requirement


Examination of Traveler Review Time 2016-2018 160 approved LARs to adopt travelers Average review time (Submittal to Approval): 308 days (< 10 months)
Examination of Traveler Review Time 2016-2018 Page 1 EXCEL Services Corporation 160 approved LARs to adopt travelers Average review time (Submittal to Approval): 308 days (< 10 months)
Excluding Vogtle TSTF-505 review (1,565 days)
Excluding Vogtle TSTF-505 review (1,565 days)
* 35 (22%) review time over 1 year (Average 480 days, 15.8 months)
* 35 (22%) review time over 1 year (Average 480 days, 15.8 months)
* 16 (10%) review over 13 months (Average 525 days, 17.25 months)
* 16 (10%) review over 13 months (Average 525 days, 17.25 months)
Traveler Adoption Review Time > 13 months Plant Name         TSTF Number       Approval       Submittal Review Date            Date      Time Hatch 1 & 2             TSTF-500-A,       08/29/17       08/11/15     749 Rev. 2 Cook 1 & 2               TSTF-490, Rev. 10/20/16           11/14/14     706 0
Traveler Adoption Review Time > 13 months Plant Name TSTF Number Approval Date Submittal Date Review Time Hatch 1 & 2 TSTF-500-A, Rev. 2 08/29/17 08/11/15 749 Cook 1 & 2 TSTF-490, Rev.
Perry                   TSTF-425, Rev. 02/23/16           03/25/14     700 3
0 10/20/16 11/14/14 706 Perry TSTF-425, Rev.
Columbia                 TSTF-425, Rev. 11/02/16           03/17/15     596 3
3 02/23/16 03/25/14 700 Columbia TSTF-425, Rev.
Susquehanna 1 & 2       TSTF-425, Rev. 05/20/16           10/26/14     572 3
3 11/02/16 03/17/15 596 Susquehanna 1 & 2 TSTF-425, Rev.
Columbia                 TSTF-423, Rev. 02/03/16           08/12/14     540 1
3 05/20/16 10/26/14 572 Columbia TSTF-423, Rev.
Brunswick 1 & 2         TSTF-425, Rev. 05/24/17           12/21/15     520 3
1 02/03/16 08/12/14 540 Brunswick 1 & 2 TSTF-425, Rev.
Fermi                   TSTF-545, Rev. 11/29/17           07/25/16     492 3
3 05/24/17 12/21/15 520 Fermi TSTF-545, Rev.
Cook 1 & 2               TSTF-425, Rev. 03/31/17           12/14/15     473 3
3 11/29/17 07/25/16 492 Cook 1 & 2 TSTF-425, Rev.
Harris                   TSTF-425, Rev. 11/29/16           08/18/15     469 3
3 03/31/17 12/14/15 473 Harris TSTF-425, Rev.
Hatch 1 & 2             TSTF-523-A,       04/16/16       01/13/15     459 Rev. 2 Watts Bar Unit 2         TSTF-547, Rev. 02/13/18           11/23/16     447 1
3 11/29/16 08/18/15 469 Hatch 1 & 2 TSTF-523-A, Rev. 2 04/16/16 01/13/15 459 Watts Bar Unit 2 TSTF-547, Rev.
Nine Mile Point 1       TSTF-425, Rev. 05/31/16           03/26/15     432 3
1 02/13/18 11/23/16 447 Nine Mile Point 1 TSTF-425, Rev.
Farley 1 & 2             TSTF-432,         06/10/16       04/13/15     424 Rev.1 Surry 1 & 2             TSTF-523-A,       02/29/16       01/14/15     411 Rev. 2 Waterford 3             TSTF-425, Rev. 07/26/16           06/17/15     405 3
3 05/31/16 03/26/15 432 Farley 1 & 2 TSTF-432, Rev.1 06/10/16 04/13/15 424 Surry 1 & 2 TSTF-523-A, Rev. 2 02/29/16 01/14/15 411 Waterford 3 TSTF-425, Rev.
Page 1              EXCEL Services Corporation
3 07/26/16 06/17/15 405  


Examination of Traveler Review Time 2016-2018 TSTF-425, 10 submittals, average of 493 days (16 months)
Examination of Traveler Review Time 2016-2018 Page 2 EXCEL Services Corporation TSTF-425, 10 submittals, average of 493 days (16 months)
TSTF-425 Review Time vs. Approval Date 800 700 600 500 400 300 200 100 0
Examining the three TSTF-425 approvals in 2017:
Examining the three TSTF-425 approvals in 2017:
* Brunswick submitted 3 supplements and 5 RAI responses
* Brunswick submitted 3 supplements and 5 RAI responses
* D.C. Cook submitted 2 supplements and 4 RAI responses
* D.C. Cook submitted 2 supplements and 4 RAI responses
* Cooper had no supplements and one RAI response Page 2            EXCEL Services Corporation}}
* Cooper had no supplements and one RAI response 0
100 200 300 400 500 600 700 800 TSTF-425 Review Time vs. Approval Date}}

Latest revision as of 20:45, 5 January 2025

May 17, 2018, Meeting Agenda Item 3.A - Traveler Adoption
ML18142B034
Person / Time
Site: Technical Specifications Task Force
Issue date: 05/17/2018
From:
Technical Specifications Task Force
To:
Office of Nuclear Reactor Regulation
Honcharik M
Shared Package
ML18142B058 List:
References
Download: ML18142B034 (3)


Text

TSTF Number TSTF Title Adoption (Approvals Submittals TSTF-358, Rev. 6 Missed Surveillance Requirements 100%

TSTF-369, Rev. 1 Removal of Monthly Operating Report and Occupational Radiation Exposure Report 100%

TSTF-413, Rev. 0 Elimination of Requirements for a Post Accident Sampling System (PASS) (NEDO-3299) 100%

TSTF-442, Rev. 0 Elimination of Requirements for a Post Accident Sampling System (PASS) 100%

TSTF-449, Rev. 4 Steam Generator Tube Integrity 100%

TSTF-479, Rev, 0 Changes to Reflect Revision of 10CFR50.55a 100%

TSTF-497, Rev, 0 Limit Inservice Testing Program SR 3.0.2 Application to Frequencies of 2 Years or Less 100%

TSTF-448, Rev. 3 Control Room Habitability 98%

TSTF-366, Rev. 0 Elimination of Requirements for a Post Accident Sampling System (PASS) 97%

TSTF-447, Rev. 1 Elimination of Hydrogen Recombiners and Change to Hydrogen and Oxygen Monitors 97%

TSTF-535, Rev. 0 Revise Shutdown Margin Definition to Address Advanced Fuel Designs 92%

TSTF-404, Rev. 0 SDV Actions 92%

TSTF-460, Rev. 0 Control Rod Scram Time Testing Frequency 88%

TSTF-542,Rev. 2 Reactor Pressure Vessel Water Inventory Control 88%

TSTF-359, Rev. 9 Increase Flexibility in MODE Restraints 84%

TSTF-425, Rev. 3 Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b 84%

TSTF-511, Rev. 0 Eliminate Working Hour Restrictions from TS 5.2.2 to Support Compliance with 10 CFR Part 2 83%

TSTF-510-A, Rev. 2 Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection 80%

TSTF-484, Rev. 0 Use of TS 3.10.1 for Scram Time Testing Activities.

79%

TSTF-426, Rev. 5 Revise or Add Actions to Preclude Entry into LCO 3.0.3 - RITSTF Initiatives 6b & 6c 71%

TSTF-421, Rev. 0 Revision to RCP Flywheel Inspection Program (WCAP-15666) 69%

TSTF-545, Rev. 3 TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing 69%

TSTF-523-A, Rev. 2 Generic Letter 2008-01, Managing Gas Accumulation 63%

TSTF-372, Rev. 4 Addition of LCO 3.0.8, Inoperability of Snubbers 60%

TSTF-370, Rev. 0 Increase accumulator Completion Time from 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> (WCAP-15049) 60%

TSTF-522, Rev. 0 Revise Ventilation System Surveillance Requirements to Operate for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> per Month 59%

TSTF-490, Rev. 0 Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec 58%

N/A Elimination of Typical License Condition Requiring Reporting of Violations of Section 2.C 56%

TSTF-476, Rev. 1 Improved BPWS Control Rod Insertion Process (NEDO-33091) 54%

TSTF-477, Rev. 3 Add Action for Two Inoperable Control Room AC Subsystems 50%

TSTF-423, Rev. 1 Technical Specifications End States, NEDC-32988-A 46%

TSTF-514, Rev. 3 Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation 46%

TSTF-374, Rev. 0 Revision to TS 5.5.13 and associated TS Bases for Diesel Fuel Oil 45%

TSTF-486, Rev. 2 Revise MTC Surveillance for Startup Test Activity Reduction (STAR) Program (WCAP-16011) 43%

TSTF-551, Rev. 3 Revise Secondary Containment Surveillance Requirements 42%

TSTF-513, Rev. 3 Revise PWR Operability Requirements and Actions for RCS Leakage Instrumentation 40%

TSTF-529, Rev. 4 Clarify Use and Application Rules 38%

TSTF-427, Rev. 2 Allowance for Non Technical Specification Barrier Degradation on Supported System OPERABIL 38%

TSTF-475, Rev. 1 Control Rod Notch Testing Frequency and SRM Insert Control Rod Action 38%

TSTF-491, Rev. 2 Removal of Main Steam and Main Feedwater Valve Isolation Times From Technical Specificatio 38%

TSTF-422, Rev. 2 Change in Technical Specifications End States (CE NPSD-1186) 29%

TSTF-487, Rev. 1 Relocate DNB Parameters to the COLR 29%

TSTF-501, Rev. 1 Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control 28%

TSTF-547, Rev. 1 Clarification of Rod Position Requirements 28%

TSTF-412, Rev. 3 Provide Actions for One Steam Supply to Turbine Driven AFW/EFW Pump Inoperable 26%

TSTF-430, Rev. 0 AOT Extension to 7 Days for LPI and Containment Spray (BAW-2295-A, Rev. 1) 25%

TSTF-431, Rev. 3 Change in Technical Specifications End States (BAW-2441) 25%

TSTF-432, Rev.1 Change in Technical Specifications End States (WCAP-16294) 21%

TSTF-500-A, Rev. 2 DC Electrical Rewrite - Update to TSTF-360 20%

TSTF-493, Rev. 4 Clarify Application of Setpoint Methodology for LSSS Functions 16%

TSTF-478, Rev. 2 BWR Technical Specification Changes that Implement the Revised Rule for Combustible Gas Co 13%

TSTF-505-A, Rev. 1 Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b 9%

TSTF-446, Rev. 3 Risk Informed Evaluation of Extensions to Containment Isolation Valve Completion Times (WCAP-15791) 7%

TSTF-546, Rev. 0 Revise APRM Channel Adjustment Surveillance Requirement 4%

TSTF-409, Rev. 2 Containment Spray System Completion Time Extension (CE NPSD-1045-A) 0%

TSTF-454, Rev. 1 Increase PCIV Completion Times from 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, and 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 7 days (NEDC-33046) 0%

TSTF-498, Rev. 1 Risk-Informed Containment Isolation Valve Completion Times (BAW-2461) 0%

Green Underline - Risk Informed Red Underline - NRC Initiated or Requirement

Examination of Traveler Review Time 2016-2018 Page 1 EXCEL Services Corporation 160 approved LARs to adopt travelers Average review time (Submittal to Approval): 308 days (< 10 months)

Excluding Vogtle TSTF-505 review (1,565 days)

  • 35 (22%) review time over 1 year (Average 480 days, 15.8 months)
  • 16 (10%) review over 13 months (Average 525 days, 17.25 months)

Traveler Adoption Review Time > 13 months Plant Name TSTF Number Approval Date Submittal Date Review Time Hatch 1 & 2 TSTF-500-A, Rev. 2 08/29/17 08/11/15 749 Cook 1 & 2 TSTF-490, Rev.

0 10/20/16 11/14/14 706 Perry TSTF-425, Rev.

3 02/23/16 03/25/14 700 Columbia TSTF-425, Rev.

3 11/02/16 03/17/15 596 Susquehanna 1 & 2 TSTF-425, Rev.

3 05/20/16 10/26/14 572 Columbia TSTF-423, Rev.

1 02/03/16 08/12/14 540 Brunswick 1 & 2 TSTF-425, Rev.

3 05/24/17 12/21/15 520 Fermi TSTF-545, Rev.

3 11/29/17 07/25/16 492 Cook 1 & 2 TSTF-425, Rev.

3 03/31/17 12/14/15 473 Harris TSTF-425, Rev.

3 11/29/16 08/18/15 469 Hatch 1 & 2 TSTF-523-A, Rev. 2 04/16/16 01/13/15 459 Watts Bar Unit 2 TSTF-547, Rev.

1 02/13/18 11/23/16 447 Nine Mile Point 1 TSTF-425, Rev.

3 05/31/16 03/26/15 432 Farley 1 & 2 TSTF-432, Rev.1 06/10/16 04/13/15 424 Surry 1 & 2 TSTF-523-A, Rev. 2 02/29/16 01/14/15 411 Waterford 3 TSTF-425, Rev.

3 07/26/16 06/17/15 405

Examination of Traveler Review Time 2016-2018 Page 2 EXCEL Services Corporation TSTF-425, 10 submittals, average of 493 days (16 months)

Examining the three TSTF-425 approvals in 2017:

  • Brunswick submitted 3 supplements and 5 RAI responses
  • D.C. Cook submitted 2 supplements and 4 RAI responses
  • Cooper had no supplements and one RAI response 0

100 200 300 400 500 600 700 800 TSTF-425 Review Time vs. Approval Date