ML14234A085: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:0 L-2014-25710 CFR 50.54(f)FPL. August 7, 2014U.S. Nuclear Regulatory CommissionAttn: Document Control DeskWashington, DC 20555-0001Re: Turkey Point Units 3 and 4Docket Nos. 50-250 and 50-251Renewed Facility Operating License Nos. DPR-31 and DPR-41
{{#Wiki_filter:0 L-2014-257 10 CFR 50.54(f)FPL. August 7, 2014U.S. Nuclear Regulatory Commission Attn: Document Control DeskWashington, DC 20555-0001 Re: Turkey Point Units 3 and 4Docket Nos. 50-250 and 50-251Renewed Facility Operating License Nos. DPR-31 and DPR-41


==Subject:==
==Subject:==
Supplemental Information Regarding the Flood Hazard Reevaluation
Supplemental Information Regarding the Flood Hazard Reevaluation


==References:==
==References:==
: 1. NRC Letter, "Request for Information Pursuant to Title 10 of the Code of FederalRegulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident," datedMarch 12, 2012, ML12073A348.2. NRC Letter, "Prioritization of Response Due Dates for Request for InformationPursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding FloodingHazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Reviewof Insights from the Fukushima Dai-ichi Accident," dated May 11, 2012,ML12097A509.3. Florida Power & Light Company Letter L-2013-087, "Response to NRC Request forInformation Pursuant to 10 CFR 5 0.54(f) Regarding the Flood Hazard Reevaluationof Recommendation 2.1," dated March 11, 2013.On March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued Reference 1to all power reactor licensees and holders of construction permits in active or deferredstatus, Enclosure 2 of Reference 1 contains specific Requested Actions, RequestedInformation and Required Responses associated with Recommendation 2.1 for FloodingHazard Reevaluation. Item 1 of the Requested Information asks for a Flood HazardReevaluation Report. In accordance with Reference 2, Florida Power & Light Company(FPL) submitted a Flood Hazard Reevaluation Report for Turkey Point Units 3 and 4 inReference 3.The purpose of this letter is to provide supplemental information regarding the FloodHazard Reevaluation Report. One of the reevaluated hazards is the hurricane stormsurge. As part of the flooding hazard reevaluation for the Integrated Assessment Report, A o)[Florida Power & Light Company9760 SW 344' Street, Florida City, FL 33035 LUL Florida Power & Light Company L-2014-257Flooding Hazard Reevaluation Supplemental InformationEnclosure Page 2 of 2new storm surge level and new wave run-up levels were determined for the storm surgehazard. Additionally, the wave run-up, which was previously evaluated only for the eastside of the power block, needs to be re-evaluated on all sides.This condition is captured in the Turkey Point Corrective Action Program. The newstorm and wave run-up levels were compared to the current licensing bases and it wasdetermined the flooding protection features were adequate to withstand the new stormand wave run up levels at the present time. This condition will be evaluated in theIntegrated Assessment for long term effects.This supplemental information was discussed with the NRC Staff on July 29, 2014.Based on the NRC/FPL discussion and because this condition will be addressed in theIntegrated Assessment Report no updates are needed at this time to the Flood HazardReevaluation Report. The Integrated Assessment Report will be submitted to the NRC asrequested in Item 2 of Enclosure 2 of Reference I prior to March 12, 2015 as provided inReference 3.This letter contains no new regulatory commitments.Should you have any questions concerning the content of this letter, please contact RobertJ. Tomonto, Licensing Manager, at (305) 746-7327.I declare under penalty of perjury that the foregoing is true and correct.Executed on August 7" , 2014.Sincerely,Michael KileyVice PresidentTurkey Point Nuclear Plant
: 1. NRC Letter, "Request for Information Pursuant to Title 10 of the Code of FederalRegulations 50.54(f)
Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident,"
datedMarch 12, 2012, ML12073A348.
: 2. NRC Letter, "Prioritization of Response Due Dates for Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f)
Regarding FloodingHazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Reviewof Insights from the Fukushima Dai-ichi Accident,"
dated May 11, 2012,ML12097A509.
: 3. Florida Power & Light Company Letter L-2013-087, "Response to NRC Request forInformation Pursuant to 10 CFR 5 0.54(f) Regarding the Flood Hazard Reevaluation of Recommendation 2.1," dated March 11, 2013.On March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued Reference 1to all power reactor licensees and holders of construction permits in active or deferredstatus, Enclosure 2 of Reference 1 contains specific Requested  
: Actions, Requested Information and Required Responses associated with Recommendation 2.1 for FloodingHazard Reevaluation.
Item 1 of the Requested Information asks for a Flood HazardReevaluation Report. In accordance with Reference 2, Florida Power & Light Company(FPL) submitted a Flood Hazard Reevaluation Report for Turkey Point Units 3 and 4 inReference 3.The purpose of this letter is to provide supplemental information regarding the FloodHazard Reevaluation Report. One of the reevaluated hazards is the hurricane stormsurge. As part of the flooding hazard reevaluation for the Integrated Assessment Report, A o)[Florida Power & Light Company9760 SW 344' Street, Florida City, FL 33035 LUL Florida Power & Light Company L-2014-257 Flooding Hazard Reevaluation Supplemental Information Enclosure Page 2 of 2new storm surge level and new wave run-up levels were determined for the storm surgehazard. Additionally, the wave run-up, which was previously evaluated only for the eastside of the power block, needs to be re-evaluated on all sides.This condition is captured in the Turkey Point Corrective Action Program.
The newstorm and wave run-up levels were compared to the current licensing bases and it wasdetermined the flooding protection features were adequate to withstand the new stormand wave run up levels at the present time. This condition will be evaluated in theIntegrated Assessment for long term effects.This supplemental information was discussed with the NRC Staff on July 29, 2014.Based on the NRC/FPL discussion and because this condition will be addressed in theIntegrated Assessment Report no updates are needed at this time to the Flood HazardReevaluation Report. The Integrated Assessment Report will be submitted to the NRC asrequested in Item 2 of Enclosure 2 of Reference I prior to March 12, 2015 as provided inReference 3.This letter contains no new regulatory commitments.
Should you have any questions concerning the content of this letter, please contact RobertJ. Tomonto, Licensing  
: Manager, at (305) 746-7327.
I declare under penalty of perjury that the foregoing is true and correct.Executed on August 7" , 2014.Sincerely, Michael KileyVice President Turkey Point Nuclear Plant


==Enclosure:==
==Enclosure:==
Supplement to Flooding Hazard Reevaluation Reportcc: USNRC Regional Administrator, Region II,USNRC Senior Resident Inspector Turkey PointUSNRC Project Manager for Turkey Point Florida Power & Light Company L-2014-257Flooding Hazard Reevaluation Supplemental InformationEnclosure Page 1 of 2Flooding Hazard ReevaluationSupplemental InformationEnclosureBackgroundNRC directives associated with the Fukushima Dai-ichi accident require that each site bereevaluated for certain natural hazards. Among these are flooding hazards that could impact safeoperation and shutdown of the units.A flooding hazard reevaluation report (FHRR) was completed in March 2013 and submitted tothe NRC to comply with the directive. One of the hazards that were reevaluated was hurricanestorm surge. A new storm surge level was determined as part of the reevaluation, and new waverun-up levels associated with the surge were also determined. These new storm surge levels andwave run-up were compared to the current licensing basis (CLB), and it was determined thatalthough margin had been lost, the flooding protection features were adequate to withstand thenew levels.The next step in the flooding hazard reevaluation, as prescribed by the NRC directive, is toperform an integrated assessment of flooding effects when the new hazard exceeds the CLB. Inthe process of performing this evaluation, it was determined that the wave run-up hazard that wasonly evaluated for the east side of the power block, similar to the CLB, needs to be considered allaround. A Condition Report was initiated in the Corrective Action Program to identify thediscrepancy and evaluate any interim measures needed until the integrated assessment iscompleted.Technical DiscussionThe FHRR determined that the existing eastern power-block flood barriers provide a margin of0.6 ft when considering the new hurricane storm surge, associated wave run-up, and sea levelrise. When the wave run-up is applied to the northern and southern power-block flood protectionwalls during the probable maximum storm surge (PMSS) there is a potential for the waves toovertop the barriers towards the end of plant life.The PMSS level presented in the FHRR includes a future, 20-year sea level rise component of0.4 feet, which does not characterize the present hazard. When future sea level rise is removedfrom the wave run-up calculation, a margin exists on the east, north, west, and south floodprotection walls. The margin on the east flood protection wall is 1.0 feet. The margin on thewest flood protection wall is 0.7 feet. The margin on the south flood protection wall is 0.2 feetwhile the margin on the north flood protection wall is 0.1 feet.However, when sea level rise is included, there is a potential overtopping on the north and southflood protection walls by 0.3 and 0.2 feet respectively. The overtopping would only occur Florida Power & Light CompanyFlooding Hazard Reevaluation Supplemental InformationEnclosureL-2014-257Page 2 of 2during the peak of the storm; for most of the event, the south flood protection wall would not beovertopped.Based on the above, no immediate actions are needed to address this hazard; however, thiscondition will need to be addressed in the long term.Immediate Actions TakenNone RequiredRecommended ActionsThe integrated assessment will document this condition and present options to address it. Thesemay include recommendations to monitor potential margin loss on the flood protection wallsthrough annual analysis of regional sea level rise and walkdowns of barrier walls or installationof protection features for the wave run-up hazard.}}
 
Supplement to Flooding Hazard Reevaluation Reportcc: USNRC Regional Administrator, Region II,USNRC Senior Resident Inspector Turkey PointUSNRC Project Manager for Turkey Point Florida Power & Light Company L-2014-257 Flooding Hazard Reevaluation Supplemental Information Enclosure Page 1 of 2Flooding Hazard Reevaluation Supplemental Information Enclosure
 
===Background===
NRC directives associated with the Fukushima Dai-ichi accident require that each site bereevaluated for certain natural hazards.
Among these are flooding hazards that could impact safeoperation and shutdown of the units.A flooding hazard reevaluation report (FHRR) was completed in March 2013 and submitted tothe NRC to comply with the directive.
One of the hazards that were reevaluated was hurricane storm surge. A new storm surge level was determined as part of the reevaluation, and new waverun-up levels associated with the surge were also determined.
These new storm surge levels andwave run-up were compared to the current licensing basis (CLB), and it was determined thatalthough margin had been lost, the flooding protection features were adequate to withstand thenew levels.The next step in the flooding hazard reevaluation, as prescribed by the NRC directive, is toperform an integrated assessment of flooding effects when the new hazard exceeds the CLB. Inthe process of performing this evaluation, it was determined that the wave run-up hazard that wasonly evaluated for the east side of the power block, similar to the CLB, needs to be considered allaround. A Condition Report was initiated in the Corrective Action Program to identify thediscrepancy and evaluate any interim measures needed until the integrated assessment iscompleted.
Technical Discussion The FHRR determined that the existing eastern power-block flood barriers provide a margin of0.6 ft when considering the new hurricane storm surge, associated wave run-up, and sea levelrise. When the wave run-up is applied to the northern and southern power-block flood protection walls during the probable maximum storm surge (PMSS) there is a potential for the waves toovertop the barriers towards the end of plant life.The PMSS level presented in the FHRR includes a future, 20-year sea level rise component of0.4 feet, which does not characterize the present hazard. When future sea level rise is removedfrom the wave run-up calculation, a margin exists on the east, north, west, and south floodprotection walls. The margin on the east flood protection wall is 1.0 feet. The margin on thewest flood protection wall is 0.7 feet. The margin on the south flood protection wall is 0.2 feetwhile the margin on the north flood protection wall is 0.1 feet.However, when sea level rise is included, there is a potential overtopping on the north and southflood protection walls by 0.3 and 0.2 feet respectively.
The overtopping would only occur Florida Power & Light CompanyFlooding Hazard Reevaluation Supplemental Information Enclosure L-2014-257 Page 2 of 2during the peak of the storm; for most of the event, the south flood protection wall would not beovertopped.
Based on the above, no immediate actions are needed to address this hazard; however, thiscondition will need to be addressed in the long term.Immediate Actions TakenNone RequiredRecommended ActionsThe integrated assessment will document this condition and present options to address it. Thesemay include recommendations to monitor potential margin loss on the flood protection wallsthrough annual analysis of regional sea level rise and walkdowns of barrier walls or installation of protection features for the wave run-up hazard.}}

Revision as of 11:47, 1 July 2018

Turkey Point, Units 3 and 4, Supplemental Information Regarding the Flood Hazard Reevaluation
ML14234A085
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 08/07/2014
From: Kiley M
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-2014-257
Download: ML14234A085 (4)


Text

0 L-2014-257 10 CFR 50.54(f)FPL. August 7, 2014U.S. Nuclear Regulatory Commission Attn: Document Control DeskWashington, DC 20555-0001 Re: Turkey Point Units 3 and 4Docket Nos. 50-250 and 50-251Renewed Facility Operating License Nos. DPR-31 and DPR-41

Subject:

Supplemental Information Regarding the Flood Hazard Reevaluation

References:

1. NRC Letter, "Request for Information Pursuant to Title 10 of the Code of FederalRegulations 50.54(f)

Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident,"

datedMarch 12, 2012, ML12073A348.

2. NRC Letter, "Prioritization of Response Due Dates for Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f)

Regarding FloodingHazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Reviewof Insights from the Fukushima Dai-ichi Accident,"

dated May 11, 2012,ML12097A509.

3. Florida Power & Light Company Letter L-2013-087, "Response to NRC Request forInformation Pursuant to 10 CFR 5 0.54(f) Regarding the Flood Hazard Reevaluation of Recommendation 2.1," dated March 11, 2013.On March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued Reference 1to all power reactor licensees and holders of construction permits in active or deferredstatus, Enclosure 2 of Reference 1 contains specific Requested
Actions, Requested Information and Required Responses associated with Recommendation 2.1 for FloodingHazard Reevaluation.

Item 1 of the Requested Information asks for a Flood HazardReevaluation Report. In accordance with Reference 2, Florida Power & Light Company(FPL) submitted a Flood Hazard Reevaluation Report for Turkey Point Units 3 and 4 inReference 3.The purpose of this letter is to provide supplemental information regarding the FloodHazard Reevaluation Report. One of the reevaluated hazards is the hurricane stormsurge. As part of the flooding hazard reevaluation for the Integrated Assessment Report, A o)[Florida Power & Light Company9760 SW 344' Street, Florida City, FL 33035 LUL Florida Power & Light Company L-2014-257 Flooding Hazard Reevaluation Supplemental Information Enclosure Page 2 of 2new storm surge level and new wave run-up levels were determined for the storm surgehazard. Additionally, the wave run-up, which was previously evaluated only for the eastside of the power block, needs to be re-evaluated on all sides.This condition is captured in the Turkey Point Corrective Action Program.

The newstorm and wave run-up levels were compared to the current licensing bases and it wasdetermined the flooding protection features were adequate to withstand the new stormand wave run up levels at the present time. This condition will be evaluated in theIntegrated Assessment for long term effects.This supplemental information was discussed with the NRC Staff on July 29, 2014.Based on the NRC/FPL discussion and because this condition will be addressed in theIntegrated Assessment Report no updates are needed at this time to the Flood HazardReevaluation Report. The Integrated Assessment Report will be submitted to the NRC asrequested in Item 2 of Enclosure 2 of Reference I prior to March 12, 2015 as provided inReference 3.This letter contains no new regulatory commitments.

Should you have any questions concerning the content of this letter, please contact RobertJ. Tomonto, Licensing

Manager, at (305) 746-7327.

I declare under penalty of perjury that the foregoing is true and correct.Executed on August 7" , 2014.Sincerely, Michael KileyVice President Turkey Point Nuclear Plant

Enclosure:

Supplement to Flooding Hazard Reevaluation Reportcc: USNRC Regional Administrator, Region II,USNRC Senior Resident Inspector Turkey PointUSNRC Project Manager for Turkey Point Florida Power & Light Company L-2014-257 Flooding Hazard Reevaluation Supplemental Information Enclosure Page 1 of 2Flooding Hazard Reevaluation Supplemental Information Enclosure

Background

NRC directives associated with the Fukushima Dai-ichi accident require that each site bereevaluated for certain natural hazards.

Among these are flooding hazards that could impact safeoperation and shutdown of the units.A flooding hazard reevaluation report (FHRR) was completed in March 2013 and submitted tothe NRC to comply with the directive.

One of the hazards that were reevaluated was hurricane storm surge. A new storm surge level was determined as part of the reevaluation, and new waverun-up levels associated with the surge were also determined.

These new storm surge levels andwave run-up were compared to the current licensing basis (CLB), and it was determined thatalthough margin had been lost, the flooding protection features were adequate to withstand thenew levels.The next step in the flooding hazard reevaluation, as prescribed by the NRC directive, is toperform an integrated assessment of flooding effects when the new hazard exceeds the CLB. Inthe process of performing this evaluation, it was determined that the wave run-up hazard that wasonly evaluated for the east side of the power block, similar to the CLB, needs to be considered allaround. A Condition Report was initiated in the Corrective Action Program to identify thediscrepancy and evaluate any interim measures needed until the integrated assessment iscompleted.

Technical Discussion The FHRR determined that the existing eastern power-block flood barriers provide a margin of0.6 ft when considering the new hurricane storm surge, associated wave run-up, and sea levelrise. When the wave run-up is applied to the northern and southern power-block flood protection walls during the probable maximum storm surge (PMSS) there is a potential for the waves toovertop the barriers towards the end of plant life.The PMSS level presented in the FHRR includes a future, 20-year sea level rise component of0.4 feet, which does not characterize the present hazard. When future sea level rise is removedfrom the wave run-up calculation, a margin exists on the east, north, west, and south floodprotection walls. The margin on the east flood protection wall is 1.0 feet. The margin on thewest flood protection wall is 0.7 feet. The margin on the south flood protection wall is 0.2 feetwhile the margin on the north flood protection wall is 0.1 feet.However, when sea level rise is included, there is a potential overtopping on the north and southflood protection walls by 0.3 and 0.2 feet respectively.

The overtopping would only occur Florida Power & Light CompanyFlooding Hazard Reevaluation Supplemental Information Enclosure L-2014-257 Page 2 of 2during the peak of the storm; for most of the event, the south flood protection wall would not beovertopped.

Based on the above, no immediate actions are needed to address this hazard; however, thiscondition will need to be addressed in the long term.Immediate Actions TakenNone RequiredRecommended ActionsThe integrated assessment will document this condition and present options to address it. Thesemay include recommendations to monitor potential margin loss on the flood protection wallsthrough annual analysis of regional sea level rise and walkdowns of barrier walls or installation of protection features for the wave run-up hazard.