ML14356A583: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (2 intermediate revisions by the same user not shown) | |||
| Line 2: | Line 2: | ||
| number = ML14356A583 | | number = ML14356A583 | ||
| issue date = 11/24/2014 | | issue date = 11/24/2014 | ||
| title = | | title = NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) | ||
| author name = Silk D | | author name = Silk D | ||
| author affiliation = NRC/RGN-I/DRS/OB | | author affiliation = NRC/RGN-I/DRS/OB | ||
| Line 20: | Line 20: | ||
=Text= | =Text= | ||
{{#Wiki_filter:Salem Op Test Comments Job Performance Measures: | {{#Wiki_filter:Salem Op Test Comments Job Performance Measures: | ||
Sima: Update cover page-this is not an alternate path JPM. Sim b: No comment. Sim c: Change to put 21 charging pump in service instead of PDP for set up. Sim d: No comment. Sim e: JPM step 12 is not critical. | Sima: Update cover page-this is not an alternate path JPM. | ||
Remove T-hot from initial conditions. | Sim b: No comment. | ||
Add cue to elicit C/D rate and observe applicant response to adjust C/D rate. Sim f: Update cover page-this is not an alternate path JPM. Sim g: Modify simulator set up regarding procedure IOP-3. Sim h: No comment. IP i: At JPM step 5.9.4 clarify droop switch position. | Sim c: Change to put 21 charging pump in service instead of PDP for set up. | ||
IP j: Clarify how to remove key from lock. IP k: At step 5.5.4 specify what is being used. At steps 5.5.5 & 5.5.6 specify the location of the valves. RO Admin A 1-1: Conduct in classroom instead of simulator. | Sim d: No comment. | ||
Clarify cues to focus applicant actions. Correct number of minutes (1 010 vs 1000) or start time to equal 1000 minutes. RO Admin A 1-2: No comment. RO Admin A2: Delete last line of initiating cue. Enhance answer key due to possible multiple isolation points. RO Admin A4: Add set up info for simulator operator. | Sim e: JPM step 12 is not critical. Remove T-hot from initial conditions. Add cue to elicit C/D rate and observe applicant response to adjust C/D rate. | ||
SRO Admin A1-1: Fix cue sheet to match cover page initial conditions. | Sim f: Update cover page-this is not an alternate path JPM. | ||
Add trend data to support conservative decision on application of table. SRO Admin A 1-2: No comment. SRO Admin A2: Provide optional tagging point in JPM step 2. SRO Admin A3: No comment. SRO Admin A4: No comment. | Sim g: Modify simulator set up regarding procedure IOP-3. | ||
Scenarios ESG-1: Modify the expected dilution for the reactivity plan. ESG-2: Correct 21 B vs 23 BOOS in initial conditions. | Sim h: No comment. | ||
Explain Note on Form ES-D-1 about CTs in parentheses. | IP i: At JPM step 5.9.4 clarify droop switch position. | ||
Make this the spare. ESG-3: No comment. ESG-4: Add TS to event 4. ESG-5: Replace event 7 (LOOP) with RCP 'C' tripping. | IP j: Clarify how to remove key from lock. | ||
IP k: At step 5.5.4 specify what ~1auge is being used. At steps 5.5.5 & 5.5.6 specify the location of the valves. | |||
RO Admin A 1-1: Conduct in classroom instead of simulator. Clarify cues to focus applicant actions. Correct number of minutes (1 010 vs 1000) or start time to equal 1000 minutes. | |||
RO Admin A 1-2: No comment. | |||
RO Admin A2: Delete last line of initiating cue. Enhance answer key due to possible multiple isolation points. | |||
RO Admin A4: Add set up info for simulator operator. | |||
SRO Admin A1-1: Fix cue sheet to match cover page initial conditions. Add trend data to support conservative decision on application of table. | |||
SRO Admin A 1-2: No comment. | |||
SRO Admin A2: Provide optional tagging point in JPM step 2. | |||
SRO Admin A3: No comment. | |||
SRO Admin A4: No comment. | |||
Scenarios ESG-1: Modify the expected dilution for the reactivity plan. | |||
ESG-2: Correct 21 B vs 23 BOOS in initial conditions. Explain Note on Form ES-D-1 about CTs in parentheses. Make this the spare. | |||
ESG-3: No comment. | |||
ESG-4: Add TS to event 4. | |||
ESG-5: Replace event 7 (LOOP) with RCP 'C' tripping. | |||
Salem Op Test Comments Job Performance Measures: | Salem Op Test Comments Job Performance Measures: | ||
Sima: Update cover page-this is not an alternate path JPM. Sim b: No comment. Sim c: Change to put 21 charging pump in service instead of PDP for set up. Sim d: No comment. Sim e: JPM step 12 is not critical. | Sima: Update cover page-this is not an alternate path JPM. | ||
Remove T-hot from initial conditions. | Sim b: No comment. | ||
Add cue to elicit C/D rate and observe applicant response to adjust C/D rate. Sim f: Update cover page-this is not an alternate path JPM. Sim g: Modify simulator set up regarding procedure IOP-3. Sim h: No comment. IP i: At JPM step 5.9.4 clarify droop switch position. | Sim c: Change to put 21 charging pump in service instead of PDP for set up. | ||
IP j: Clarify how to remove key from lock. IP k: At step 5.5.4 specify what is being used. At steps 5.5.5 & 5.5.6 specify the location of the valves. RO Admin A 1-1: Conduct in classroom instead of simulator. | Sim d: No comment. | ||
Clarify cues to focus applicant actions. Correct number of minutes (1 010 vs 1000) or start time to equal 1000 minutes. RO Admin A 1-2: No comment. RO Admin A2: Delete last line of initiating cue. Enhance answer key due to possible multiple isolation points. RO Admin A4: Add set up info for simulator operator. | Sim e: JPM step 12 is not critical. Remove T-hot from initial conditions. Add cue to elicit C/D rate and observe applicant response to adjust C/D rate. | ||
SRO Admin A1-1: Fix cue sheet to match cover page initial conditions. | Sim f: Update cover page-this is not an alternate path JPM. | ||
Add trend data to support conservative decision on application of table. SRO Admin A 1-2: No comment. SRO Admin A2: Provide optional tagging point in JPM step 2. SRO Admin A3: No comment. SRO Admin A4: No comment. | Sim g: Modify simulator set up regarding procedure IOP-3. | ||
Scenarios ESG-1: Modify the expected dilution for the reactivity plan. ESG-2: Correct 21 B vs 23 BOOS in initial conditions. | Sim h: No comment. | ||
Explain Note on Form ES-D-1 about CTs in parentheses. | IP i: At JPM step 5.9.4 clarify droop switch position. | ||
Make this the spare. ESG-3: No comment. ESG-4: Add TS to event 4. ESG-5: Replace event 7 (LOOP) with RCP 'C' tripping.}} | IP j: Clarify how to remove key from lock. | ||
IP k: At step 5.5.4 specify what ~1auge is being used. At steps 5.5.5 & 5.5.6 specify the location of the valves. | |||
RO Admin A 1-1: Conduct in classroom instead of simulator. Clarify cues to focus applicant actions. Correct number of minutes (1 010 vs 1000) or start time to equal 1000 minutes. | |||
RO Admin A 1-2: No comment. | |||
RO Admin A2: Delete last line of initiating cue. Enhance answer key due to possible multiple isolation points. | |||
RO Admin A4: Add set up info for simulator operator. | |||
SRO Admin A1-1: Fix cue sheet to match cover page initial conditions. Add trend data to support conservative decision on application of table. | |||
SRO Admin A 1-2: No comment. | |||
SRO Admin A2: Provide optional tagging point in JPM step 2. | |||
SRO Admin A3: No comment. | |||
SRO Admin A4: No comment. | |||
Scenarios ESG-1: Modify the expected dilution for the reactivity plan. | |||
ESG-2: Correct 21 B vs 23 BOOS in initial conditions. Explain Note on Form ES-D-1 about CTs in parentheses. Make this the spare. | |||
ESG-3: No comment. | |||
ESG-4: Add TS to event 4. | |||
ESG-5: Replace event 7 (LOOP) with RCP 'C' tripping.}} | |||
Latest revision as of 15:18, 10 January 2025
| ML14356A583 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 11/24/2014 |
| From: | David Silk Operations Branch I |
| To: | Public Service Enterprise Group |
| Shared Package | |
| ML14174B408 | List: |
| References | |
| TAC U01894 | |
| Download: ML14356A583 (2) | |
Text
Salem Op Test Comments Job Performance Measures:
Sima: Update cover page-this is not an alternate path JPM.
Sim b: No comment.
Sim c: Change to put 21 charging pump in service instead of PDP for set up.
Sim d: No comment.
Sim e: JPM step 12 is not critical. Remove T-hot from initial conditions. Add cue to elicit C/D rate and observe applicant response to adjust C/D rate.
Sim f: Update cover page-this is not an alternate path JPM.
Sim g: Modify simulator set up regarding procedure IOP-3.
Sim h: No comment.
IP i: At JPM step 5.9.4 clarify droop switch position.
IP j: Clarify how to remove key from lock.
IP k: At step 5.5.4 specify what ~1auge is being used. At steps 5.5.5 & 5.5.6 specify the location of the valves.
RO Admin A 1-1: Conduct in classroom instead of simulator. Clarify cues to focus applicant actions. Correct number of minutes (1 010 vs 1000) or start time to equal 1000 minutes.
RO Admin A 1-2: No comment.
RO Admin A2: Delete last line of initiating cue. Enhance answer key due to possible multiple isolation points.
RO Admin A4: Add set up info for simulator operator.
SRO Admin A1-1: Fix cue sheet to match cover page initial conditions. Add trend data to support conservative decision on application of table.
SRO Admin A 1-2: No comment.
SRO Admin A2: Provide optional tagging point in JPM step 2.
SRO Admin A3: No comment.
SRO Admin A4: No comment.
Scenarios ESG-1: Modify the expected dilution for the reactivity plan.
ESG-2: Correct 21 B vs 23 BOOS in initial conditions. Explain Note on Form ES-D-1 about CTs in parentheses. Make this the spare.
ESG-3: No comment.
ESG-4: Add TS to event 4.
ESG-5: Replace event 7 (LOOP) with RCP 'C' tripping.
Salem Op Test Comments Job Performance Measures:
Sima: Update cover page-this is not an alternate path JPM.
Sim b: No comment.
Sim c: Change to put 21 charging pump in service instead of PDP for set up.
Sim d: No comment.
Sim e: JPM step 12 is not critical. Remove T-hot from initial conditions. Add cue to elicit C/D rate and observe applicant response to adjust C/D rate.
Sim f: Update cover page-this is not an alternate path JPM.
Sim g: Modify simulator set up regarding procedure IOP-3.
Sim h: No comment.
IP i: At JPM step 5.9.4 clarify droop switch position.
IP j: Clarify how to remove key from lock.
IP k: At step 5.5.4 specify what ~1auge is being used. At steps 5.5.5 & 5.5.6 specify the location of the valves.
RO Admin A 1-1: Conduct in classroom instead of simulator. Clarify cues to focus applicant actions. Correct number of minutes (1 010 vs 1000) or start time to equal 1000 minutes.
RO Admin A 1-2: No comment.
RO Admin A2: Delete last line of initiating cue. Enhance answer key due to possible multiple isolation points.
RO Admin A4: Add set up info for simulator operator.
SRO Admin A1-1: Fix cue sheet to match cover page initial conditions. Add trend data to support conservative decision on application of table.
SRO Admin A 1-2: No comment.
SRO Admin A2: Provide optional tagging point in JPM step 2.
SRO Admin A3: No comment.
SRO Admin A4: No comment.
Scenarios ESG-1: Modify the expected dilution for the reactivity plan.
ESG-2: Correct 21 B vs 23 BOOS in initial conditions. Explain Note on Form ES-D-1 about CTs in parentheses. Make this the spare.
ESG-3: No comment.
ESG-4: Add TS to event 4.