| {{#Wiki_filter:SOUTHERN NUCLEAR OPERATING COMPANY, INC. | | {{#Wiki_filter:SOUTHERN NUCLEAR OPERATING COMPANY, INC. |
| GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MEAG POWER SPVM, LLC MEAG POWER SPVJ, LLC MEAG POWER SPVP, LLC CITY OF DALTON, GEORGIA VOGTLE ELECTRIC GENERATING PLANT UNIT 3 DOCKET NO. 52-025 EXEMPTION FROM REGULATIONS SET FORTH IN APPENDIX D OF 10 CFR PART 52 Exemption License No. NPF-91 | | |
| : 1. In a {{letter dated|date=August 24, 2021|text=letter dated August 24, 2021}}, Southern Nuclear Operating Company (SNC) requested from the Nuclear Regulatory Commission (NRC or Commission) an exemption to allow departures from Tier 1 information in the certified Design Control Document (DCD) incorporated by reference in Title 10 of the Code of Federal Regulations (10 CFR) Part 52, Appendix D, Design Certification Rule for the AP1000 Design, as part of license amendment request (LAR) 21-001, Clarification of ITAAC Regarding Invessel Components. | | GEORGIA POWER COMPANY |
| For the reasons set forth in Section 3.2 of the NRC staffs Safety Evaluation, which can be found at Agencywide Documents Access and Management System (ADAMS) | | |
| | OGLETHORPE POWER CORPORATION |
| | |
| | MEAG POWER SPVM, LLC |
| | |
| | MEAG POWER SPVJ, LLC |
| | |
| | MEAG POWER SPVP, LLC |
| | |
| | CITY OF DALTON, GEORGIA |
| | |
| | VOGTLE ELECTRIC GENERATING PLANT UNIT 3 |
| | |
| | DOCKET NO. 52-025 |
| | |
| | EXEMPTION FROM REGULATIONS SET FORTH IN |
| | |
| | APPENDIX D OF 10 CFR PART 52 |
| | |
| | Exemption License No. NPF-91 |
| | : 1. In a {{letter dated|date=August 24, 2021|text=letter dated August 24, 2021}}, Southern Nuclear Operatin g Company (SNC) requested from the Nuclear Regulatory Commission (NRC or Commis sion) an exemption to allow departures from Tier 1 information in the ce rtified Design Control Document (DCD) incorporated by reference in Title 10 of the Code of Federal Regulations (10 CFR) Part 52, Appendix D, Design Certification Rule for t he AP1000 Design, as part of license amendment request (LAR) 21-001, Cl arification of ITAAC Regarding Invessel Components. |
| | |
| | For the reasons set forth in Section 3.2 of the NRC staffs Saf ety Evaluation, which can be found at Agencywide Documents Access and Management System ( ADAMS) |
| Accession Number ML21237A240, the Commission finds that: | | Accession Number ML21237A240, the Commission finds that: |
| A. the exemption is authorized by law; B. the exemption presents no undue risk to public health and safety; C. the exemption is consistent with the common defense and security; D. special circumstances are present in that the application of the rule in this circumstance would not serve the underlying purpose of the rule or is not necessary to serve the underlying purpose of the rule;
| |
|
| |
|
| E. the special circumstances outweigh any decrease in safety that may result from the reduction in standardization caused by the exemption; and F. the exemption will not result in a significant decrease in the level of safety otherwise provided by the design. | | A. the exemption is authorized by law; |
| : 2. Accordingly, SNC is granted an exemption from the certified AP1000 DCD Tier 1 information, with corresponding changes to Appendix C of the Facility Combined License, as described in the licensees request dated August 24, 2021. This exemption is related to, and necessary for the granting of License Amendment No. 188, which is being issued concurrently with this exemption. | | |
| : 3. As explained in Section 6.0 of the NRC staffs Safety Evaluation (ADAMS Accession Number ML21237A240), this exemption meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Therefore, pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment needs to be prepared in connection with the issuance of the exemption. | | B. the exemption presents no undue risk to public health and sa fety; |
| | |
| | C. the exemption is consistent with the common defense and secu rity; |
| | |
| | D. special circumstances are present in that the application of the rule in this circumstance would not serve the underlying purpose of the rule or is not necessary to serve the underlying purpose of the rule; |
| | |
| | E. the special circumstances outweigh any decrease in safety th at may result from the reduction in standardization caused by the exemption; and |
| | |
| | F. the exemption will not result in a significant decrease in t he level of safety otherwise provided by the design. |
| | : 2. Accordingly, SNC is granted an exemption from the certified AP1000 DCD Tier 1 information, with corresponding changes to Appendix C of the Fa cility Combined License, as described in the licensees request dated August 24, 2021. This exemption is related to, and necessary for the granting of License Amendm ent No. 188, which is being issued concurrently with this exemption. |
| | : 3. As explained in Section 6.0 of the NRC staffs Safety Evalua tion (ADAMS Accession Number ML21237A240), this exemption meets the eligibility crite ria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Therefore, pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment needs to be prepared in connection with the issuance of the exemption. |
| : 4. This exemption is effective as of the date of its issuance. | | : 4. This exemption is effective as of the date of its issuance. |
| | |
| FOR THE NUCLEAR REGULATORY COMMISSION: | | FOR THE NUCLEAR REGULATORY COMMISSION: |
| /RA/
| | |
| Gregory T. Bowman, Director Vogtle Project Office Office of Nuclear Reactor Regulation Date of Issuance: October 15th, 2021}} | | /RA/ |
| | |
| | Gregory T. Bowman, Director Vogtle Project Office Office of Nuclear Reactor Regulation |
| | |
| | Date of Issuance: October 15 th, 2021}} |
Letter Sequence Approval |
---|
|
|
MONTHYEARML21179A1302021-06-15015 June 2021 Updated Final Safety Analysis Report, Tier 1, Technical Requirements Manual and Technical Specifications Bases Annual Submittal Project stage: Request ML21179A0982021-06-15015 June 2021 Updated Final Safety Analysis Report, Tier 1, Technical Requirements Manual and Technical Specifications Bases Annual Submittal Project stage: Request ML21179A0972021-06-15015 June 2021 to Tier 1 Project stage: Request ND-21-0772, Request for License Amendment and Exemption: Clarification of ITAAC Regarding Invessel Components (LAR-21-001)2021-08-24024 August 2021 Request for License Amendment and Exemption: Clarification of ITAAC Regarding Invessel Components (LAR-21-001) Project stage: Request ML21237A2402021-10-15015 October 2021 Safety Evaluation for Amendment No. LAR-21-001: Clarification of ITAAC Regarding Invessel Components Project stage: Approval ML21237A2052021-10-15015 October 2021 Issuance of Amendment Nos. 188 and 186 and Exemptions: Clarifications of ITAAC Regarding Invessel Components (LAR-21-001) Project stage: Request ML21237A2392021-10-15015 October 2021 Exemption Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components Project stage: Approval ML21237A2382021-10-15015 October 2021 Exemption Unit 3 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components Project stage: Approval ML21237A2362021-10-15015 October 2021 Amendment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components Project stage: Approval ML21237A2372021-10-15015 October 2021 Attachment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components Project stage: Approval ML21237A2352021-10-15015 October 2021 Attachment Unit 3 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components Project stage: Approval ML21237A2342021-10-15015 October 2021 Amendment Unit 3 - Vogtle Electric Generating Plant LAR 21-001: Clarification of ITAAC Regarding Invessel Components Project stage: Approval ML21237A2332021-10-15015 October 2021 Cover Letter for Amendment Nos. 188 and 186 (LAR 21-001): Clarification of ITAAC Regarding Invessel Components Project stage: Approval 2021-06-15
[Table View] |
|
---|
Category:Exemption from NRC Requirements
MONTHYEARML24102A2662024-09-11011 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - FRN ML24102A2642024-09-0909 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - Letter ML24102A2652024-09-0909 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - Exemption NL-24-0097, Exemption Request: Final Safety Analysis Report Update Schedule2024-03-22022 March 2024 Exemption Request: Final Safety Analysis Report Update Schedule ML24044A0732024-02-28028 February 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - January 2024 ML24010A0712024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports and Recordkeeping and Suspicious Activity Reporting) NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23093A1012023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors (EPID L-2022-LLE-0020) - Letter ML23093A1032023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors (EPID L-2022-LLE-0020) - Exemption ML23094A1142023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 68, Criticality Accident Requirements (EPID L-2022-LLE-0022)- Exemption ML23094A1192023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 68, Criticality Accident Requirements (EPID L-2022-LLE-0022)- Letter ML23096A1902023-08-0101 August 2023 Exemption from the Requirements of 10 CFR 50, Appendix K, ECCS (Emergency Core Cooling Systems) Evaluation Models (EPID L-2022-LLE-0021) - Cover Letter ML23096A1952023-08-0101 August 2023 Exemption from the Requirements of 10 CFR 50, Appendix K, ECCS (Emergency Core Cooling Systems) Evaluation Models (EPID L-2022-LLE-0021) - Exemption ML22284A1322022-11-22022 November 2022 Exemption - Vogtle LAR-22-003 U4 Electrical ITAAC Consolidation Amendment NL-22-0583, Request for Fee Exemption for NRC Review Fees for the Licensing Amendment and 10 CFR 50.68 Exemption Submitted for Lead Test Assemblies with Increased Enrichment2022-08-12012 August 2022 Request for Fee Exemption for NRC Review Fees for the Licensing Amendment and 10 CFR 50.68 Exemption Submitted for Lead Test Assemblies with Increased Enrichment ML21279A1922021-11-23023 November 2021 Draft Federal Register Notice Regarding Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses ML21320A0442021-11-23023 November 2021 FRN Exemption from the Requirements of 73.55(a)(4) and 73.56(a)(3) (EPID L-2021-LLE-0049)_Rev.1 ML21306A0022021-11-0404 November 2021 Request for Exemption: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load - Draft ML21299A0272021-10-31031 October 2021 Southern Nuclear Operating Company (SNC) Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Draft Request for Exemption: Protected Area Declaration ML21237A2382021-10-15015 October 2021 Exemption Unit 3 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2392021-10-15015 October 2021 Exemption Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21179A1762021-08-0505 August 2021 FRN for Issuance of Exemption - Farley and Vogtle FSAR Update Exemption - Rev 1 ML21179A1852021-08-0404 August 2021 Exemption - Farley and Vogtle - FSAR Update Exemption - Rev 1 ML21179A2042021-08-0404 August 2021 LTR - Farley and Vogtle - Exemption Transmittal Letter - FSAR Update Exemption - Rev 1. Exemptions from the Requirements of 10 CFR Part 50, Section 50.71(e)(4), Final Safety Analysis Report Update Schedule ML21071A0532021-07-30030 July 2021 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors (Exemption) ML21189A1552021-07-0808 July 2021 Enclosure 1: Request for Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses ML21189A1562021-07-0808 July 2021 Enclosure 2: Unit 4 Operator Candidates Requesting Credit for Unit 3 Written Examination and Operating Test NL-21-0543, Units 1 and 2 and Vogtle Electric Generating Plant - Units 1 and 2, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2021-06-0909 June 2021 Units 1 and 2 and Vogtle Electric Generating Plant - Units 1 and 2, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule ML20329A3922020-12-0404 December 2020 Exemption from Annual Force-On-Force Exercise Requirement of 10 Cfr Part 73, Appendix B, General Criteria for Security Personnel Subsection VI C.3(I)(1) (EPID L 2020 Lle 0216 (Covid 19)) ML20315A3742020-12-0404 December 2020 Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel Subsection VI C.3(I)(1) (EPID L-2020-LLE-0183 (COVID-19)) NL-20-1254, Request for One-Time Exemptions from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to COVID-19 Pandemic2020-11-0606 November 2020 Request for One-Time Exemptions from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to COVID-19 Pandemic ML20132A0772020-08-0303 August 2020 Exemption - Vogtle Electric Generating Plant Unit 3 (LAR 20-001) NL-20-0620, SNC Requests a Temporary Exemption from the Quarterly Fire Brigade Drills and Annual Live Fire Fighting Training Requirements of the Regulation2020-05-22022 May 2020 SNC Requests a Temporary Exemption from the Quarterly Fire Brigade Drills and Annual Live Fire Fighting Training Requirements of the Regulation ML20126G2662020-05-14014 May 2020 Exemption Request from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Section VI ML20059N7872020-05-12012 May 2020 Exemption - LAR-19-010: Auxiliary Building Room Heatup ML20059N7902020-05-12012 May 2020 Exemption - LAR-19-010: Auxiliary Building Room Heatup ML20066G9042020-03-0606 March 2020 Request for Exemption from 10 CFR Part 50, Appendix E Exercise Requirements ND-20-0204, Enclosure 1 - Vogtle Electric Generating Plant (VEGP) Unit 4, Exemption Request 10 CFR Part 50, Appendix E Exercise Requirements2020-03-0606 March 2020 Enclosure 1 - Vogtle Electric Generating Plant (VEGP) Unit 4, Exemption Request 10 CFR Part 50, Appendix E Exercise Requirements ML19350C6272020-01-28028 January 2020 Exemption - Vogtle Electric Generating Plant Unit 3 (LAR 19-015) ML19350C6612020-01-28028 January 2020 Exemption - Vogtle Electric Generating Plant Unit 4 (LAR 19-015) ML19361A1092020-01-13013 January 2020 Exemption - Vogtle Electric Generating Plant Unit 4 (LAR 19-003) ML19361A1192020-01-13013 January 2020 Exemption - Vogtle Electric Generating Plant Unit 3 (LAR 19-003) ML19337A7412019-12-27027 December 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 (LAR 19-002) Exemption from Regulations Set Forth in Appendix D of 10CFR52 ML19337B1392019-12-27027 December 2019 Exemption - Vogtle Electric Generating Plant Unit 4 (LAR 19-002) Exemption from Regulations Set Forth in Appendix D of 10CFR52 ML19164A2652019-11-15015 November 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 (LAR 19-005) ML19164A2662019-11-15015 November 2019 Exemption - Vogtle Electric Generating Plant, Unit 4 (LAR 19-005) NL-19-0801, Quality Assurance Topical Report Submittal, Request for Schedular Exemption - 10 CFR 50.54(a)(3)2019-10-31031 October 2019 Quality Assurance Topical Report Submittal, Request for Schedular Exemption - 10 CFR 50.54(a)(3) ML19238A3512019-09-27027 September 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 LAR 19-004 ML19239A0892019-09-27027 September 2019 Exemption - Vogtle Electric Generating Plant, Unit 4 LAR 19-004 ND-19-0782, Request for License Amendment and Exemption: Onsite Standby Diesel Generator Loading Changes (LAR-19-015)2019-08-0909 August 2019 Request for License Amendment and Exemption: Onsite Standby Diesel Generator Loading Changes (LAR-19-015) 2024-09-09
[Table view] |
Text
SOUTHERN NUCLEAR OPERATING COMPANY, INC.
GEORGIA POWER COMPANY
OGLETHORPE POWER CORPORATION
MEAG POWER SPVM, LLC
MEAG POWER SPVJ, LLC
MEAG POWER SPVP, LLC
CITY OF DALTON, GEORGIA
VOGTLE ELECTRIC GENERATING PLANT UNIT 3
DOCKET NO.52-025
EXEMPTION FROM REGULATIONS SET FORTH IN
APPENDIX D OF 10 CFR PART 52
Exemption License No. NPF-91
- 1. In a letter dated August 24, 2021, Southern Nuclear Operatin g Company (SNC) requested from the Nuclear Regulatory Commission (NRC or Commis sion) an exemption to allow departures from Tier 1 information in the ce rtified Design Control Document (DCD) incorporated by reference in Title 10 of the Code of Federal Regulations (10 CFR) Part 52, Appendix D, Design Certification Rule for t he AP1000 Design, as part of license amendment request (LAR)21-001, Cl arification of ITAAC Regarding Invessel Components.
For the reasons set forth in Section 3.2 of the NRC staffs Saf ety Evaluation, which can be found at Agencywide Documents Access and Management System ( ADAMS)
Accession Number ML21237A240, the Commission finds that:
A. the exemption is authorized by law;
B. the exemption presents no undue risk to public health and sa fety;
C. the exemption is consistent with the common defense and secu rity;
D. special circumstances are present in that the application of the rule in this circumstance would not serve the underlying purpose of the rule or is not necessary to serve the underlying purpose of the rule;
E. the special circumstances outweigh any decrease in safety th at may result from the reduction in standardization caused by the exemption; and
F. the exemption will not result in a significant decrease in t he level of safety otherwise provided by the design.
- 2. Accordingly, SNC is granted an exemption from the certified AP1000 DCD Tier 1 information, with corresponding changes to Appendix C of the Fa cility Combined License, as described in the licensees request dated August 24, 2021. This exemption is related to, and necessary for the granting of License Amendm ent No. 188, which is being issued concurrently with this exemption.
- 3. As explained in Section 6.0 of the NRC staffs Safety Evalua tion (ADAMS Accession Number ML21237A240), this exemption meets the eligibility crite ria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Therefore, pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment needs to be prepared in connection with the issuance of the exemption.
- 4. This exemption is effective as of the date of its issuance.
FOR THE NUCLEAR REGULATORY COMMISSION:
/RA/
Gregory T. Bowman, Director Vogtle Project Office Office of Nuclear Reactor Regulation
Date of Issuance: October 15 th, 2021