Line 14: Line 14:
| document type = OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING, TEXT-LICENSE APPLICATIONS & PERMITS
| document type = OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING, TEXT-LICENSE APPLICATIONS & PERMITS
| page count = 5
| page count = 5
| project =  
| project = TAC:60703, TAC:60730, TAC:60731
| stage = Request
| stage = Request
}}
}}


=Text=
=Text=
{{#Wiki_filter:}}
{{#Wiki_filter:c.                                                                                                              ]
Georgia Power Company 333 Pbdmont Avenue
    . Atlanta, Georgia 30308 Telephone 404 526 7020
        - Maihng Address:
Post office Box 4545 Atlanta, Georgia 30302                                                                    g Georgia Power J. T. Beckham, Jr.                                                      the sotshem electoc system Vice President and General Manager Nuclear operations SL-71 0103C Jaruary 6,1986 Director of N1 clear Reactor Recplation Attention: Mr. D. Miller, Project Director IMR Project Directorate No. 2 Division of Boiling Water Reactor Licensing U. S. M1 clear Recplatory Oxmtission Washington, D. C. 20555 NRC DOCKE'IS 50-321, 50-366 OPERATING LICENSES Dm-57, NPF-5 EDWIN I. HA'IGI NUCLEAR PLANT UNITS 1 AND 2 RECUEST 'IO REVISE 'IEGINICAL SPECIFICATIONS:
DEIETION OF CDN'IROL BUIIDING CD9 FIRE SUPmESSION SYSTEM Gentlemen:
In accordance with the provisions of 10 CFR 50.90 as recuired by 10 CFR 50.59(c) (1) , Georgia Ruer (bmpany (GPC) hereby proposes changes to the Technical Specifications, Appendix A to Operating Licenses DPR-57 and NPF -5.
                  'Ihese proposed changes would delete from Plant Hatch Units 1 and 2
            'Ibchnical Specifications recnirements for the Control axilding CD2 fire alppression system.
                  'Ihis system is now reclindant to other installed fire protection systems and is not recpired for adecuate fire alppression capability.                    In addition, this system poses a personnel life safety hazard daring altveillance ard operation Attachment 1 provides a detailed description of the proposed changes anG circumstances necessitating the change recuest.
Attachment 2 details the basis for our determination that the proposed changes do not constitute an unreviewed safety cuestion.
Attachment 3 details the basis for our determination that the proposed changes do not involve significant hazards considerations.
Attachment 4 provides page change instructions for incorporating the proposed change.
                                              ^
8601170595 860106                                                                                  i I l        PDR        ADOCK 05000321 kC[c!taJhet6//SCD
 
'0-                                                                                                j Georgia Powerd Attention: Mr. D. M111er, Project Director BWR Project Directorate No. 2 Director of N2 clear Reactor Regulation Jamary 6,1986 Page 'IWo The proposed changed Technical Specification pages follow Attachment 4.
Payment of filing fee is enclosed.
In order to allow time for proced2re revision and orderly incorporation into copies of the Technical Specifications, we reglest that the proposed amendment once approved by the NRC, be ismed with an effective date to be no later than 30 days from the date of ismance of the amendment.
R1rmant to the recalirements of 10 GR 50.91, Mr. J. L. Iedbetter of the Environmental Protection Division of the Georgia Department of Nat11ral Resctarces will be sent a copy of this letter and all applicable attachments.
J. T. Beckhar          Jr. states that he is Vice President of Georgia Ibwer Conpany and is althorized to execute this oath on behalf of Georgia Ibwer Conpany, and that to the best of his knowledge and belief the facts set forth in this letter are tnie.
GEORGIA IOWER (DMPANY By:                  b g  J. T. Beckham, Jr.
Sworn to ard mbscribed before me this 6th day of Jamary,1986.
hh {                      1.__  _m Notary Pubhc, Georgia,5 tate at Large  Notary Riblic My Commisson Expres Aug.26,1986 10G/ REB /lc Enclomre c:      Mr. H. C. Nix, Jr.
Senior Resident Inspector Dr. J. N. Grace, (NRC-Region II)
Mr. J. L. Iedbetter G)-NORMS mns
 
LGeorgia Pbwer f
ATTACINENT 1 NRC 00CKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5
                                      -EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 BASIS FOR CHANGE REQUEST Plant Hatch Unit 1. Technical Specification 3/4.13.4 and Unit 2 Technical Specification 3/4.7.6.3 require the Control Building C02 fire protection system to be operable 'at all times when the equipment in the area is
                  .' required to be - operable. The carbon dioxide suppression system in the Control Building was originally intended to protect the cable spreading room and the computer room. Additionally two . CO2 hose reels were provided in the Control Building. corridor on the 130' elevation for primary protection of the switchgear rooms and switchgear transformer rooms. Backup protection was . previously provided by the CO2 hose reels for the laboratory and the Control Building corridor.
However, primary and- secondary fire - protection in each of the areas serviced:by the Control Building C02 system is now provided by other means including sprinklers, hose stations, and portable. fire extinguishers. These changes were initiated by the requirements. of the Appendix A response for
                    ' APCS 8 .9.5.1. Therefore.. the Control Building C02 system is now redundant
                  - to other installed fire suppression systems. And, because C02 displaces oxygen in. the human body, a life safety hazard is presented during performance of surveillance-on this system. Maintenance and surveillance of the system by ~ personnel, < as . well as inadvertent actuation, could pose a significant personnel safety hazard. On the above basis GPC requests that
"                    the' NRC delete- the requirement for an operable ~ Control Building ~ C02 system
                  .from the Plant Hatch Unit 1 and 2 Technical Specifications.
E
                                                                                                      )
 
Georgia Power d ATTACMENT 2 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5 EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 DELETION OF CONTROL-BUILDING C0p FIRE SUPPRESSION SYSTEM 10 CFR 50.59 EVALUATION Pursuant to 10 CFR. 50.59, the Plant Review Board and Safety Review Board have reviewed the attached proposed amendment to the Plant Hatch Units
                  .1 and 2 Technical Specifications and have determined that implementation of the proposed change does not constitute an unreviewed safety question PROPOSED CHANGE The proposed change would delete the requirement for an operable C02 fire suppression system from the Unit 1 and 2 Technical Specifications.
BASIS The probability of occurrence and the consequences of an accident or malfunction of equipment important to safety are not increased above those analyzed in the FSAR due to this change because other fire protection systems are provided which will ensure equivalent or better protection from the fire hazard in each of the areas serviced by the control building C02 system.
The possibility of an accident or malfunction of a different type than analyzed in the FSAR does not result from this change because no changes to the plant modes of operation are being proposed and the remaining fire suppression capabilities are sufficient for the hazards involved.
The margin of safety as defined in the Technical Specifications is unaffected by deletion of the Control Building CO2 system because new systems    have  been  added    a1d  provided  with appropriate  Technical Specification requirements.
700775 u,
 
@dddi -
GeorgiaPower A ATTACINENT 3 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5
                                    . EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 DELETION OF CONTROL BUILDING CO2 FIRE SUPPRESSION SYSTEM 10 CFR 50.92 EVALUATION Pursuant to 10 CFR 50.92, Georgia Power Company has evaluated the attached proposed amendment for Plant Hatch Units 1 and 2 and has determined that _ its adoption' would not ' involve a significant hazard. The basis for this determination is as follows:
PROPOSED CHANGE The. proposed - change would delete the requirement for an operable C0 2 fire suppression system from the Unit 1 and 2 Technical Specifications.
BASIS The proposed - change does . not involve a significant increase in the probability or consequences of an accident previously evaluated because this
_ change _would delete what is now a redundant fire suppression system which is no longer required for adequate fire protection and which poses a potential personnel safety hazard during surveillance and operation.
                        'The proposed change does not create the possibility of a new or different kind of accident from any accident previously evaluated because no safety limits or safety system settings are being changed. Sufficient fire suppression capability will still be available in the affected fire areas.
The proposed change does not involve a significant reduction in the margin of'_ safety because safety settings are not altered and the affected fire areas will still have sufficient suppression capability.
700775}}

Latest revision as of 20:44, 13 December 2021

Application for Amend to Licenses DPR-57 & NPF-5,changing Tech Specs to Delete Control Bldg CO2 Fire Suppression Sys. Fee Paid
ML20137F915
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 01/06/1986
From: Backham J, Backhan J, Beckham J, Beckhan J, Beckhman J, Beckman J
GEORGIA POWER CO.
To: Miller D
Office of Nuclear Reactor Regulation
Shared Package
ML20137F919 List:
References
0103C, 103C, SL-71, TAC-60703, TAC-60730, TAC-60731, NUDOCS 8601170595
Download: ML20137F915 (5)


Text

c. ]

Georgia Power Company 333 Pbdmont Avenue

. Atlanta, Georgia 30308 Telephone 404 526 7020

- Maihng Address:

Post office Box 4545 Atlanta, Georgia 30302 g Georgia Power J. T. Beckham, Jr. the sotshem electoc system Vice President and General Manager Nuclear operations SL-71 0103C Jaruary 6,1986 Director of N1 clear Reactor Recplation Attention: Mr. D. Miller, Project Director IMR Project Directorate No. 2 Division of Boiling Water Reactor Licensing U. S. M1 clear Recplatory Oxmtission Washington, D. C. 20555 NRC DOCKE'IS 50-321, 50-366 OPERATING LICENSES Dm-57, NPF-5 EDWIN I. HA'IGI NUCLEAR PLANT UNITS 1 AND 2 RECUEST 'IO REVISE 'IEGINICAL SPECIFICATIONS:

DEIETION OF CDN'IROL BUIIDING CD9 FIRE SUPmESSION SYSTEM Gentlemen:

In accordance with the provisions of 10 CFR 50.90 as recuired by 10 CFR 50.59(c) (1) , Georgia Ruer (bmpany (GPC) hereby proposes changes to the Technical Specifications, Appendix A to Operating Licenses DPR-57 and NPF -5.

'Ihese proposed changes would delete from Plant Hatch Units 1 and 2

'Ibchnical Specifications recnirements for the Control axilding CD2 fire alppression system.

'Ihis system is now reclindant to other installed fire protection systems and is not recpired for adecuate fire alppression capability. In addition, this system poses a personnel life safety hazard daring altveillance ard operation Attachment 1 provides a detailed description of the proposed changes anG circumstances necessitating the change recuest.

Attachment 2 details the basis for our determination that the proposed changes do not constitute an unreviewed safety cuestion.

Attachment 3 details the basis for our determination that the proposed changes do not involve significant hazards considerations.

Attachment 4 provides page change instructions for incorporating the proposed change.

^

8601170595 860106 i I l PDR ADOCK 05000321 kC[c!taJhet6//SCD

'0- j Georgia Powerd Attention: Mr. D. M111er, Project Director BWR Project Directorate No. 2 Director of N2 clear Reactor Regulation Jamary 6,1986 Page 'IWo The proposed changed Technical Specification pages follow Attachment 4.

Payment of filing fee is enclosed.

In order to allow time for proced2re revision and orderly incorporation into copies of the Technical Specifications, we reglest that the proposed amendment once approved by the NRC, be ismed with an effective date to be no later than 30 days from the date of ismance of the amendment.

R1rmant to the recalirements of 10 GR 50.91, Mr. J. L. Iedbetter of the Environmental Protection Division of the Georgia Department of Nat11ral Resctarces will be sent a copy of this letter and all applicable attachments.

J. T. Beckhar Jr. states that he is Vice President of Georgia Ibwer Conpany and is althorized to execute this oath on behalf of Georgia Ibwer Conpany, and that to the best of his knowledge and belief the facts set forth in this letter are tnie.

GEORGIA IOWER (DMPANY By: b g J. T. Beckham, Jr.

Sworn to ard mbscribed before me this 6th day of Jamary,1986.

hh { 1.__ _m Notary Pubhc, Georgia,5 tate at Large Notary Riblic My Commisson Expres Aug.26,1986 10G/ REB /lc Enclomre c: Mr. H. C. Nix, Jr.

Senior Resident Inspector Dr. J. N. Grace, (NRC-Region II)

Mr. J. L. Iedbetter G)-NORMS mns

LGeorgia Pbwer f

ATTACINENT 1 NRC 00CKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5

-EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 BASIS FOR CHANGE REQUEST Plant Hatch Unit 1. Technical Specification 3/4.13.4 and Unit 2 Technical Specification 3/4.7.6.3 require the Control Building C02 fire protection system to be operable 'at all times when the equipment in the area is

.' required to be - operable. The carbon dioxide suppression system in the Control Building was originally intended to protect the cable spreading room and the computer room. Additionally two . CO2 hose reels were provided in the Control Building. corridor on the 130' elevation for primary protection of the switchgear rooms and switchgear transformer rooms. Backup protection was . previously provided by the CO2 hose reels for the laboratory and the Control Building corridor.

However, primary and- secondary fire - protection in each of the areas serviced:by the Control Building C02 system is now provided by other means including sprinklers, hose stations, and portable. fire extinguishers. These changes were initiated by the requirements. of the Appendix A response for

' APCS 8 .9.5.1. Therefore.. the Control Building C02 system is now redundant

- to other installed fire suppression systems. And, because C02 displaces oxygen in. the human body, a life safety hazard is presented during performance of surveillance-on this system. Maintenance and surveillance of the system by ~ personnel, < as . well as inadvertent actuation, could pose a significant personnel safety hazard. On the above basis GPC requests that

" the' NRC delete- the requirement for an operable ~ Control Building ~ C02 system

.from the Plant Hatch Unit 1 and 2 Technical Specifications.

E

)

Georgia Power d ATTACMENT 2 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5 EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 DELETION OF CONTROL-BUILDING C0p FIRE SUPPRESSION SYSTEM 10 CFR 50.59 EVALUATION Pursuant to 10 CFR. 50.59, the Plant Review Board and Safety Review Board have reviewed the attached proposed amendment to the Plant Hatch Units

.1 and 2 Technical Specifications and have determined that implementation of the proposed change does not constitute an unreviewed safety question PROPOSED CHANGE The proposed change would delete the requirement for an operable C02 fire suppression system from the Unit 1 and 2 Technical Specifications.

BASIS The probability of occurrence and the consequences of an accident or malfunction of equipment important to safety are not increased above those analyzed in the FSAR due to this change because other fire protection systems are provided which will ensure equivalent or better protection from the fire hazard in each of the areas serviced by the control building C02 system.

The possibility of an accident or malfunction of a different type than analyzed in the FSAR does not result from this change because no changes to the plant modes of operation are being proposed and the remaining fire suppression capabilities are sufficient for the hazards involved.

The margin of safety as defined in the Technical Specifications is unaffected by deletion of the Control Building CO2 system because new systems have been added a1d provided with appropriate Technical Specification requirements.

700775 u,

@dddi -

GeorgiaPower A ATTACINENT 3 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5

. EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 DELETION OF CONTROL BUILDING CO2 FIRE SUPPRESSION SYSTEM 10 CFR 50.92 EVALUATION Pursuant to 10 CFR 50.92, Georgia Power Company has evaluated the attached proposed amendment for Plant Hatch Units 1 and 2 and has determined that _ its adoption' would not ' involve a significant hazard. The basis for this determination is as follows:

PROPOSED CHANGE The. proposed - change would delete the requirement for an operable C0 2 fire suppression system from the Unit 1 and 2 Technical Specifications.

BASIS The proposed - change does . not involve a significant increase in the probability or consequences of an accident previously evaluated because this

_ change _would delete what is now a redundant fire suppression system which is no longer required for adequate fire protection and which poses a potential personnel safety hazard during surveillance and operation.

'The proposed change does not create the possibility of a new or different kind of accident from any accident previously evaluated because no safety limits or safety system settings are being changed. Sufficient fire suppression capability will still be available in the affected fire areas.

The proposed change does not involve a significant reduction in the margin of'_ safety because safety settings are not altered and the affected fire areas will still have sufficient suppression capability.

700775