| issue date = 04/03/2006
| issue date = 04/03/2006
| title = Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power
| title = Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power
| author name = Dacimo F R
| author name = Dacimo F
| author affiliation = Entergy Nuclear Northeast
| author affiliation = Entergy Nuclear Northeast
| addressee name =  
| addressee name =  
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:Entergy Nuclear Northeast Indian Point Energy Center 450 Broadway, GSB IEnlerg <y P.O. Box 249 0 Buchanan, NY 10511-0:249 Tel 914 734 6700 Fred Dacimo Site Vice President Administration April 3, 2006 Re: Indian Point Units 2 & 3 Dockets 50-247 & 50-286 NL-06-043 U.S. Nuclear Regulatory Commission ATTN:Document Control Desk 115!55 Rockville Pike Rocville, Maryland 20852  
{{#Wiki_filter:Entergy Nuclear Northeast Indian Point Energy Center 450 Broadway, GSB IEnlerg   <y 0                                                P.O. Box 249 Buchanan,   NY 10511-0:249 Tel 914 734 6700 Fred Dacimo Site Vice President Administration April 3, 2006 Re: Indian Point Units 2 & 3 Dockets 50-247 & 50-286 NL-06-043 U.S. Nuclear Regulatory Commission ATTN:Document Control Desk 115!55 Rockville Pike Rocville, Maryland 20852


==Subject:==
==Subject:==
Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power  
Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power


==Reference:==
==Reference:==
: 1. NRC Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power, dated February 1,2006  
: 1. NRC Generic Letter 2006-02, GridReliability and the Impact on Plant Risk and the Operabilityof Offsite Power, dated February 1,2006


==Dear Sir or Madam:==
==Dear Sir or Madam:==
The NRC issued Generic Letter 2006-02 (Reference  
 
: 1) to request information for determining compliance with regulatory requirements governing electric power sources. Specifically, the NRC is requesting information regarding (1) use of protocols between the nuclear power plant (NP]') and the transmission system operator (TSO), independent system operator (ISO), or reliability coordinator/authority (RC/RA) including transmission load flow analysis tools (analysis tools) by TSOs to assist NPPs in monitoring grid conditions to determine the operability of offsite power systems under plant Technical Specification (TS); (2) use of NPP/TSO protocols and analysis tools by TSOs to assist NPPs in monitoring grid conditions for consideration in maintenance risk assessments; (3) offsite power restoration procedures in accordance with Section 2 of NRC Regulatory Guide (RG) 1.155, "Station Blackout;" and, (4)losses of offsite power caused by grid failures at a frequency equal to or greater than once in 20 site-years in accordance with RG 1.155. The requested information is being provided under the requirements of 10 CFR 50.54(f).Attaihment 1 to this letter provides the Entergy Nuclear Operations, Inc. (ENO) response for Indian Point Unit 2 and 3 to Generic Letter 2006-02. Generic Letter 2006-02 discusses compliance with General Design Criterion (GDC) 17 and several other 10CFR50 requirements in several locations.
The NRC issued Generic Letter 2006-02 (Reference 1) to request information for determining compliance with regulatory requirements governing electric power sources. Specifically, the NRC is requesting information regarding (1) use of protocols between the nuclear power plant (NP]') and the transmission system operator (TSO), independent system operator (ISO), or reliability coordinator/authority (RC/RA) including transmission load flow analysis tools (analysis tools) by TSOs to assist NPPs in monitoring grid conditions to determine the operability of offsite power systems under plant Technical Specification (TS); (2) use of NPP/TSO protocols and analysis tools by TSOs to assist NPPs in monitoring grid conditions for consideration in maintenance risk assessments; (3) offsite power restoration procedures in accordance with Section 2 of NRC Regulatory Guide (RG) 1.155, "Station Blackout;" and, (4) losses of offsite power caused by grid failures at a frequency equal to or greater than once in 20 site-years in accordance with RG 1.155. The requested information is being provided under the requirements of 10 CFR 50.54(f).
The exact extent of the compliance of IP2 and IP3 to the GDC are desc:ibed in each plant's Updated Final Safety Analysis Report.A4{/
Attaihment 1 to this letter provides the Entergy Nuclear Operations, Inc. (ENO) response for Indian Point Unit 2 and 3 to Generic Letter 2006-02. Generic Letter 2006-02 discusses compliance with General Design Criterion (GDC) 17 and several other 10CFR50 requirements in several locations. The exact extent of the compliance of IP2 and IP3 to the GDC are desc:ibed in each plant's Updated Final Safety Analysis Report.
Sorae of the questions in Generic Letter 2006-02 seek information, procedures and activities concerning grid reliability which is provided by the TSO and/or ISO. ENO has not independently verified all information provided by:* New York Independent System Operator* Consolidated Edison Company of New York, Inc.Thi; letter contains no new commitments.
A4{/
Should you or your staff have any questions regarding this response, please contact Mr. Patric W. Conroy, Manager, Licensing at (914)734-6668.I declare under penalty of perjury that the foregoing is true and correct. Executed on; 3 2006.V ru styours, R. Dacimo Site Vice President Indian Point Energy Center Attachment 1: Response to Generic Letter 2006-02, Grid Reliability and the Impact On Plant Risk and the Operability of Offsite Power cc: Mr. Samuel J. Collins, Regional Administrator, Region I Mr. John Boska, NRR Senior Project Manager IPEC NRC Resident Inspector's Office, Indian Point Unit 2 IPEC NRC Resident Inspector's Office, Indian Point Unit 3 Mr. ?aul Eddy, New York State Department of Public Service Mr. Peter R. Smith, President NYSERDA Attachment 1 to NL-06-043 RESPONSE TO GENERIC LETTER 2006-02, GRID RELIABILITY AND THE IMPACT ON PLANT RISK AND THE OPERABILITY OF OFFSITE POWER (26 Pages)ENTERGY NUCLEAR OPERATIONS, INC.Indian Point Nuclear Generating Unit No. 2 Docket No. 50-247 Indian Point Nuclear Generating Unit No. 3 Docket No. 50-286 Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page I of 26 Note The following provides a description of the IPEC off-site power system at Indian Point.Unit 2: Offsite power is supplied from the offsite transmission network to the plant by two electrically and physically separated circuits (a 138kV circuit and a 13.8kV circuit).
 
All offsite power enters the plant via 6.9kV buses Nos. 5 and 6 which are normally connected to the 138kV offsite circuit but have the ability to be connected to the 13.8kV offsite circuit. The 138kV offsite circuit satisfies the requirement in GDC 17 that at least one of the two required circuits can, within a few seconds, provide power to safety-related equipment following a loss-of-coolant accident.
Sorae of the questions in Generic Letter 2006-02 seek information, procedures and activities concerning grid reliability which is provided by the TSO and/or ISO. ENO has not independently verified all information provided by:
The 13.8kV offsite circuit is considered a delayed access circuit because operator action is normally required to supply offsite power to the plant using the 13.8kV offsite source.Unit 3:Offsite power is supplied to the plant from the transmission network by two electrically and physically separated circuits, the 138kV or normal circuit and the 13.8kV or alternate circuit. Each of the offsite circuits from the Buchanan substation into the plant is required to be supported by a physically independent circuit from the offsite network into the Buchanan substation.
* New York Independent System Operator
All offsite power enters the plant via 6.9kV buses Nos. 5 and 6 which are connected to the 138kV (normal) offsite circuit and have the ability to be connected to the 13.8kV (alternate) offsite circuit. The arrangement satisfies the requirement that at least one of the two required circuits can within a few seconds; provide power to safety-related equipment following a loss-of-coolant accident.
* Consolidated Edison Company of New York, Inc.
Operator action is required to supply offsite power to the plant using the 13.8kV (alternate) offsite source.The key points to highlight here are as follows: 1. Both units' safeguards loads are powered from the 480V System. The connection to the offsite 138kV and 13.8kV circuits are via the six buses of the 6.9kV System. The arrangement of these six 6.9kV buses allows various alignments to both the 138kV and 13.8kV system and the 480V safeguards buses follow these alignments accordingly.
Thi; letter contains no new commitments. Should you or your staff have any questions regarding this response, please contact Mr. Patric W. Conroy, Manager, Licensing at (914) 734-6668.
Two of the six 6.9kV buses and consequently two of the associated 480V safeguards trains are directly connected to the 138kV offsite circuit, but can also be connected to the 13.8kV offsite circuit via manual transfer.2. As described above, both units have two of the three available trains of safeguards loads connected directly to the preferred offsite circuit (138kV), via two of the six buses of the 6.9kV System, during normal operation and as such, there is no transfer action involved.
I declare under penalty of perjury that the foregoing is true and correct. Executed on
Normal operation includes start-up, hot shutdown, cold shutdown, etc. The third train would be auto-transferred to the preferred offsite circuit during a unit trip from power operation (Mode 1) condition.
          ;3   2006.
Both plants design basis requires two of three safeguards trains to mitigate a loss of coolant accident.3. There is no auto-transfer to the alternate 13.8kV offsite circuit from the 138kV circuit. This transfer, when needed, is manually performed at the 6.9kV System voltage level, and controlled by plant operating procedures.
V     ru styours, R. Dacimo Site Vice President Indian Point Energy Center : Response to Generic Letter 2006-02, Grid Reliability and the Impact On Plant Risk and the Operability of Offsite Power cc:
The procedures call for the Transmission Owner (TO)(i.e., ConEd) to be notified whenever the 13.8kV offsite circuit is to be used for plant operating load. This is because the 13.8kV offsite circuit is a local distribution circuit that also powers residential and commercial loads and the TO maintained voltage level is based on the load on the circuit. The higher the load, the higher the voltage that the TO maintains.
Mr. Samuel J. Collins, Regional Administrator, Region I Mr. John Boska, NRR Senior Project Manager IPEC NRC Resident Inspector's Office, Indian Point Unit 2 IPEC NRC Resident Inspector's Office, Indian Point Unit 3 Mr. ?aul Eddy, New York State Department of Public Service Mr. Peter R. Smith, President NYSERDA
The 13.8kV offsite circuit is controlled by a TO procedure and based on the load on the circuit, the circuit voltage is set accordingly.
 
The lowest specified voltage permitted on this circuit is 13.4KV. TO notifications (to and from IPEC) are based on this value as well.
Attachment 1 to NL-06-043 RESPONSE TO GENERIC LETTER 2006-02, GRID RELIABILITY AND THE IMPACT ON PLANT RISK AND THE OPERABILITY OF OFFSITE POWER (26 Pages)
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 2 of 26 Roth the I 3RIA/ and the I ~ 13.R.A/! cir-uine are m0nfit^Ir by bi Siaiiur- procedures.
ENTERGY NUCLEAR OPERATIONS, INC.
However only the 138kV offsite circuit is monitored by the On-line AC Contingency Monitoring Program. The 13.8kV offsite circuit is monitored by the TO from its Energy Control Center via a Real-time State Estimator (RTISE) Voltage Profile display. This display provides voltage monitoring and alarming functions and the operations procedure contains the necessary notification responsibilities and notification voltages for both the 138kV and 13.8kV offsite circuits.
Indian Point Nuclear Generating Unit No. 2 Docket No. 50-247 Indian Point Nuclear Generating Unit No. 3 Docket No. 50-286
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 3 of 26 r.MWAT*VMAI Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA and the use of analysis tools by TSOs to assist NPP licensee in monitoring grid conditions to determine the operability of offsite power systems under plant TS.GDC 17, 10 CFR Part 50, Appendix A, requires that licensees minimize the probability of the loss of power from the transmission network given a loss of the power generated by the nuclear power unit(s).1. Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA to assist the NPP licensee in monitoring grid conditions to determine the operability of offsite power systems under plant TS.I (a) Do you have a formal agreement or protocol with your TSO?In the New York Reliability Coordinator Area the New York Independent System Operator (NYISO) has operational authority over the bulk power system. The Transmission Owners (TO) have operational authority over the non-bulk power system. The NYISO operates the bulk power system in accordance with NERC, NPCC and New York State Reliability Council (NYSRC) criteria.
 
Established communications protocols are between the NYISO and the Transmission Owners (TO). Communications to the generating resources are through the TOs. The associated TO monitors the localized grid conditions and coordinates issues such as off site power operability with the NPP. In this document TSO refers to the TO.Yes, IPEC has a number of formal agreements with the NYISO and TOs (which also performs the TSO function for IPEC as follows:* IPEC Unit 3 Interconnection Agreement with the Consolidated Edison Company of New York, Inc.(Con Ed)* IPEC Unit 2 Indian Point Continuing Site Agreement with Consolidated Edison Company of New York, Inc.* The New York State Transmission Tariffs with the NYISO* NYISO Customer & Guest Application Form of Service Agreement for NYISO Market Administration and Control Area Service Tariff* Transaction Form between Entergy-IPEC and Con Edison for 138kV and 13.8kV monitoring and notification services The NYISO and TSO agreements require all parties to operate per NYISO and/or TSO procedures and documents, therefore the NYISO and TSO procedures and documents are considered part of the formal agreements.
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page I of 26 Note The following provides a description of the IPEC off-site power system at Indian Point.
Compliance with GDC-17, as documented in the IPEC license basis and plant Technical Specifications, is not Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 4 of 26 II picuicatcu on such an agreemeni.
Unit 2: Offsite power is supplied from the offsite transmission network to the plant by two electrically and physically separated circuits (a 138kV circuit and a 13.8kV circuit). All offsite power enters the plant via 6.9kV buses Nos. 5 and 6 which are normally connected to the 138kV offsite circuit but have the ability to be connected to the 13.8kV offsite circuit. The 138kV offsite circuit satisfies the requirement in GDC 17 that at least one of the two required circuits can, within a few seconds, provide power to safety-related equipment following a loss-of-coolant accident. The 13.8kV offsite circuit is considered a delayed access circuit because operator action is normally required to supply offsite power to the plant using the 13.8kV offsite source.
*I.I (b) Describe any grid conditions that would trigger a notification from the TSO to the NPP licensee and if there is a time period required for the notification The TSO is required to notify IPEC as soon as practical per good utility practice whenever an impaired or potentially degraded grid condition is recognized by the TSO. Specific examples of known potentially degrading conditions identified in the agreement include: 1. De-energizing, switching or in-service work on critical transmission lines 2. Potentially damaging inclement weather 3. Solar Magnetic Disturbances
Unit 3:Offsite power is supplied to the plant from the transmission network by two electrically and physically separated circuits, the 138kV or normal circuit and the 13.8kV or alternate circuit. Each of the offsite circuits from the Buchanan substation into the plant is required to be supported by a physically independent circuit from the offsite network into the Buchanan substation. All offsite power enters the plant via 6.9kV buses Nos. 5 and 6 which are connected to the 138kV (normal) offsite circuit and have the ability to be connected to the 13.8kV (alternate) offsite circuit. The arrangement satisfies the requirement that at least one of the two required circuits can within a few seconds; provide power to safety-related equipment following a loss-of-coolant accident. Operator action is required to supply offsite power to the plant using the 13.8kV (alternate) offsite source.
The key points to highlight here are as follows:
: 1. Both units' safeguards loads are powered from the 480V System. The connection to the offsite 138kV and 13.8kV circuits are via the six buses of the 6.9kV System. The arrangement of these six 6.9kV buses allows various alignments to both the 138kV and 13.8kV system and the 480V safeguards buses follow these alignments accordingly. Two of the six 6.9kV buses and consequently two of the associated 480V safeguards trains are directly connected to the 138kV offsite circuit, but can also be connected to the 13.8kV offsite circuit via manual transfer.
: 2. As described above, both units have two of the three available trains of safeguards loads connected directly to the preferred offsite circuit (138kV), via two of the six buses of the 6.9kV System, during normal operation and as such, there is no transfer action involved. Normal operation includes start-up, hot shutdown, cold shutdown, etc. The third train would be auto-transferred to the preferred offsite circuit during a unit trip from power operation (Mode 1) condition. Both plants design basis requires two of three safeguards trains to mitigate a loss of coolant accident.
: 3. There is no auto-transfer to the alternate 13.8kV offsite circuit from the 138kV circuit. This transfer, when needed, is manually performed at the 6.9kV System voltage level, and controlled by plant operating procedures. The procedures call for the Transmission Owner (TO)
(i.e., ConEd) to be notified whenever the 13.8kV offsite circuit is to be used for plant operating load. This is because the 13.8kV offsite circuit is a local distribution circuit that also powers residential and commercial loads and the TO maintained voltage level is based on the load on the circuit. The higher the load, the higher the voltage that the TO maintains. The 13.8kV offsite circuit is controlled by a TO procedure and based on the load on the circuit, the circuit voltage is set accordingly. The lowest specified voltage permitted on this circuit is 13.4KV. TO notifications (to and from IPEC) are based on this value as well.
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 2 of 26 Roth the I 3RIA/           ~
and the I13.R.A/! cir-uine are m0nfit^Ir by bi                           Siaiiur- procedures. However only the 138kV offsite circuit is monitored by the On-line AC Contingency Monitoring Program. The 13.8kV offsite circuit is monitored by the TO from its Energy Control Center via a Real-time State Estimator (RTISE) Voltage Profile display. This display provides voltage monitoring and alarming functions and the operations procedure contains the necessary notification responsibilities and notification voltages for both the 138kV and 13.8kV offsite circuits.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 3 of 26 r.MWAT*VMAI Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA and the use of analysis tools by TSOs to assist NPP licensee in monitoring grid conditions to determine the operability of offsite power systems under plant TS.
GDC 17, 10 CFR Part 50, Appendix A, requires that licensees minimize the probability of the loss of power from the transmission network given a loss of the power generated by the nuclear power unit(s).
: 1. Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA to assist the NPP licensee in monitoring grid conditions to determine the operability of offsite power systems under plant TS.
I(a) Do you have a formal agreement or protocol with your TSO?                           In the New York Reliability Coordinator Area the New York Independent System Operator (NYISO) has operational authority over the bulk power system. The Transmission Owners (TO) have operational authority over the non-bulk power system. The NYISO operates the bulk power system in accordance with NERC, NPCC and New York State Reliability Council (NYSRC) criteria. Established communications protocols are between the NYISO and the Transmission Owners (TO). Communications to the generating resources are through the TOs. The associated TO monitors the localized grid conditions and coordinates issues such as off site power operability with the NPP. In this document TSO refers to the TO.
Yes, IPEC has a number of formal agreements with the NYISO and TOs (which also performs the TSO function for IPEC as follows:
* IPEC Unit 3 Interconnection Agreement with the Consolidated Edison Company of New York, Inc.
(Con Ed)
* IPEC Unit 2 Indian Point Continuing Site Agreement with Consolidated Edison Company of New York, Inc.
* The New York State Transmission Tariffs with the NYISO
* NYISO Customer & Guest Application Form of Service Agreement for NYISO Market Administration and Control Area Service Tariff
* Transaction Form between Entergy-IPEC and Con Edison for 138kV and 13.8kV monitoring and notification services The NYISO and TSO agreements require all parties to operate per NYISO and/or TSO procedures and documents, therefore the NYISO and TSO procedures and documents are considered part of the formal agreements.
Compliance with GDC-17, as documented in the IPEC license basis and plant Technical Specifications, is not
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 4 of 26 II                               *I.
picuicatcu on such an agreemeni.
I (b) Describe any grid conditions that would     The TSO is required to notify IPEC as soon as practical per good utility practice whenever an impaired or trigger a notification from the TSO to the        potentially degraded grid condition is recognized by the TSO. Specific examples of known potentially NPP licensee and                                  degrading conditions identified in the agreement include:
: 1. De-energizing, switching or in-service work on critical transmission lines if there is a time period required for the              2. Potentially damaging inclement weather notification                                            3. Solar Magnetic Disturbances
: 4. Post-contingency voltage alarm for the 138kV transmission system after 30-minutes.
: 5. Areal-time 13.8kV degraded voltage condition below a normal system schedule voltage after 30-minutes
: 6. Prior to any 138kV feeder, which could impact IPEC being removed or restored to service
: 7. When the TSO 138kV or 13.8kV monitoring and alarm capability are out of service and have not been restored after 30-minutes.
: 8. Other system or equipment conditions determine by the TSO to be of importance to IPEC.
I (c) Describe any grid conditions that would      Grid conditions and status are the primary responsibility of ISO and TSO.
cause the NPP licensee to contact the TSO.
Relative to this question, "grid conditions' is assumed to be IPEC changes that impact the TSO real-time post Describe the procedures associated with such      contingency analysis capability. IPEC typically notified ISO and/or TSO for changes in the following grid a communication. If you do not have                conditions:
procedures, describe how you assess grid conditions that may cause the NPP licensee to            0  Unit power capability changes contact the TSO.                                        0  Unit Startup and Shutdown 0  Modifications resulting in changes to generator electrical characteristics S  Breaker alignment and offsite voltage verification 0  MVAR Loading 0  Post-trip off-site voltage criteria 0  Changes in IPEC post trip station and accident loading
                                                      .0    Loss of preferred 138KV Offsite Power Supply 0  Loss of 13.8KV Offsite Power Supply 0  Status of 13.8kv and 138kv 0  Maintenance activities directly affecting Switchyard components
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 5 of 26 I    5                                                                                                                                                          I a  Mvieihod of voitage controi, automatic or manual.
EDG Surveillance Testing 0  Load tap changer position / Auto-Manual Mode I(d) Describe how NPP operators are trained    The Licensed Operators at IPEC have had training on site procedure that addresses offsite power continuous and tested on the use of                      monitoring and notification. This procedure establishes monitoring, and notification responsibilities of the Buchanan Substation, as well as the interface between the IPEC and Con Edison's Energy Control Center. The the procedures or                              most recent training occurred in Cycle 3 of 2005.
assessing grid conditions in question I (c).
Typically, IPEC operators are trained and tested, using procedures, on the following:
* LOOP
* System Restoration Typically, IPEC operators are trained, using procedures, on the following:
* LOOP
* System Restoration e    Degraded voltage conditions
* Voltage (number for inadequate grid capacity)
* VARs
* Breaker status
* Notification of the ISO and/or TSO of changed conditions.
1(e) If you do not have a formal agreement or As previously stated, IPEC does have a formal agreement with the TSO. Prompt notification from the TSO protocol with your TSO, describe why you      (after 30-minutes) and a pre-trip analysis of whether the post-trip voltage will be below acceptable values are believe you continue to comply with the        included in Indian Point Energy Center Offsite Power Continuous Monitoring And Notification procedure.
provisions of GDC 17 as stated above, or      Additionally TSO procedure describes Con Edison responsibility to notify IPEC of low voltage issues as it describe what actions you intend to take to    relates to the 138kV and 13.8kV systems. The procedure requires the TSO to notify both IP2 & IP3 Control assure compliance with GDC 17.                Rooms after 30-minutes if the real-time analysis tool determines the post IPEC trip voltage would be below the value specified by IPEC. In addition, the TSO will notify IPEC after 30-minutes if the 13.8kV system voltage is below the normal system voltage schedule.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 6 of 26
  !.'11 EMM                                                                                                                                                        - -sI~l, Comluianut: wit CiiGC-i, kir2 and ii;3 are not a GDU plants, the FSARs describe to what extent 1P2 and IP3 were reviewed to the draft GDCs or its equivalent is not predicated on this agreement).
I(f) If you have an existing formal          As previously stated, IPEC does have formal agreements with the TSO. These agreements require the TSO to interconnection agreement or protocol that    notify IPEC as soon as practicable per good utility practice, upon receipt of a potential post-trip degraded ensures adequate communication and            voltage alarm.
coordination between the NPP licensee and the TSO, describe whether this agreement or protocol requires that you be promptly notified when the conditions of the surrounding grid could result in degraded voltage (i.e., below TS nominal trip setpoint value requirements; including NPP licensees using allowable value in its TSs) or LOOP after a trip of the reactor unit(s).
I(g) Describe the low switchyard voltage    These are the Switchyard voltage conditions that will initiate operation of IPEC degraded voltage protection conditions that would initiate operation of  i. 138 kv Offsite Power Source <133kv plant degraded voltage protection.            ii. 13.8kv Offsite Power Source <13.4kv Note: The design of these systems is described in front of this attachment.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 7 of 26
: 2. Use of criteria and methodologies to assess whether the offsite power system will become inoperable as a result of a trip of your NPP.
2(a) Does your NPP's TSO use any            Yes. The TSO, uses a State Estimator and a Contingency Evaluation Program to analyze analysis tools, an online analytical        real time and contingency voltage levels and thermal loading for IPEC 138kV off-site transmission system studies program, or sources.
other equivalent predictive methods to determine the grid conditions that would    The 138kV transmission system program and related actions are summarized as follows:
make the NPP offsite power system inoperable during various                      Real-Time Contingency Analysis Program: The program and related actions are contingencies?                                  summarized as follows; the program utilizes real-time transmission system information If available to you, please provide a brief    and nuclear generating unit specific shutdown loads and minimum voltage description of the analysis tool that is        requirements. The program creates a model by combining real-time telemetry with used by the TSO.                                the network model. The network model includes the nuclear power plant facilities.
The State Estimator is then used to provide a consistent power flow that is used to run the contingencies. The contingency case assumes the simultaneous loss of the generator and the addition of load at the appropriate bus. An alarm is issued if the prescribed voltage limits are violated.
The 13.8kV distribution system is monitored on a real-time voltage basis. If the voltage drops below a predetermined 13.8kV system voltage value, IPEC is notified. This approach is determined to be acceptable because the 13.8kV off-site source is a manually aligned supply and the predetermined notification value is at the lower limit of the 13.8kV systems normal voltage schedule. Therefore, the TSO will make all reasonable efforts to maintain the voltage schedule.
2(b) Does your NPP's TSO use an            Yes. The TSO uses the real-time analysis tool described in 2(a), in conjunction with analysis tool as the basis for notifying    procedures, as the basis for determining when conditions warrant IPEC notification of the the NPP licensee when such a condition      138kV system.
is identified? If not, how does the TSO determine if conditions on the grid        As described above the TSO use real-time voltage monitoring, in conjunction with warrant NPP licensee notification?          procedures, as basis to determining when conditions warrant IPEC notification of the 13.8kV system.
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043
                                                                              --  -                                    Page 8 of 26 II yOum J  I  vJ UQ~Oc am CA am mGl yoia LvuI, l
I 'es. IFI        S aIai-Liine          ayaiSis ivoi for ihe i35KV, in conjunction witn i-'E; plant load would the analysis tool identify a                  flow studies, have the capability to determine if the trip of their IPEC plants would result in condition in which a trip of the NPP                a switchyard voltage which would actuate the associated unit's degraded voltage would result in switchyard voltages                protection logic and initiate separation from the offsite power source.
(immediate and/or long-term) falling below TS nominal trip setpoint value                The 13.8kV source is a manually aligned distribution system, which the TSO has local requirements (including NPP licensees              resources available to adjust system voltage. Prior to IPEC aligning the 480VAC safety using allowable value in its TSs) and              buses to the 13.8 kV system (via the 6.9 kV system), communication between the TSO consequent actuation of plant degraded              and IPEC is required to ensure the adequacy of the 13.8 kV system voltage to support voltage protection?                                accident loads.
If not, discuss how such a condition would be identified on the grid.
2(d) If your TSO uses an analysis tool,            The TSO 138kV real-time analysis tool presently resolves the IPEC Unit 2 and IPEC Unit how frequently does the analysis tool              3 trip contingencies every minute for the steady state conditions.
program update?
2(e) Provide details of analysis tool-              The 138kV IPEC Unit 2 and IPEC Unit 3 contingencies results (see response to item 2(a))
identified contingency conditions that              are automatically compared to off-site post trip voltage limits. If any limit is violated, an would trigger an NPP licensee                        alarm is generated and IPEC is notified if not cleared after 30 minutes notification from the TSO.
2(f) If an interface agreement exists              Yes. IPEC would be notified by the TSO when:
between the TSO and the NPP licensee, does it require that the NPP licensee be
* When all three 138 kV monitoring and alarm systems are out of service and have notified of periods when the TSO is                            not been restored within 30 minutes.
unable to determine if offsite power
* When the 13.8 kV monitoring and alarm systems are out of service and have not voltage and capacity could be                                  been restored within 30 minutes.
inadequate?
Loss of the voltage prediction tool alone has no impact on operability. If notified by the If so, how does the NPP licensee                    TSO that the Low Voltage Contingency Alarm is inoperable, then the IPEC Operators determine that the offsite power would              perform the following:
remain operable when such a                              1. Contact the TSO once per shift to verify imminent/expected degraded voltage notification is received?                                      conditions do not exist.
l      2. Minimize      large electrical load changes
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 9 of 26 li]Zs1Me  g                                I M5    M-. . M                                                                          M J. Mtintraize iutaidriance and testing of the electrical distribution system.            i
: 4. Terminate maintenance or testing on critical components of the electrical distribution system as soon as possible.
: 5. Limit MVAR Output (OP2 only) 2(g) After an unscheduled inadvertent          No. Verification of the post trip 138kV switchyard voltage real-time analysis results against trip of the NPP, are the resultant              actual post trip voltage is not performed. Since the real-time analysis tool uses real time switchyard voltages verified by                system data and assumed worst case station loads a comparison of values would be procedure to be bounded by the                  difficult even if the real-time analysis predicted values were available which they are not; voltages predicted by the analysis tool?
2(h) If an analysis tool is not available to    This question is not applicable to IPEC. The TSO has a real-time analysis tool presently in the NPP licensee's TSO, do you know if          use for the 138kV system as discussed above.
there are any plans for the TSO to obtain one? If so, when?                        The TSO has no plans to install a real-time contingency monitor for the 13.8 kV off-site power source.
2(i) If an analysis tool is not available,      Not Applicable for the 138kV transmission lines, TSO uses real-time analysis tool as does your TSO perform periodic studies          discussed above.
to verify that adequate offsite power capability, including adequate NPP post-        IPEC performs periodic station load flow studies to ensure that the minimum 13.8kV trip switchyard voltages (immediate            scheduled voltage is adequate to support voltage requirements.
and/or long-term), will be available to the NPP licensee over the projected timeframe of the study?
(a) Are the key assumptions and parameters of these periodic studies translated into TSO guidance to ensure that the transmission system is operated within the bounds of the analyses?
(b) If the bounds of the analyses are exceeded, does this condition trigger the notification provisions discussed in question 1 above?
[l      ______                                I  ___                ___________
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 we]
S
* tii.!
I  I-.  ..
I M*1111 P-r  --
AA  ! t! _  e- -
Page IUof26                I.
I  -  /i\  shoe    I  WS    I OWL LW7, IJI 7LDU UV  iivti apPICIavult: I  I O0KV arIU 13.0 KV Oystems i
not have access to the results of an analysis tool, or your TSO does not perform and make available to you periodic studies that determine the adequacy of offsite power capability, please describe why you believe you comply with the provisions of GDC 17 as stated above, or describe what compensatory actions you intend to take to ensure that the offsite power system will be sufficiently reliable and remain operable with high probability following a trip of your NPP.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 11 of 26 W~      0 1'lll 3.Use of criteria and methodologies to-assess whether the NPP's offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.
3(a) If the TSO notifies the NPP            IPEC would declare the 138kV off-site source "inoperable". The TSO has real-time operator that                                monitor capability for the 138kV source and IPEC is notified by the TSO if the loss of the unit would result in an unacceptable off-site post-trip voltage. There are no identified
* a trip of the NPP, or              system conditions where the loss of a transmission line or large supply would result in the
* the loss of the most critical      trip of the generator.
transmission line or
* the largest supply to the grid would result in switchyard voltages (immediate and/or long-term) below TS nominal trip setpoint value requirements (including NPP licensees using allowable value in its TSs) and would actuate plant degraded voltage protection, is the NPP offsite power system declared inoperable under the plant TSs? If not, why not?                    3(b) If onsite safety-related equipment      IPEC is not designed for double sequencing events. LOCA with a Delayed LOOP is (e.g., emergency diesel generators or        outside the design basis for both IP2 and IP3.
safety-related motors) is lost when subjected to a double sequencing (LOCA with delayed LOOP event) as a result of the anticipated system performance and is incanihie of performing its safety functions as a
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 12 of 26 I _SUIL e'=,
          %J;IsV-0JU ju n IVLJ al 1I W IIC!J llcy I". !-      in
                                                              '    M actuation signal during this condition, is the equipment considered inoperable?
If not, why not?
3(c) Describe your evaluation of onsite        Indian Point Units 2 and 3 are designed to a GDC that postulates a LOCA concurrent with safety-related equipment to determine          a LOOP. Neither plant models a LOCA with Delayed LOOP scenario in its voltage profile whether it will operate as designed            and loading analyses, because this event is outside the design basis of both units.
during the condition described in question 3(b).
3(d) If the NPP licensee is notified by        This condition is addressed by our site procedures. Under these circumstances we would the TSO of other grid conditions that          enter the applicable site procedure for offsite power continuous monitoring and may impair the capability or availability      notification, a Technical Specification action statement would not be entered until an of offsite power, are any plant TS action      applicable system, structure or component was declared inoperable.
statements entered? If so, please identify them.
3(e) If you believe your plant TSs do not      Not applicable.
require you to declare your offsite power      Based on responses, we declare offsite power or applicable equipment inoperable under system or safety-related equipment            circumstances as described above.
inoperable in any of these circumstances, explain why you believe you comply with the provisions of GDC 17 and your plant TSs, or describe what compensatory actions you intend to take to ensure that the offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.
3(f) Describe if and how NPP operators        The Licensed Operators have been trained on the applicable site procedure for offsite are trained and tested on the                power continuous monitoring and notification. This procedure contains the requirements compensatory actions mentioned in your        for declaring off-site power inoperable and entering the appropriate Technical answers to questions 3(a) through (e).        Specifications.
For events such as LOCAs followed later hy a I nap event the    Opnnraors confinuing training includes the sequencing or manual loading of safeguards equipment. The
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 13 of 26 le _I! *-  II  ; *  ! ! e I
I          McUiMe111iiL to IIIrIIudiIy Iad safeguards equipment is contingent on whether or not tile Safeguards signal has been reset. The site's Westinghouse owner's group Emergency Operating Procedures address these situations. The licensed operators are tested on these procedures and in dynamic simulator evaluations, as applicable.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 14of26 WIinISTAJ*WAO
: 4. Use of criteria and methodologies to assess whether the offsite power system will remain operable following a trip of your NPP.
4(a) Do the NPP operators have any          Yes, procedural guidance for abnormal situations related to this equipment is available to guidance or procedures in plant TS          IPEC operators in Annunciator Response Procedures.
bases sections, the final safety analysis report, or plant procedures regarding      The operators are trained and tested on systems such as the main generator voltage situations in which the condition of plant- regulator and tap changers.
controlled or -monitored equipment (e.g., voltage regulators, auto tap changing transformers, capacitors, static VAR compensators, main generator voltage regulators) can adversely affect the operability of the NPP offsite power system? If so, describe how the operators are trained and tested on the guidance and procedures.
4(b) If your TS bases sections, the final  Not applicable.
safety analysis report, and plant procedures do not provide guidance regarding situations in which the condition of plant-controlled or -
monitored equipment can adversely affect the operability of the NPP offsite power system, explain why you believe you comply with the provisions of GDC 17 and the plant TSs, or describe what actions you intend to take to provide such guidance or procedures.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 15 of 26 Use of NPP licensee/TSO protocols and analysis tool by TSOs to assist NPP licensees in monitoring grid conditions for consideration in maintenance risk assessments The Maintenance Rule (10 CFR 50.65(a)(4)) requires that licensees assess and manage the increase in risk that may result from proposed maintenance activities before performing them.
: 5. Performance of grid reliability evaluations as part of the maintenance risk assessments required by 10 CFR 50.65(a)(4).
5(a) Is a quantitative or qualitative grid    Yes reliability evaluation performed at your NPP as part of the maintenance risk            IPEC performs qualitative risks assessment as required by 10 CFR 50.65 and IPEC assessment required by 10 CFR                  Plant Technical Specification. The program is implemented by IPECNPP On-Line Risk 50.65(a)(4) before performing grid-risk-      Assessment and Outage Risk Assessment procedures.
sensitive maintenance activities? This        These procedures require plant risk assessment before removing equipment from includes surveillances, post-maintenance service for planned maintenance activities, or upon discovery of equipment out of service testing, and preventive and corrective        that is unplanned.
maintenance that could increase the probability of a plant trip or LOOP or        The IPECNPP On-Line Risk Assessment procedure requires an evaluation of current impact LOOP or SBO coping capability,          and anticipated grid conditions before removing risk significant equipment from service.
for example, before taking a risk-            The Equipment Out of Service (EOOS) Monitor is a computer based program that is significant piece of equipment (such as        used to calculate Core Damage Frequency and conditional Core Damage Frequency for an EDG, a battery, a steam-driven pump, the plant equipment configuration and testing activities for both planned and unplanned an alternate AC power source)                  configurations.
out-of-service?                                The IPECNPP Work Management procedure requires a risk plan development for activities that would increase grid instability in combination with external events.
5(b) Is grid status monitored by some          Yes means for the duration of the grid-risk-sensitive maintenance to confirm the continued validity of the risk assessment and is risk reassessed when warranted?
If not, how is the risk assessed during
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 16 of 26 WE  .    !!S**!i.                                            --  "  -
I  -;-  J  _., -s - --  &.._  __:-    -- -    - - n H41 u1-1f-0 ;>1o 10LV ;> tic 1 fl  1 lsL    Fa1 1VV
                                                      -I.
5(c) Is there a significant variation in the            Yes stress on the grid in the vicinity of your              The NYISO Reliability Coordination Area is a summer peaking area. Due to high intra NPP site caused by                                      area and inter area power flows, it would be expected that the grid would be stressed.
However, this stress is managed through facility maintenance coordination. During the seasonal loads                                          summer peak season scheduled transmission facility maintenance is avoided in June, July and August if possible.
or Anytime that maintenance is scheduled, the schedules are managed in order to maintain maintenance activities associated with                  operation of the bulk power system within established operating criteria.
critical transmission elements?
Is there a seasonal variation (or the                    No, based on the limited number of LOOP occurrences in the NYISO region over the potential for a seasonal variation) in the              past 10 years, no seasonal variation can be established. IPEC last experienced a LOOP frequency in the local transmission                transmission system related LOOP on August 14, 2003.
region?
If the answer to either question is yes, discuss the time of year when the variations occur and their magnitude.
5(d) Are known time-related variations in                No. However, Con Edison the TSO by procedure does not schedule feeder outages the probability of a LOOP at your plant                  between May 1 and September 15 due to summer loading concerns. IPEC will not site considered in the grid-risk-sensitive              schedule maintenance activities during this time. IPEC will schedule emergent activities maintenance evaluation? If not, what is                  to address issues that could pose a threat to grid stability.
your basis for not considering them?
5(e) Do you have contacts with the TSO                  Yes.
to determine current and anticipated grid conditions as part of the grid reliability              TSO Communication contacts are available for assessment of grid conditions before and evaluation performed before conducting                  during the performance of grid-risk sensitive maintenance activities.
grid-risk-sensitive maintenance activities?
5(f) Describe any formal agreement or                    Site level procedures provide the guidance on scheduling. The procedure for protocol that you have with your TSO to                  performance of the offsite power continuous monitoring and notification contains assure that you are promptly alerted to a                  jguidelines for risk management of feeder outages. This would include the ability to
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 IMMUNE~)Page                                                                                  17 of26 us.,                        -S.        -I l...-  - -n -__
VV'jIQVI III
_-. A__L        A __, ,
UalIU .,UIIUILIuII tIaL IdL t II y
CIIyI l
restiict wor'Korku feoeers iquriiiiit oi q    deum  o U WIairitefrince      on grid equipment. Tne Hiant during a maintenance activity.                            models grid feeder outage in the risk assessment Program EOOS.
Notification occurs whether or not maintenance is on-going. The TSO is required to notify IPEC whenever an impaired or potentially degraded grid condition is recognized by the TSO. Specific examples of known potentially degrading conditions identified in the agreement include:
: 1. De-energizing, switching or in-service work on critical transmission lines.
: 2. Potentially damaging inclement weather.
: 3. Solar Magnetic Disturbances.
: 4. Post-contingency voltage alarm for the 138kV transmission system after 30-minutes.
: 5. A real-time 13.8kV degraded voltage condition below a normal system schedule voltage after 30-minutes.
: 6. Prior to any 138kV feeder outage which could impact IPEC being removed or restored to service
: 7. When the TSO 138kV or 13.8kV monitoring and alarm capability are out of service and have not been restored after 30-minutes.
: 8. Other system or equipment conditions determine by the TSO to be of importance to IPEC.
5(g) Do you contact your TSO periodically Yes.
for the duration of the grid-risk-sensitive              Additionally the TSO is contacted before the start of grid- risk sensitive maintenance maintenance activities?                                activities and at the completion of the activity. Changes to grid conditions are communicated to IPEC as stated in 5(f).
5(h) If you have a formal agreement or                  The formal agreement with the System Operator at IPEC is described in the offsite protocol with your TSO, describe how                    power continuous monitoring and notification station procedure. This procedure NPP operators and maintenance                          establishes monitoring, and notification responsibilities of the Buchanan Substation, as personnel are trained and tested on this                well as the interface between the IPEC and Con Edison's Energy Control Center. The formal agreement or protocol.                            Licensed Operators have had training on this procedure. The most recent training occurred in Cycle 3 of 2005.
____There                                                          was no testing associated with this training.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 18 of 26 56.6                  0~            M-                                                                      I Maintenance personnel do not have training on this agreement or procedure because Operations and Work Control assess the risk and conditions for performing maintenance activities.
5(i) If your grid reliability evaluation,  Not applicable.
performed as part of the maintenance risk assessment required by 10 CFR 50.65(a)(4), does not consider or rely on some arrangement for communication with the TSO, explain why you believe you comply with 10 CFR 50.65(a)(4).
: 50) If risk is not assessed (when          Not applicable warranted) based on continuing communication with the TSO throughout the duration of grid-risk-sensitive maintenance activities, explain why you believe you have effectively implemented the relevant provisions of the endorsed industry guidance associated with the maintenance rule.
5(k) With respect to questions 5(i) and    Not applicable. No alternative actions required.
50), you may, as an alternative, describe what actions you intend to take to ensure that the increase in risk that may result from proposed grid-risk-sensitive activities is assessed before and during grid-risk-sensitive maintenance activities, respectively.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 19of26
: 6. - Use of risk assessment results, including the results of grid reliability evaluations, in managing maintenance risk, as required by 10 CFR 50.65(a)(4).            -- - .
TSO does grid reliability evaluations; not NPPs. ugrid reliability evaluations" Enter AP, if notified un-normality on grid.
6(a) Does the TSO coordinate                  Yes.
transmission system maintenance                The TSO coordinates all scheduled work activities with the plant. The Process is activities that can have an impact on the      described in site level procedures.
NPP operation with the NPP operator?
6(b) Do you coordinate NPP                    Yes.
maintenance activities that can have an        IPEC coordinates all scheduled work activities with the TSO. The plant process is impact on the transmission system with        described in site procedures.
the TSO?
6(c) Do you consider and implement, if        Yes.
warranted, the rescheduling of grid-risk-      IPEC will reschedule activities as required to prevent challenging the stability of the local sensitive maintenance activities              Grid. This would include activities which would likely cause plant trip or loss of off site (activities that could (i) increase the        power. Guidance is described in site procedures. If the Grid voltage degrades to a point likelihood of a plant trip, (ii) increase      where it challenges the NPP, the TSO will immediately correct it or notify the IPEC Control LOOP probability, or (iii) reduce LOOP        room operators. IF emergent equipment outage occurs the TSO will notify the control or SBO coping capability) under                room. The Switchyard coordinator or lead system engineer will be notified. A risk existing, imminent, or worsening              assessment evaluation will be performed and if applicable, restrict feeders as required.
degraded grid reliability conditions?
6(d) If there is an overriding need to        Yes.
perform grid-risk-sensitive maintenance        Guidance is described in site procedures. The Switchyard coordinator or lead system activities under existing or imminent          engineer will be notified. A risk assessment evaluation will be performed and if applicable conditions of degraded grid reliability, or restrict feeders as required.
continue grid-risk-sensitive maintenance when grid conditions worsen, do you            Additionally, mitigative actions such as feeder restrictions and protected equipment will be implement appropriate risk management implemented.
actions? If so; describe the actinnq that you would take. (These actions could        l
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 20 of 26 f.
Include adteai-iel I    quipi mer it pi vzuttutI I
                                                .!    --.      -i:                                                                          Iss and compensatory measures to limit or minimize risk.)
6(e) Describe the actions associated            Emergent maintenance or declining grid condition guidance is described in site with questions 6(a) through 6(d) above          procedures. The operator will perform appropriate actions as required by Technical that would be taken, state whether each        Specifications. The Switchyard Coordinator or Lead System Engineer will be notified.
action is governed by documented                They will perform a risk evaluation and if applicable restrict feeders as required. The procedures and identify the procedures,        feeder or equipment outage will be run through the plant risk program. These actions are and explain why these actions are              required by Procedure and must be performed.
effective and will be consistently accomplished.
6(f) De scribe how NPP operators and            The Licensed Operators and Work Control Personnel at IPEC were provided training on maintenance personnel are trained and          the applicable procedure that addresses Offsite Power Continuous Monitoring and tested to assure they can accomplish            Notification. This procedure establishes monitoring, and notification responsibilities of the the actions described in your answers to        Buchanan Substation, as well as the interface between the IPEC and Con Edison's question 6(e).                                Energy Control Center. The most recent training occurred in Cycle 3 of 2005.
There was no testing associated with this training.
6(g) If there is no effective coordination    Not applicable between the NPP operator and the TSO regarding transmission system maintenance or NPP maintenance activities, please explain why you believe you comply with the provisions of 10 CFR 50.65(a)(4).
6(h) If you do not consider and                Not applicable effectively implement appropriate risk management actions during the conditions described above, explain why you believe you effectively addressed the relevant provisions of the associated NRC-endorsed industry guidance.
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 21 of 26 I us s&#xa3;                              I -P  i;,:    -l, V(i) You miiay, as an aiternailve LO      Not appilcaDie. No alternative actions required.
questions 6(g) and 6(h) describe what actions you intend to take to ensure that the increase in risk that may result from grid-risk-sensitive maintenance activities is managed in accordance with 10 CFR 50.65(a)(4).
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 22 of 26 I .. Ue                                  U              -
Offsite power restoration procedures in accordance with 10 CFR 50.63 as developed in Section 2 of RG 1.155 Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.
7.-Pibcedures for identifying local power sources' that could be made available to resupply your plant following a LOOP event.
Note: Section 2, 'Offsite Power," of RG 1.155 (ADAMS Accession No. ML003740034) states:
Procedures should include the actions necessary to restore offsite power and use nearby power sources when offsite power is unavailable. As a minimum, the following potential causes for loss of offsite power should be considered:
- Grid under-voltage and collapse
- Weather-induced power loss
- Preferred power distribution system faults that could result in the loss of normal power to essential switchgear buses 7(a) Briefly describe any agreement            IPEC has no agreement with local power sources. The NYISO and the TSO have made with the TSO to identify local            restoration plans which identify how power will be restored to the NPPs as a priority load.
power sources that could be made              The TSO is responsible for coordinating the restoration of off-site power to the NPP. The available to re-supply power to your          NPP is considered a critical facility and restoration of power is a priority.
plant following a LOOP event.
4 7(b) Are your NPP operators trained and        Yes.
tested on identifying and using local          Continuing Licensed Operator Re-qualification Training includes electrical bus and power power sources to resupply your plant          supply training. Also included is training on applicable Abnormal Operating procedures, following a LOOP event? If so, describe        which address re-energizing plant electrical systems following a LOOP.
how.
I    This includes items such as nearby or onsite gas turbine generators, portable generators, hydro generators, and black-smttZOI
                      *I..MIJVwII EVICTSILO.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 23 of 26 g!le t.
7(c) if you nave not established an      !
                                              .-    MIa Not appiicabie.
I agreement with your plant's TSO to identify local power sources that could    The NYISO has agreements with area black-start capable units in accordance with NYISO be made available to resupply power to    bulk power restoration plan. The NYISO restoration plan identifies restoring power to the your plant following a LOOP event,        NPPs as a priority, and the TSO is responsible for coordinating the restoration of off-site explain why you believe you comply with    power to the NPP. The NPP is considered a critical facility and restoration of power is a the provisions of 10 CFR 50.63, or        priority.
describe what actions you intend to take to establish compliance.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 24 of 26 Losses of offsite power caused by grid failures at a frequency of equal to or greater than once in 20 site-years in accordance with Table 4 of Regulatory Guide 1.155 for complying with 10 CFR 50.63 Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.
: 8. Maintaining SBO coping capabilities in accordance with 10 CFR 50.63.
8(a) Has your NPP experienced a total      Yes, a LOOP caused by grid failure occurred during August 2003.
LOOP caused by grid failure since the plant's coping duration was initially determined under 10 CFR 50.63?
8(b) If so, have you reevaluated the        No. See additional information in the response to Question 8(d) below.
NPP using the guidance in Table 4 of RG 1.155 to determine if your NPP should be assigned to the P3 offsite power design characteristic group?
8(c) If so, what were the results of this  Both Units 2 and 3 remain 8 hour coping plants.
reevaluation, and did the initially determined coping duration for the NPP need to be adjusted?
8(d) If your NPP has experienced a total Per RG 1.155 Table 4, Sites that expect to experience a total loss of offsite power caused LOOP caused by grid failure since the      by grid failures at a frequency equal to or greater than 20 site-years are considered to be plant's coping duration was initially      an Offsite Power Design Characteristic Group 'P3", unless the site has a procedure to determined under 10 CFR 50.63 and          recover AC power from reliable alternate (non-emergency) AC power sources within has not been reevaluated using the          approximately one-half hour following a grid failure are considered.
guidance in Table 4 of RG 1.155, explain why you believe you comply with Both IP2 and IP3 are already considered as Offsite Power Design Characteristic UP3" with the provisions of 10 CFR 50.63 as          8 hour coping duration. This classification already accounts for a frequency of grid related stated above, or describe what actions      loss of offsite power events greater than once per 20 years. Therefore, no reevaluation of you intend to take to ensure that the      coping time for either plant is required as a result of a LOOP subsequent to existing NPP maintains its SBO coping                evaluations.
capabilities in accordance with 10 CFR l_l
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 25 of 26 geM  -_:  ro -S _ _.
The IP-RTP-04-00811 Station Blackout Report (Tenera Report), dated March 1990 documents IP2 as Offsite Power Design Characteristic 'P3" with an 8 hour coping duration. This is based on past loss of offsite experience at the site, the probabilities of severe weather, and the independence of offsite power supplies. The factor used for determining coping duration is the high EDG reliability. A target reliability of 0.95 gives IP2 a coping duration category of 8 hours.
Indian Point Unit 3 NRC Letter Docket No 50-286, dated June 9, 1992 Supplemental Safety Evaluation (SSE)
Station Blackout Rule 10 CFR 50.63 states IP3 is an Offsite Power Design Characteristic
    'P3" with a minimum required coping duration of 8 hours.
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 26 of 26 Actions to ensure compliance 9: If y-ou-determine th-at any-actio-n is-warranted to bring your NPP into compliance with NRC regulatory requirements, including TSs, GDC 17, 10 CFR 50.65(a)(4), 10 CFR 50.63, 10 CFR 55.59 or 10 CFR 50.120, describe the schedule for implementing it.
Areas of non-compliance were entered in the Corrective Action Process and will drive the actions necessary to implement changes to bring the condition into compliance and will include a detailed schedule.
CR-IP2-2006-01450 was initiated to change operations procedure to give the Operators direct guidance that when notified by the TO of the Real-time Contingency Analysis (RTCA) alarm, the Offsite Power Supply will be Inoperable and TS actions will be entered. Additionally, the 133kV criteria will be deleted from the procedure.}}
 
=Text=
{{#Wiki_filter:Entergy Nuclear Northeast Indian Point Energy Center 450 Broadway, GSB IEnlerg  <y 0                                                P.O. Box 249 Buchanan,  NY 10511-0:249 Tel 914 734 6700 Fred Dacimo Site Vice President Administration April 3, 2006 Re: Indian Point Units 2 & 3 Dockets 50-247 & 50-286 NL-06-043 U.S. Nuclear Regulatory Commission ATTN:Document Control Desk 115!55 Rockville Pike Rocville, Maryland 20852
 
==Subject:==
Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power
 
==Reference:==
: 1. NRC Generic Letter 2006-02, GridReliability and the Impact on Plant Risk and the Operabilityof Offsite Power, dated February 1,2006
 
==Dear Sir or Madam:==
 
The NRC issued Generic Letter 2006-02 (Reference 1) to request information for determining compliance with regulatory requirements governing electric power sources. Specifically, the NRC is requesting information regarding (1) use of protocols between the nuclear power plant (NP]') and the transmission system operator (TSO), independent system operator (ISO), or reliability coordinator/authority (RC/RA) including transmission load flow analysis tools (analysis tools) by TSOs to assist NPPs in monitoring grid conditions to determine the operability of offsite power systems under plant Technical Specification (TS); (2) use of NPP/TSO protocols and analysis tools by TSOs to assist NPPs in monitoring grid conditions for consideration in maintenance risk assessments; (3) offsite power restoration procedures in accordance with Section 2 of NRC Regulatory Guide (RG) 1.155, "Station Blackout;" and, (4) losses of offsite power caused by grid failures at a frequency equal to or greater than once in 20 site-years in accordance with RG 1.155. The requested information is being provided under the requirements of 10 CFR 50.54(f).
Attaihment 1 to this letter provides the Entergy Nuclear Operations, Inc. (ENO) response for Indian Point Unit 2 and 3 to Generic Letter 2006-02. Generic Letter 2006-02 discusses compliance with General Design Criterion (GDC) 17 and several other 10CFR50 requirements in several locations. The exact extent of the compliance of IP2 and IP3 to the GDC are desc:ibed in each plant's Updated Final Safety Analysis Report.
A4{/
 
Sorae of the questions in Generic Letter 2006-02 seek information, procedures and activities concerning grid reliability which is provided by the TSO and/or ISO. ENO has not independently verified all information provided by:
* New York Independent System Operator
* Consolidated Edison Company of New York, Inc.
Thi; letter contains no new commitments. Should you or your staff have any questions regarding this response, please contact Mr. Patric W. Conroy, Manager, Licensing at (914) 734-6668.
I declare under penalty of perjury that the foregoing is true and correct. Executed on
          ;3    2006.
V      ru styours, R. Dacimo Site Vice President Indian Point Energy Center : Response to Generic Letter 2006-02, Grid Reliability and the Impact On Plant Risk and the Operability of Offsite Power cc:
Mr. Samuel J. Collins, Regional Administrator, Region I Mr. John Boska, NRR Senior Project Manager IPEC NRC Resident Inspector's Office, Indian Point Unit 2 IPEC NRC Resident Inspector's Office, Indian Point Unit 3 Mr. ?aul Eddy, New York State Department of Public Service Mr. Peter R. Smith, President NYSERDA
 
Attachment 1 to NL-06-043 RESPONSE TO GENERIC LETTER 2006-02, GRID RELIABILITY AND THE IMPACT ON PLANT RISK AND THE OPERABILITY OF OFFSITE POWER (26 Pages)
ENTERGY NUCLEAR OPERATIONS, INC.
Indian Point Nuclear Generating Unit No. 2 Docket No. 50-247 Indian Point Nuclear Generating Unit No. 3 Docket No. 50-286
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page I of 26 Note The following provides a description of the IPEC off-site power system at Indian Point.
Unit 2: Offsite power is supplied from the offsite transmission network to the plant by two electrically and physically separated circuits (a 138kV circuit and a 13.8kV circuit). All offsite power enters the plant via 6.9kV buses Nos. 5 and 6 which are normally connected to the 138kV offsite circuit but have the ability to be connected to the 13.8kV offsite circuit. The 138kV offsite circuit satisfies the requirement in GDC 17 that at least one of the two required circuits can, within a few seconds, provide power to safety-related equipment following a loss-of-coolant accident. The 13.8kV offsite circuit is considered a delayed access circuit because operator action is normally required to supply offsite power to the plant using the 13.8kV offsite source.
Unit 3:Offsite power is supplied to the plant from the transmission network by two electrically and physically separated circuits, the 138kV or normal circuit and the 13.8kV or alternate circuit. Each of the offsite circuits from the Buchanan substation into the plant is required to be supported by a physically independent circuit from the offsite network into the Buchanan substation. All offsite power enters the plant via 6.9kV buses Nos. 5 and 6 which are connected to the 138kV (normal) offsite circuit and have the ability to be connected to the 13.8kV (alternate) offsite circuit. The arrangement satisfies the requirement that at least one of the two required circuits can within a few seconds; provide power to safety-related equipment following a loss-of-coolant accident. Operator action is required to supply offsite power to the plant using the 13.8kV (alternate) offsite source.
The key points to highlight here are as follows:
: 1. Both units' safeguards loads are powered from the 480V System. The connection to the offsite 138kV and 13.8kV circuits are via the six buses of the 6.9kV System. The arrangement of these six 6.9kV buses allows various alignments to both the 138kV and 13.8kV system and the 480V safeguards buses follow these alignments accordingly. Two of the six 6.9kV buses and consequently two of the associated 480V safeguards trains are directly connected to the 138kV offsite circuit, but can also be connected to the 13.8kV offsite circuit via manual transfer.
: 2. As described above, both units have two of the three available trains of safeguards loads connected directly to the preferred offsite circuit (138kV), via two of the six buses of the 6.9kV System, during normal operation and as such, there is no transfer action involved. Normal operation includes start-up, hot shutdown, cold shutdown, etc. The third train would be auto-transferred to the preferred offsite circuit during a unit trip from power operation (Mode 1) condition. Both plants design basis requires two of three safeguards trains to mitigate a loss of coolant accident.
: 3. There is no auto-transfer to the alternate 13.8kV offsite circuit from the 138kV circuit. This transfer, when needed, is manually performed at the 6.9kV System voltage level, and controlled by plant operating procedures. The procedures call for the Transmission Owner (TO)
(i.e., ConEd) to be notified whenever the 13.8kV offsite circuit is to be used for plant operating load. This is because the 13.8kV offsite circuit is a local distribution circuit that also powers residential and commercial loads and the TO maintained voltage level is based on the load on the circuit. The higher the load, the higher the voltage that the TO maintains. The 13.8kV offsite circuit is controlled by a TO procedure and based on the load on the circuit, the circuit voltage is set accordingly. The lowest specified voltage permitted on this circuit is 13.4KV. TO notifications (to and from IPEC) are based on this value as well.
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 2 of 26 Roth the I 3RIA/            ~
and the I13.R.A/! cir-uine are m0nfit^Ir by bi                            Siaiiur- procedures. However only the 138kV offsite circuit is monitored by the On-line AC Contingency Monitoring Program. The 13.8kV offsite circuit is monitored by the TO from its Energy Control Center via a Real-time State Estimator (RTISE) Voltage Profile display. This display provides voltage monitoring and alarming functions and the operations procedure contains the necessary notification responsibilities and notification voltages for both the 138kV and 13.8kV offsite circuits.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 3 of 26 r.MWAT*VMAI Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA and the use of analysis tools by TSOs to assist NPP licensee in monitoring grid conditions to determine the operability of offsite power systems under plant TS.
GDC 17, 10 CFR Part 50, Appendix A, requires that licensees minimize the probability of the loss of power from the transmission network given a loss of the power generated by the nuclear power unit(s).
: 1. Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA to assist the NPP licensee in monitoring grid conditions to determine the operability of offsite power systems under plant TS.
I(a) Do you have a formal agreement or protocol with your TSO?                          In the New York Reliability Coordinator Area the New York Independent System Operator (NYISO) has operational authority over the bulk power system. The Transmission Owners (TO) have operational authority over the non-bulk power system. The NYISO operates the bulk power system in accordance with NERC, NPCC and New York State Reliability Council (NYSRC) criteria. Established communications protocols are between the NYISO and the Transmission Owners (TO). Communications to the generating resources are through the TOs. The associated TO monitors the localized grid conditions and coordinates issues such as off site power operability with the NPP. In this document TSO refers to the TO.
Yes, IPEC has a number of formal agreements with the NYISO and TOs (which also performs the TSO function for IPEC as follows:
* IPEC Unit 3 Interconnection Agreement with the Consolidated Edison Company of New York, Inc.
(Con Ed)
* IPEC Unit 2 Indian Point Continuing Site Agreement with Consolidated Edison Company of New York, Inc.
* The New York State Transmission Tariffs with the NYISO
* NYISO Customer & Guest Application Form of Service Agreement for NYISO Market Administration and Control Area Service Tariff
* Transaction Form between Entergy-IPEC and Con Edison for 138kV and 13.8kV monitoring and notification services The NYISO and TSO agreements require all parties to operate per NYISO and/or TSO procedures and documents, therefore the NYISO and TSO procedures and documents are considered part of the formal agreements.
Compliance with GDC-17, as documented in the IPEC license basis and plant Technical Specifications, is not
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 4 of 26 II                                *I.
picuicatcu on such an agreemeni.
I (b) Describe any grid conditions that would      The TSO is required to notify IPEC as soon as practical per good utility practice whenever an impaired or trigger a notification from the TSO to the        potentially degraded grid condition is recognized by the TSO. Specific examples of known potentially NPP licensee and                                  degrading conditions identified in the agreement include:
: 1. De-energizing, switching or in-service work on critical transmission lines if there is a time period required for the              2. Potentially damaging inclement weather notification                                            3. Solar Magnetic Disturbances
: 4. Post-contingency voltage alarm for the 138kV transmission system after 30-minutes.
: 4. Post-contingency voltage alarm for the 138kV transmission system after 30-minutes.
: 5. A real-time 13.8kV degraded voltage condition below a normal system schedule voltage after 30-minutes 6. Prior to any 138kV feeder, which could impact IPEC being removed or restored to service 7. When the TSO 138kV or 13.8kV monitoring and alarm capability are out of service and have not been restored after 30-minutes.
: 5. Areal-time 13.8kV degraded voltage condition below a normal system schedule voltage after 30-minutes
: 8. Other system or equipment conditions determine by the TSO to be of importance to IPEC.I (c) Describe any grid conditions that would cause the NPP licensee to contact the TSO.Describe the procedures associated with such a communication.
: 6. Prior to any 138kV feeder, which could impact IPEC being removed or restored to service
If you do not have procedures, describe how you assess grid conditions that may cause the NPP licensee to contact the TSO.Grid conditions and status are the primary responsibility of ISO and TSO.Relative to this question, "grid conditions' is assumed to be IPEC changes that impact the TSO real-time post contingency analysis capability.
: 7. When the TSO 138kV or 13.8kV monitoring and alarm capability are out of service and have not been restored after 30-minutes.
IPEC typically notified ISO and/or TSO for changes in the following grid conditions:
: 8. Other system or equipment conditions determine by the TSO to be of importance to IPEC.
0 0 0 S 0 0 0.0 0 0 0 Unit power capability changes Unit Startup and Shutdown Modifications resulting in changes to generator electrical characteristics Breaker alignment and offsite voltage verification MVAR Loading Post-trip off-site voltage criteria Changes in IPEC post trip station and accident loading Loss of preferred 138KV Offsite Power Supply Loss of 13.8KV Offsite Power Supply Status of 13.8kv and 138kv Maintenance activities directly affecting Switchyard components Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 5 of 26 I 5 I a 0 Mvieihod of voitage controi, automatic or manual.EDG Surveillance Testing Load tap changer position / Auto-Manual Mode I(d) Describe how NPP operators are trained and tested on the use of the procedures or assessing grid conditions in question I (c).The Licensed Operators at IPEC have had training on site procedure that addresses offsite power continuous monitoring and notification.
I (c) Describe any grid conditions that would     Grid conditions and status are the primary responsibility of ISO and TSO.
This procedure establishes monitoring, and notification responsibilities of the Buchanan Substation, as well as the interface between the IPEC and Con Edison's Energy Control Center. The most recent training occurred in Cycle 3 of 2005.Typically, IPEC operators are trained and tested, using procedures, on the following:
cause the NPP licensee to contact the TSO.
* LOOP* System Restoration Typically, IPEC operators are trained, using procedures, on the following:
Relative to this question, "grid conditions' is assumed to be IPEC changes that impact the TSO real-time post Describe the procedures associated with such      contingency analysis capability. IPEC typically notified ISO and/or TSO for changes in the following grid a communication. If you do not have                conditions:
* LOOP* System Restoration e Degraded voltage conditions
procedures, describe how you assess grid conditions that may cause the NPP licensee to            0   Unit power capability changes contact the TSO.                                        0   Unit Startup and Shutdown Modifications resulting in changes to generator electrical characteristics Breaker alignment and offsite voltage verification MVAR Loading Post-trip off-site voltage criteria Changes in IPEC post trip station and accident loading
* Voltage (number for inadequate grid capacity)* VARs* Breaker status* Notification of the ISO and/or TSO of changed conditions.
                                                      .0    Loss of preferred 138KV Offsite Power Supply Loss of 13.8KV Offsite Power Supply Status of 13.8kv and 138kv Maintenance activities directly affecting Switchyard components
1 (e) If you do not have a formal agreement or protocol with your TSO, describe why you believe you continue to comply with the provisions of GDC 17 as stated above, or describe what actions you intend to take to assure compliance with GDC 17.As previously stated, IPEC does have a formal agreement with the TSO. Prompt notification from the TSO (after 30-minutes) and a pre-trip analysis of whether the post-trip voltage will be below acceptable values are included in Indian Point Energy Center Offsite Power Continuous Monitoring And Notification procedure.
 
Additionally TSO procedure describes Con Edison responsibility to notify IPEC of low voltage issues as it relates to the 138kV and 13.8kV systems. The procedure requires the TSO to notify both IP2 & IP3 Control Rooms after 30-minutes if the real-time analysis tool determines the post IPEC trip voltage would be below the value specified by IPEC. In addition, the TSO will notify IPEC after 30-minutes if the 13.8kV system voltage is below the normal system voltage schedule.
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 5 of 26 I     5                                                                                                                                                         I a   Mvieihod of voitage controi, automatic or manual.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 6 of 26 EMM !.'11 --sI~l, Comluianut:
EDG Surveillance Testing Load tap changer position / Auto-Manual Mode I(d) Describe how NPP operators are trained   The Licensed Operators at IPEC have had training on site procedure that addresses offsite power continuous and tested on the use of                      monitoring and notification. This procedure establishes monitoring, and notification responsibilities of the Buchanan Substation, as well as the interface between the IPEC and Con Edison's Energy Control Center. The the procedures or                              most recent training occurred in Cycle 3 of 2005.
wit CiiGC-i, kir2 and ii;3 are not a GDU plants, the FSARs describe to what extent 1P2 and IP3 were reviewed to the draft GDCs or its equivalent is not predicated on this agreement).
assessing grid conditions in question I (c).
I (f) If you have an existing formal interconnection agreement or protocol that ensures adequate communication and coordination between the NPP licensee and the TSO, describe whether this agreement or protocol requires that you be promptly notified when the conditions of the surrounding grid could result in degraded voltage (i.e., below TS nominal trip setpoint value requirements; including NPP licensees using allowable value in its TSs)or As previously stated, IPEC does have formal agreements with the TSO. These agreements require the TSO to notify IPEC as soon as practicable per good utility practice, upon receipt of a potential post-trip degraded voltage alarm.LOOP after a trip of the reactor unit(s).I(g) Describe the low switchyard voltage These are the Switchyard voltage conditions that will initiate operation of IPEC degraded voltage protection conditions that would initiate operation of i. 138 kv Offsite Power Source <133kv plant degraded voltage protection.
Typically, IPEC operators are trained and tested, using procedures, on the following:
ii. 13.8kv Offsite Power Source <13.4kv Note: The design of these systems is described in front of this attachment.
* LOOP
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 7 of 26 2. Use of criteria and methodologies to assess whether the offsite power system will become inoperable as a result of a trip of your NPP.2(a) Does your NPP's TSO use any analysis tools, an online analytical transmission system studies program, or other equivalent predictive methods to determine the grid conditions that would make the NPP offsite power system inoperable during various contingencies?
* System Restoration Typically, IPEC operators are trained, using procedures, on the following:
If available to you, please provide a brief description of the analysis tool that is used by the TSO.Yes. The TSO, uses a State Estimator and a Contingency Evaluation Program to analyze real time and contingency voltage levels and thermal loading for IPEC 138kV off-site sources.The 138kV transmission system program and related actions are summarized as follows: Real-Time Contingency Analysis Program: The program and related actions are summarized as follows; the program utilizes real-time transmission system information and nuclear generating unit specific shutdown loads and minimum voltage requirements.
* LOOP
The program creates a model by combining real-time telemetry with the network model. The network model includes the nuclear power plant facilities.
* System Restoration e   Degraded voltage conditions
The State Estimator is then used to provide a consistent power flow that is used to run the contingencies.
* Voltage (number for inadequate grid capacity)
The contingency case assumes the simultaneous loss of the generator and the addition of load at the appropriate bus. An alarm is issued if the prescribed voltage limits are violated.The 13.8kV distribution system is monitored on a real-time voltage basis. If the voltage drops below a predetermined 13.8kV system voltage value, IPEC is notified.
* VARs
This approach is determined to be acceptable because the 13.8kV off-site source is a manually aligned supply and the predetermined notification value is at the lower limit of the 13.8kV systems normal voltage schedule.
* Breaker status
Therefore, the TSO will make all reasonable efforts to maintain the voltage schedule.2(b) Does your NPP's TSO use an Yes. The TSO uses the real-time analysis tool described in 2(a), in conjunction with analysis tool as the basis for notifying procedures, as the basis for determining when conditions warrant IPEC notification of the the NPP licensee when such a condition 138kV system.is identified?
* Notification of the ISO and/or TSO of changed conditions.
If not, how does the TSO determine if conditions on the grid As described above the TSO use real-time voltage monitoring, in conjunction with warrant NPP licensee notification?
1(e) If you do not have a formal agreement or As previously stated, IPEC does have a formal agreement with the TSO. Prompt notification from the TSO protocol with your TSO, describe why you       (after 30-minutes) and a pre-trip analysis of whether the post-trip voltage will be below acceptable values are believe you continue to comply with the       included in Indian Point Energy Center Offsite Power Continuous Monitoring And Notification procedure.
procedures, as basis to determining when conditions warrant IPEC notification of the 13.8kV system.
provisions of GDC 17 as stated above, or       Additionally TSO procedure describes Con Edison responsibility to notify IPEC of low voltage issues as it describe what actions you intend to take to   relates to the 138kV and 13.8kV systems. The procedure requires the TSO to notify both IP2 & IP3 Control assure compliance with GDC 17.                 Rooms after 30-minutes if the real-time analysis tool determines the post IPEC trip voltage would be below the value specified by IPEC. In addition, the TSO will notify IPEC after 30-minutes if the 13.8kV system voltage is below the normal system voltage schedule.
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043-- -Page 8 of 26 II yOum J I vJ UQ~Oc am C A am mGl yoia LvuI, would the analysis tool identify a condition in which a trip of the NPP would result in switchyard voltages (immediate and/or long-term) falling below TS nominal trip setpoint value requirements (including NPP licensees using allowable value in its TSs) and consequent actuation of plant degraded voltage protection?
 
l I 'es. I FI S aIai-Liine ayaiSis ivoi for ihe i35KV, in conjunction witn i-'E; plant load flow studies, have the capability to determine if the trip of their IPEC plants would result in a switchyard voltage which would actuate the associated unit's degraded voltage protection logic and initiate separation from the offsite power source.The 13.8kV source is a manually aligned distribution system, which the TSO has local resources available to adjust system voltage. Prior to IPEC aligning the 480VAC safety buses to the 13.8 kV system (via the 6.9 kV system), communication between the TSO and IPEC is required to ensure the adequacy of the 13.8 kV system voltage to support accident loads.!If not, discuss how such a condition would be identified on the grid.2(d) If your TSO uses an analysis tool, The TSO 138kV real-time analysis tool presently resolves the IPEC Unit 2 and IPEC Unit how frequently does the analysis tool 3 trip contingencies every minute for the steady state conditions.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 6 of 26
program update?2(e) Provide details of analysis tool- The 138kV IPEC Unit 2 and IPEC Unit 3 contingencies results (see response to item 2(a))identified contingency conditions that are automatically compared to off-site post trip voltage limits. If any limit is violated, an would trigger an NPP licensee alarm is generated and IPEC is notified if not cleared after 30 minutes notification from the TSO.2(f) If an interface agreement exists Yes. IPEC would be notified by the TSO when: between the TSO and the NPP licensee, does it require that the NPP licensee be
  !.'11 EMM                                                                                                                                                        - -sI~l, Comluianut: wit CiiGC-i, kir2 and ii;3 are not a GDU plants, the FSARs describe to what extent 1P2 and IP3 were reviewed to the draft GDCs or its equivalent is not predicated on this agreement).
* When all three 138 kV monitoring and alarm systems are out of service and have notified of periods when the TSO is not been restored within 30 minutes.unable to determine if offsite power
I(f) If you have an existing formal          As previously stated, IPEC does have formal agreements with the TSO. These agreements require the TSO to interconnection agreement or protocol that    notify IPEC as soon as practicable per good utility practice, upon receipt of a potential post-trip degraded ensures adequate communication and            voltage alarm.
* When the 13.8 kV monitoring and alarm systems are out of service and have not voltage and capacity could be been restored within 30 minutes.inadequate?
coordination between the NPP licensee and the TSO, describe whether this agreement or protocol requires that you be promptly notified when the conditions of the surrounding grid could result in degraded voltage (i.e., below TS nominal trip setpoint value requirements; including NPP licensees using allowable value in its TSs) or LOOP after a trip of the reactor unit(s).
Loss of the voltage prediction tool alone has no impact on operability.
I(g) Describe the low switchyard voltage    These are the Switchyard voltage conditions that will initiate operation of IPEC degraded voltage protection conditions that would initiate operation of  i. 138 kv Offsite Power Source <133kv plant degraded voltage protection.           ii. 13.8kv Offsite Power Source <13.4kv Note: The design of these systems is described in front of this attachment.
If notified by the If so, how does the NPP licensee TSO that the Low Voltage Contingency Alarm is inoperable, then the IPEC Operators determine that the offsite power would perform the following:
 
remain operable when such a 1. Contact the TSO once per shift to verify imminent/expected degraded voltage notification is received?
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 7 of 26
conditions do not exist.l 2. Minimize large electrical load changes Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 9 of 26 li]Zs1Me g I M 5 -.M .M M , &J. Mtintraize iutaidriance and testing of the electrical distribution system.4. Terminate maintenance or testing on critical components of the electrical distribution system as soon as possible.5. Limit MVAR Output (OP2 only)i 2(g) After an unscheduled inadvertent No. Verification of the post trip 138kV switchyard voltage real-time analysis results against trip of the NPP, are the resultant actual post trip voltage is not performed.
: 2. Use of criteria and methodologies to assess whether the offsite power system will become inoperable as a result of a trip of your NPP.
Since the real-time analysis tool uses real time switchyard voltages verified by system data and assumed worst case station loads a comparison of values would be procedure to be bounded by the difficult even if the real-time analysis predicted values were available which they are not;voltages predicted by the analysis tool?2(h) If an analysis tool is not available to This question is not applicable to IPEC. The TSO has a real-time analysis tool presently in the NPP licensee's TSO, do you know if use for the 138kV system as discussed above.there are any plans for the TSO to obtain one? If so, when? The TSO has no plans to install a real-time contingency monitor for the 13.8 kV off-site power source.2(i) If an analysis tool is not available, Not Applicable for the 138kV transmission lines, TSO uses real-time analysis tool as does your TSO perform periodic studies discussed above.to verify that adequate offsite power capability, including adequate NPP post- IPEC performs periodic station load flow studies to ensure that the minimum 13.8kV trip switchyard voltages (immediate scheduled voltage is adequate to support voltage requirements.
2(a) Does your NPP's TSO use any           Yes. The TSO, uses a State Estimator and a Contingency Evaluation Program to analyze analysis tools, an online analytical       real time and contingency voltage levels and thermal loading for IPEC 138kV off-site transmission system studies program, or sources.
and/or long-term), will be available to the NPP licensee over the projected timeframe of the study?(a) Are the key assumptions and parameters of these periodic studies translated into TSO guidance to ensure that the transmission system is operated within the bounds of the analyses?(b) If the bounds of the analyses are exceeded, does this condition trigger the notification provisions discussed in question 1 above?[l ______ I ___ ___________
other equivalent predictive methods to determine the grid conditions that would     The 138kV transmission system program and related actions are summarized as follows:
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 we] S
make the NPP offsite power system inoperable during various                       Real-Time Contingency Analysis Program: The program and related actions are contingencies?                                  summarized as follows; the program utilizes real-time transmission system information If available to you, please provide a brief     and nuclear generating unit specific shutdown loads and minimum voltage description of the analysis tool that is       requirements. The program creates a model by combining real-time telemetry with used by the TSO.                                the network model. The network model includes the nuclear power plant facilities.
* tii.! I M*1111 Page IUof26 I-/i\ I WS shoe I OWL LW7, IJI 7LDU UV not have access to the results of an analysis tool, or your TSO does not perform and make available to you periodic studies that determine the adequacy of offsite power capability, please describe why you believe you comply with the provisions of GDC 17 as stated above, or describe what compensatory actions you intend to take to ensure that the offsite power system will be sufficiently reliable and remain operable with high probability following a trip of your NPP.I I-. ! P-r --! t! _ e- -.. .I. AA i iivti apPICIavult:
The State Estimator is then used to provide a consistent power flow that is used to run the contingencies. The contingency case assumes the simultaneous loss of the generator and the addition of load at the appropriate bus. An alarm is issued if the prescribed voltage limits are violated.
I I O0KV arIU 13.0 KV Oystems Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 11 of 26 W~ 0 1'lll 3.Use of criteria and methodologies to-assess whether the NPP's offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.
The 13.8kV distribution system is monitored on a real-time voltage basis. If the voltage drops below a predetermined 13.8kV system voltage value, IPEC is notified. This approach is determined to be acceptable because the 13.8kV off-site source is a manually aligned supply and the predetermined notification value is at the lower limit of the 13.8kV systems normal voltage schedule. Therefore, the TSO will make all reasonable efforts to maintain the voltage schedule.
3(a) If the TSO notifies the NPP operator that* a trip of the NPP, or* the loss of the most critical transmission line or* the largest supply to the grid would result in switchyard voltages (immediate and/or long-term) below TS nominal trip setpoint value requirements (including NPP licensees using allowable value in its TSs)and would actuate plant degraded voltage protection, is the NPP offsite power system declared inoperable under the plant TSs? If not, why not?3(b) If onsite safety-related equipment (e.g., emergency diesel generators or safety-related motors) is lost when subjected to a double sequencing (LOCA with delayed LOOP event) as a result of the anticipated system performance and is incanihie of performing its safety functions as a IPEC would declare the 138kV off-site source "inoperable".
2(b) Does your NPP's TSO use an            Yes. The TSO uses the real-time analysis tool described in 2(a), in conjunction with analysis tool as the basis for notifying    procedures, as the basis for determining when conditions warrant IPEC notification of the the NPP licensee when such a condition      138kV system.
The TSO has real-time monitor capability for the 138kV source and IPEC is notified by the TSO if the loss of the unit would result in an unacceptable off-site post-trip voltage. There are no identified system conditions where the loss of a transmission line or large supply would result in the trip of the generator. IPEC is not designed for double sequencing events. LOCA with a Delayed LOOP is outside the design basis for both IP2 and IP3.
is identified? If not, how does the TSO determine if conditions on the grid        As described above the TSO use real-time voltage monitoring, in conjunction with warrant NPP licensee notification?          procedures, as basis to determining when conditions warrant IPEC notification of the 13.8kV system.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 12 of 26.e'=, I ". !- in M 'I _SUIL %J; Is ju n V-0JU al IVLJ 1I W IIC!J llcy actuation signal during this condition, is the equipment considered inoperable?
 
If not, why not?3(c) Describe your evaluation of onsite Indian Point Units 2 and 3 are designed to a GDC that postulates a LOCA concurrent with safety-related equipment to determine a LOOP. Neither plant models a LOCA with Delayed LOOP scenario in its voltage profile whether it will operate as designed and loading analyses, because this event is outside the design basis of both units.during the condition described in question 3(b).3(d) If the NPP licensee is notified by This condition is addressed by our site procedures.
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043
Under these circumstances we would the TSO of other grid conditions that enter the applicable site procedure for offsite power continuous monitoring and may impair the capability or availability notification, a Technical Specification action statement would not be entered until an of offsite power, are any plant TS action applicable system, structure or component was declared inoperable.
                                                                              --  -                                    Page 8 of 26 II yOum J I vJ UQ~Oc am CA am mGl yoia LvuI, l
statements entered? If so, please identify them.3(e) If you believe your plant TSs do not Not applicable.
I 'es. IFI        S aIai-Liine          ayaiSis ivoi for ihe i35KV, in conjunction witn i-'E; plant load would the analysis tool identify a                 flow studies, have the capability to determine if the trip of their IPEC plants would result in condition in which a trip of the NPP                a switchyard voltage which would actuate the associated unit's degraded voltage would result in switchyard voltages                 protection logic and initiate separation from the offsite power source.
require you to declare your offsite power Based on responses, we declare offsite power or applicable equipment inoperable under system or safety-related equipment circumstances as described above.inoperable in any of these circumstances, explain why you believe you comply with the provisions of GDC 17 and your plant TSs, or describe what compensatory actions you intend to take to ensure that the offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.
(immediate and/or long-term) falling below TS nominal trip setpoint value               The 13.8kV source is a manually aligned distribution system, which the TSO has local requirements (including NPP licensees               resources available to adjust system voltage. Prior to IPEC aligning the 480VAC safety using allowable value in its TSs) and               buses to the 13.8 kV system (via the 6.9 kV system), communication between the TSO consequent actuation of plant degraded              and IPEC is required to ensure the adequacy of the 13.8 kV system voltage to support voltage protection?                                accident loads.
3(f) Describe if and how NPP operators are trained and tested on the compensatory actions mentioned in your answers to questions 3(a) through (e).The Licensed Operators have been trained on the applicable site procedure for offsite power continuous monitoring and notification.
If not, discuss how such a condition would be identified on the grid.
This procedure contains the requirements for declaring off-site power inoperable and entering the appropriate Technical Specifications.
2(d) If your TSO uses an analysis tool,             The TSO 138kV real-time analysis tool presently resolves the IPEC Unit 2 and IPEC Unit how frequently does the analysis tool              3 trip contingencies every minute for the steady state conditions.
For events such as LOCAs followed later hy a I nap event the Opnnraors confinuing training includes the sequencing or manual loading of safeguards equipment.
program update?
The Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 13 of 26 le I _ ! *- I ;
2(e) Provide details of analysis tool-              The 138kV IPEC Unit 2 and IPEC Unit 3 contingencies results (see response to item 2(a))
* I ! ! e I I McUiMe111iiL to IIIrIIudiIy Iad safeguards equipment is contingent on whether or not tile Safeguards signal has been reset. The site's Westinghouse owner's group Emergency Operating Procedures address these situations.
identified contingency conditions that             are automatically compared to off-site post trip voltage limits. If any limit is violated, an would trigger an NPP licensee                       alarm is generated and IPEC is notified if not cleared after 30 minutes notification from the TSO.
The licensed operators are tested on these procedures and in dynamic simulator evaluations, as applicable.
2(f) If an interface agreement exists               Yes. IPEC would be notified by the TSO when:
between the TSO and the NPP licensee, does it require that the NPP licensee be
* When all three 138 kV monitoring and alarm systems are out of service and have notified of periods when the TSO is                             not been restored within 30 minutes.
unable to determine if offsite power
* When the 13.8 kV monitoring and alarm systems are out of service and have not voltage and capacity could be                                   been restored within 30 minutes.
inadequate?
Loss of the voltage prediction tool alone has no impact on operability. If notified by the If so, how does the NPP licensee                   TSO that the Low Voltage Contingency Alarm is inoperable, then the IPEC Operators determine that the offsite power would             perform the following:
remain operable when such a                             1. Contact the TSO once per shift to verify imminent/expected degraded voltage notification is received?                                       conditions do not exist.
l     2. Minimize       large electrical load changes
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 9 of 26 li]Zs1Me   g                               I M5    M-. . M                                                                           M J. Mtintraize iutaidriance and testing of the electrical distribution system.             i
: 4. Terminate maintenance or testing on critical components of the electrical distribution system as soon as possible.
: 5. Limit MVAR Output (OP2 only) 2(g) After an unscheduled inadvertent           No. Verification of the post trip 138kV switchyard voltage real-time analysis results against trip of the NPP, are the resultant             actual post trip voltage is not performed. Since the real-time analysis tool uses real time switchyard voltages verified by                 system data and assumed worst case station loads a comparison of values would be procedure to be bounded by the                 difficult even if the real-time analysis predicted values were available which they are not; voltages predicted by the analysis tool?
2(h) If an analysis tool is not available to   This question is not applicable to IPEC. The TSO has a real-time analysis tool presently in the NPP licensee's TSO, do you know if         use for the 138kV system as discussed above.
there are any plans for the TSO to obtain one? If so, when?                       The TSO has no plans to install a real-time contingency monitor for the 13.8 kV off-site power source.
2(i) If an analysis tool is not available,     Not Applicable for the 138kV transmission lines, TSO uses real-time analysis tool as does your TSO perform periodic studies         discussed above.
to verify that adequate offsite power capability, including adequate NPP post-       IPEC performs periodic station load flow studies to ensure that the minimum 13.8kV trip switchyard voltages (immediate             scheduled voltage is adequate to support voltage requirements.
and/or long-term), will be available to the NPP licensee over the projected timeframe of the study?
(a) Are the key assumptions and parameters of these periodic studies translated into TSO guidance to ensure that the transmission system is operated within the bounds of the analyses?
(b) If the bounds of the analyses are exceeded, does this condition trigger the notification provisions discussed in question 1 above?
[l       ______                               I   ___                 ___________
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 we]
S
* tii.!
I  I-.  ..
I M*1111 P-r  --
AA  ! t! _  e- -
Page IUof26                I.
I  -  /i\ shoe    I WS   I OWL LW7, IJI 7LDU UV   iivti apPICIavult: I  I O0KV arIU 13.0 KV Oystems i
not have access to the results of an analysis tool, or your TSO does not perform and make available to you periodic studies that determine the adequacy of offsite power capability, please describe why you believe you comply with the provisions of GDC 17 as stated above, or describe what compensatory actions you intend to take to ensure that the offsite power system will be sufficiently reliable and remain operable with high probability following a trip of your NPP.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 11 of 26 W~     0 1'lll 3.Use of criteria and methodologies to-assess whether the NPP's offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.
3(a) If the TSO notifies the NPP             IPEC would declare the 138kV off-site source "inoperable". The TSO has real-time operator that                               monitor capability for the 138kV source and IPEC is notified by the TSO if the loss of the unit would result in an unacceptable off-site post-trip voltage. There are no identified
* a trip of the NPP, or              system conditions where the loss of a transmission line or large supply would result in the
* the loss of the most critical      trip of the generator.
transmission line or
* the largest supply to the grid would result in switchyard voltages (immediate and/or long-term) below TS nominal trip setpoint value requirements (including NPP licensees using allowable value in its TSs) and would actuate plant degraded voltage protection, is the NPP offsite power system declared inoperable under the plant TSs? If not, why not?                    3(b) If onsite safety-related equipment      IPEC is not designed for double sequencing events. LOCA with a Delayed LOOP is (e.g., emergency diesel generators or        outside the design basis for both IP2 and IP3.
safety-related motors) is lost when subjected to a double sequencing (LOCA with delayed LOOP event) as a result of the anticipated system performance and is incanihie of performing its safety functions as a
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 12 of 26 I _SUIL e'=,
          %J;IsV-0JU ju n IVLJ al 1I W IIC!J llcy I". !-      in
                                                              '    M actuation signal during this condition, is the equipment considered inoperable?
If not, why not?
3(c) Describe your evaluation of onsite         Indian Point Units 2 and 3 are designed to a GDC that postulates a LOCA concurrent with safety-related equipment to determine           a LOOP. Neither plant models a LOCA with Delayed LOOP scenario in its voltage profile whether it will operate as designed             and loading analyses, because this event is outside the design basis of both units.
during the condition described in question 3(b).
3(d) If the NPP licensee is notified by         This condition is addressed by our site procedures. Under these circumstances we would the TSO of other grid conditions that           enter the applicable site procedure for offsite power continuous monitoring and may impair the capability or availability     notification, a Technical Specification action statement would not be entered until an of offsite power, are any plant TS action       applicable system, structure or component was declared inoperable.
statements entered? If so, please identify them.
3(e) If you believe your plant TSs do not     Not applicable.
require you to declare your offsite power     Based on responses, we declare offsite power or applicable equipment inoperable under system or safety-related equipment             circumstances as described above.
inoperable in any of these circumstances, explain why you believe you comply with the provisions of GDC 17 and your plant TSs, or describe what compensatory actions you intend to take to ensure that the offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.
3(f) Describe if and how NPP operators       The Licensed Operators have been trained on the applicable site procedure for offsite are trained and tested on the                power continuous monitoring and notification. This procedure contains the requirements compensatory actions mentioned in your        for declaring off-site power inoperable and entering the appropriate Technical answers to questions 3(a) through (e).        Specifications.
For events such as LOCAs followed later hy a I nap event the     Opnnraors confinuing training includes the sequencing or manual loading of safeguards equipment. The
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 13 of 26 le _I! *- II  ; * ! ! e I
I         McUiMe111iiL to IIIrIIudiIy Iad safeguards equipment is contingent on whether or not tile Safeguards signal has been reset. The site's Westinghouse owner's group Emergency Operating Procedures address these situations. The licensed operators are tested on these procedures and in dynamic simulator evaluations, as applicable.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 14of26 WIinISTAJ*WAO
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 14of26 WIinISTAJ*WAO
: 4. Use of criteria and methodologies to assess whether the offsite power system will remain operable following a trip of your NPP.4(a) Do the NPP operators have any guidance or procedures in plant TS bases sections, the final safety analysis report, or plant procedures regarding situations in which the condition of plant-controlled or -monitored equipment (e.g., voltage regulators, auto tap changing transformers, capacitors, static VAR compensators, main generator voltage regulators) can adversely affect the operability of the NPP offsite power system? If so, describe how the operators are trained and tested on the guidance and procedures.
: 4. Use of criteria and methodologies to assess whether the offsite power system will remain operable following a trip of your NPP.
Yes, procedural guidance for abnormal situations related to this equipment is available to IPEC operators in Annunciator Response Procedures.
4(a) Do the NPP operators have any           Yes, procedural guidance for abnormal situations related to this equipment is available to guidance or procedures in plant TS           IPEC operators in Annunciator Response Procedures.
The operators are trained and tested on systems such as the main generator voltage regulator and tap changers.4(b) If your TS bases sections, the final safety analysis report, and plant procedures do not provide guidance regarding situations in which the condition of plant-controlled or -monitored equipment can adversely affect the operability of the NPP offsite power system, explain why you believe you comply with the provisions of GDC 17 and the plant TSs, or describe what actions you intend to take to provide such guidance or procedures.
bases sections, the final safety analysis report, or plant procedures regarding       The operators are trained and tested on systems such as the main generator voltage situations in which the condition of plant- regulator and tap changers.
Not applicable.
controlled or -monitored equipment (e.g., voltage regulators, auto tap changing transformers, capacitors, static VAR compensators, main generator voltage regulators) can adversely affect the operability of the NPP offsite power system? If so, describe how the operators are trained and tested on the guidance and procedures.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 15 of 26 Use of NPP licensee/TSO protocols and analysis tool by TSOs to assist NPP licensees in monitoring grid conditions for consideration in maintenance risk assessments The Maintenance Rule (10 CFR 50.65(a)(4))
4(b) If your TS bases sections, the final   Not applicable.
requires that licensees assess and manage the increase in risk that may result from proposed maintenance activities before performing them.5. Performance of grid reliability evaluations as part of the maintenance risk assessments required by 10 CFR 50.65(a)(4).
safety analysis report, and plant procedures do not provide guidance regarding situations in which the condition of plant-controlled or -
5(a) Is a quantitative or qualitative grid reliability evaluation performed at your NPP as part of the maintenance risk assessment required by 10 CFR 50.65(a)(4) before performing grid-risk-sensitive maintenance activities?
monitored equipment can adversely affect the operability of the NPP offsite power system, explain why you believe you comply with the provisions of GDC 17 and the plant TSs, or describe what actions you intend to take to provide such guidance or procedures.
This includes surveillances, post-maintenance testing, and preventive and corrective maintenance that could increase the probability of a plant trip or LOOP or impact LOOP or SBO coping capability, for example, before taking a risk-significant piece of equipment (such as an EDG, a battery, a steam-driven pump, an alternate AC power source)out-of-service?
 
_ .Yes IPEC performs qualitative risks assessment as required by 10 CFR 50.65 and IPEC Plant Technical Specification.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 15 of 26 Use of NPP licensee/TSO protocols and analysis tool by TSOs to assist NPP licensees in monitoring grid conditions for consideration in maintenance risk assessments The Maintenance Rule (10 CFR 50.65(a)(4)) requires that licensees assess and manage the increase in risk that may result from proposed maintenance activities before performing them.
The program is implemented by IPECNPP On-Line Risk Assessment and Outage Risk Assessment procedures.
: 5. Performance of grid reliability evaluations as part of the maintenance risk assessments required by 10 CFR 50.65(a)(4).
These procedures require plant risk assessment before removing equipment from service for planned maintenance activities, or upon discovery of equipment out of service that is unplanned.
5(a) Is a quantitative or qualitative grid     Yes reliability evaluation performed at your NPP as part of the maintenance risk           IPEC performs qualitative risks assessment as required by 10 CFR 50.65 and IPEC assessment required by 10 CFR                 Plant Technical Specification. The program is implemented by IPECNPP On-Line Risk 50.65(a)(4) before performing grid-risk-      Assessment and Outage Risk Assessment procedures.
The IPECNPP On-Line Risk Assessment procedure requires an evaluation of current and anticipated grid conditions before removing risk significant equipment from service.The Equipment Out of Service (EOOS) Monitor is a computer based program that is used to calculate Core Damage Frequency and conditional Core Damage Frequency for the plant equipment configuration and testing activities for both planned and unplanned configurations.
sensitive maintenance activities? This        These procedures require plant risk assessment before removing equipment from includes surveillances, post-maintenance service for planned maintenance activities, or upon discovery of equipment out of service testing, and preventive and corrective        that is unplanned.
The IPECNPP Work Management procedure requires a risk plan development for activities that would increase grid instability in combination with external events.5(b) Is grid status monitored by some means for the duration of the grid-risk-sensitive maintenance to confirm the continued validity of the risk assessment and is risk reassessed when warranted?
maintenance that could increase the probability of a plant trip or LOOP or        The IPECNPP On-Line Risk Assessment procedure requires an evaluation of current impact LOOP or SBO coping capability,          and anticipated grid conditions before removing risk significant equipment from service.
If not, how is the risk assessed during Yes Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 16 of 26 WE .-- !!S**!i. -" I -; -J _., -s ---&.._ __:- -- ---n H41 -1f-0 10LV 1 u1 ;>1o ;> tic 1 fl lsL Fa1 1VV-I.5(c) Is there a significant variation in the stress on the grid in the vicinity of your NPP site caused by seasonal loads or maintenance activities associated with critical transmission elements?Is there a seasonal variation (or the potential for a seasonal variation) in the LOOP frequency in the local transmission region?If the answer to either question is yes, discuss the time of year when the variations occur and their magnitude.
for example, before taking a risk-            The Equipment Out of Service (EOOS) Monitor is a computer based program that is significant piece of equipment (such as        used to calculate Core Damage Frequency and conditional Core Damage Frequency for an EDG, a battery, a steam-driven pump, the plant equipment configuration and testing activities for both planned and unplanned an alternate AC power source)                  configurations.
Yes The NYISO Reliability Coordination Area is a summer peaking area. Due to high intra area and inter area power flows, it would be expected that the grid would be stressed.However, this stress is managed through facility maintenance coordination.
out-of-service?                                The IPECNPP Work Management procedure requires a risk plan development for activities that would increase grid instability in combination with external events.
During the summer peak season scheduled transmission facility maintenance is avoided in June, July and August if possible.Anytime that maintenance is scheduled, the schedules are managed in order to maintain operation of the bulk power system within established operating criteria.No, based on the limited number of LOOP occurrences in the NYISO region over the past 10 years, no seasonal variation can be established.
5(b) Is grid status monitored by some         Yes means for the duration of the grid-risk-sensitive maintenance to confirm the continued validity of the risk assessment and is risk reassessed when warranted?
IPEC last experienced a transmission system related LOOP on August 14, 2003.5(d) Are known time-related variations in No. However, Con Edison the TSO by procedure does not schedule feeder outages the probability of a LOOP at your plant between May 1 and September 15 due to summer loading concerns.
If not, how is the risk assessed during
IPEC will not site considered in the grid-risk-sensitive schedule maintenance activities during this time. IPEC will schedule emergent activities maintenance evaluation?
 
If not, what is to address issues that could pose a threat to grid stability.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 16 of 26 WE   .     !!S**!i.                                             -"   -
your basis for not considering them?5(e) Do you have contacts with the TSO Yes.to determine current and anticipated grid conditions as part of the grid reliability TSO Communication contacts are available for assessment of grid conditions before and evaluation performed before conducting during the performance of grid-risk sensitive maintenance activities.
I -;-   J _., -s - --   &.._ __:-     -- -   - - n H41 u1-1f-0 ;>1o 10LV ;> tic 1 fl 1 lsL   Fa1 1VV
                                                      -I.
5(c) Is there a significant variation in the             Yes stress on the grid in the vicinity of your               The NYISO Reliability Coordination Area is a summer peaking area. Due to high intra NPP site caused by                                      area and inter area power flows, it would be expected that the grid would be stressed.
However, this stress is managed through facility maintenance coordination. During the seasonal loads                                          summer peak season scheduled transmission facility maintenance is avoided in June, July and August if possible.
or Anytime that maintenance is scheduled, the schedules are managed in order to maintain maintenance activities associated with                  operation of the bulk power system within established operating criteria.
critical transmission elements?
Is there a seasonal variation (or the                    No, based on the limited number of LOOP occurrences in the NYISO region over the potential for a seasonal variation) in the              past 10 years, no seasonal variation can be established. IPEC last experienced a LOOP frequency in the local transmission                transmission system related LOOP on August 14, 2003.
region?
If the answer to either question is yes, discuss the time of year when the variations occur and their magnitude.
5(d) Are known time-related variations in               No. However, Con Edison the TSO by procedure does not schedule feeder outages the probability of a LOOP at your plant                 between May 1 and September 15 due to summer loading concerns. IPEC will not site considered in the grid-risk-sensitive               schedule maintenance activities during this time. IPEC will schedule emergent activities maintenance evaluation? If not, what is                 to address issues that could pose a threat to grid stability.
your basis for not considering them?
5(e) Do you have contacts with the TSO                   Yes.
to determine current and anticipated grid conditions as part of the grid reliability               TSO Communication contacts are available for assessment of grid conditions before and evaluation performed before conducting                   during the performance of grid-risk sensitive maintenance activities.
grid-risk-sensitive maintenance activities?
grid-risk-sensitive maintenance activities?
5(f) Describe any formal agreement or Site level procedures provide the guidance on scheduling.
5(f) Describe any formal agreement or                   Site level procedures provide the guidance on scheduling. The procedure for protocol that you have with your TSO to                 performance of the offsite power continuous monitoring and notification contains assure that you are promptly alerted to a                 jguidelines for risk management of feeder outages. This would include the ability to
The procedure for protocol that you have with your TSO to performance of the offsite power continuous monitoring and notification contains assure that you are promptly alerted to a jguidelines for risk management of feeder outages. This would include the ability to Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 IMMUNE~)Page 17 of 26 us., -S. -I l...- --n -__ _-. A A__L __, , .._ _ l VV'jIQVI III UalIU .,UIIUILIuII tIaL t IdL I y I I CIIyI during a maintenance activity.restiict wor'Korku feoeers oi iquriiiiit q deum U o WIairitefrince on grid equipment.
 
Tne Hiant models grid feeder outage in the risk assessment Program EOOS.Notification occurs whether or not maintenance is on-going.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 IMMUNE~)Page                                                                                   17 of26 us.,                         -S.         -I l...- - -n -__
The TSO is required to notify IPEC whenever an impaired or potentially degraded grid condition is recognized by the TSO. Specific examples of known potentially degrading conditions identified in the agreement include: 1. De-energizing, switching or in-service work on critical transmission lines.2. Potentially damaging inclement weather.3. Solar Magnetic Disturbances.
VV'jIQVI III
: 4. Post-contingency voltage alarm for the 138kV transmission system after 30-minutes.5. A real-time 13.8kV degraded voltage condition below a normal system schedule voltage after 30-minutes.
_-. A__L        A __, ,
: 6. Prior to any 138kV feeder outage which could impact IPEC being removed or restored to service 7. When the TSO 138kV or 13.8kV monitoring and alarm capability are out of service and have not been restored after 30-minutes.
UalIU .,UIIUILIuII tIaL IdL t II y
: 8. Other system or equipment conditions determine by the TSO to be of importance to IPEC.5(g) Do you contact your TSO periodically for the duration of the grid-risk-sensitive maintenance activities?
CIIyI l
Yes.Additionally the TSO is contacted before the start of grid- risk sensitive maintenance activities and at the completion of the activity.
restiict wor'Korku feoeers iquriiiiit oi q     deum o U WIairitefrince     on grid equipment. Tne Hiant during a maintenance activity.                            models grid feeder outage in the risk assessment Program EOOS.
Changes to grid conditions are communicated to IPEC as stated in 5(f).5(h) If you have a formal agreement or The formal agreement with the System Operator at IPEC is described in the offsite protocol with your TSO, describe how power continuous monitoring and notification station procedure.
Notification occurs whether or not maintenance is on-going. The TSO is required to notify IPEC whenever an impaired or potentially degraded grid condition is recognized by the TSO. Specific examples of known potentially degrading conditions identified in the agreement include:
This procedure NPP operators and maintenance establishes monitoring, and notification responsibilities of the Buchanan Substation, as personnel are trained and tested on this well as the interface between the IPEC and Con Edison's Energy Control Center. The formal agreement or protocol.
: 1. De-energizing, switching or in-service work on critical transmission lines.
Licensed Operators have had training on this procedure.
: 2. Potentially damaging inclement weather.
The most recent training occurred in Cycle 3 of 2005.____There was no testing associated with this training.
: 3. Solar Magnetic Disturbances.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 18 of 26 56.6 0~ M- I Maintenance personnel do not have training on this agreement or procedure because Operations and Work Control assess the risk and conditions for performing maintenance activities.
: 4. Post-contingency voltage alarm for the 138kV transmission system after 30-minutes.
5(i) If your grid reliability evaluation, Not applicable.
: 5. A real-time 13.8kV degraded voltage condition below a normal system schedule voltage after 30-minutes.
: 6. Prior to any 138kV feeder outage which could impact IPEC being removed or restored to service
: 7. When the TSO 138kV or 13.8kV monitoring and alarm capability are out of service and have not been restored after 30-minutes.
: 8. Other system or equipment conditions determine by the TSO to be of importance to IPEC.
5(g) Do you contact your TSO periodically Yes.
for the duration of the grid-risk-sensitive             Additionally the TSO is contacted before the start of grid- risk sensitive maintenance maintenance activities?                                activities and at the completion of the activity. Changes to grid conditions are communicated to IPEC as stated in 5(f).
5(h) If you have a formal agreement or                 The formal agreement with the System Operator at IPEC is described in the offsite protocol with your TSO, describe how                     power continuous monitoring and notification station procedure. This procedure NPP operators and maintenance                           establishes monitoring, and notification responsibilities of the Buchanan Substation, as personnel are trained and tested on this               well as the interface between the IPEC and Con Edison's Energy Control Center. The formal agreement or protocol.                             Licensed Operators have had training on this procedure. The most recent training occurred in Cycle 3 of 2005.
____There                                                           was no testing associated with this training.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 18 of 26 56.6                   0~           M-                                                                     I Maintenance personnel do not have training on this agreement or procedure because Operations and Work Control assess the risk and conditions for performing maintenance activities.
5(i) If your grid reliability evaluation,   Not applicable.
performed as part of the maintenance risk assessment required by 10 CFR 50.65(a)(4), does not consider or rely on some arrangement for communication with the TSO, explain why you believe you comply with 10 CFR 50.65(a)(4).
performed as part of the maintenance risk assessment required by 10 CFR 50.65(a)(4), does not consider or rely on some arrangement for communication with the TSO, explain why you believe you comply with 10 CFR 50.65(a)(4).
: 50) If risk is not assessed (when Not applicable warranted) based on continuing communication with the TSO throughout the duration of grid-risk-sensitive maintenance activities, explain why you believe you have effectively implemented the relevant provisions of the endorsed industry guidance associated with the maintenance rule.5(k) With respect to questions 5(i) and Not applicable.
: 50) If risk is not assessed (when           Not applicable warranted) based on continuing communication with the TSO throughout the duration of grid-risk-sensitive maintenance activities, explain why you believe you have effectively implemented the relevant provisions of the endorsed industry guidance associated with the maintenance rule.
No alternative actions required.50), you may, as an alternative, describe what actions you intend to take to ensure that the increase in risk that may result from proposed grid-risk-sensitive activities is assessed before and during grid-risk-sensitive maintenance activities, respectively.
5(k) With respect to questions 5(i) and     Not applicable. No alternative actions required.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 19of26 6. -Use of risk assessment results, including the results of grid reliability evaluations, in managing maintenance risk, as required by 10 CFR 50.65(a)(4).  
50), you may, as an alternative, describe what actions you intend to take to ensure that the increase in risk that may result from proposed grid-risk-sensitive activities is assessed before and during grid-risk-sensitive maintenance activities, respectively.
-- -.TSO does grid reliability evaluations; not NPPs. ugrid reliability evaluations" Enter AP, if notified un-normality on grid.6(a) Does the TSO coordinate Yes.transmission system maintenance The TSO coordinates all scheduled work activities with the plant. The Process is activities that can have an impact on the described in site level procedures.
 
NPP operation with the NPP operator?6(b) Do you coordinate NPP Yes.maintenance activities that can have an IPEC coordinates all scheduled work activities with the TSO. The plant process is impact on the transmission system with described in site procedures.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 19of26
the TSO?6(c) Do you consider and implement, if Yes.warranted, the rescheduling of grid-risk-IPEC will reschedule activities as required to prevent challenging the stability of the local sensitive maintenance activities Grid. This would include activities which would likely cause plant trip or loss of off site (activities that could (i) increase the power. Guidance is described in site procedures.
: 6. - Use of risk assessment results, including the results of grid reliability evaluations, in managing maintenance risk, as required by 10 CFR 50.65(a)(4).             -- - .
If the Grid voltage degrades to a point likelihood of a plant trip, (ii) increase where it challenges the NPP, the TSO will immediately correct it or notify the IPEC Control LOOP probability, or (iii) reduce LOOP room operators.
TSO does grid reliability evaluations; not NPPs. ugrid reliability evaluations" Enter AP, if notified un-normality on grid.
IF emergent equipment outage occurs the TSO will notify the control or SBO coping capability) under room. The Switchyard coordinator or lead system engineer will be notified.
6(a) Does the TSO coordinate                   Yes.
A risk existing, imminent, or worsening assessment evaluation will be performed and if applicable, restrict feeders as required.degraded grid reliability conditions?
transmission system maintenance               The TSO coordinates all scheduled work activities with the plant. The Process is activities that can have an impact on the     described in site level procedures.
6(d) If there is an overriding need to Yes.perform grid-risk-sensitive maintenance Guidance is described in site procedures.
NPP operation with the NPP operator?
The Switchyard coordinator or lead system activities under existing or imminent engineer will be notified.
6(b) Do you coordinate NPP                     Yes.
A risk assessment evaluation will be performed and if applicable conditions of degraded grid reliability, or restrict feeders as required.continue grid-risk-sensitive maintenance when grid conditions worsen, do you Additionally, mitigative actions such as feeder restrictions and protected equipment will be implement appropriate risk management implemented.
maintenance activities that can have an       IPEC coordinates all scheduled work activities with the TSO. The plant process is impact on the transmission system with         described in site procedures.
actions? If so; describe the actinnq that you would take. (These actions could l Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 20 of 26 f. .! --. -i: Iss Include adteai-iel I quipi mer it pi vzuttutI I and compensatory measures to limit or minimize risk.)6(e) Describe the actions associated with questions 6(a) through 6(d) above that would be taken, state whether each action is governed by documented procedures and identify the procedures, and explain why these actions are effective and will be consistently accomplished.
the TSO?
Emergent maintenance or declining grid condition guidance is described in site procedures.
6(c) Do you consider and implement, if         Yes.
The operator will perform appropriate actions as required by Technical Specifications.
warranted, the rescheduling of grid-risk-     IPEC will reschedule activities as required to prevent challenging the stability of the local sensitive maintenance activities               Grid. This would include activities which would likely cause plant trip or loss of off site (activities that could (i) increase the       power. Guidance is described in site procedures. If the Grid voltage degrades to a point likelihood of a plant trip, (ii) increase     where it challenges the NPP, the TSO will immediately correct it or notify the IPEC Control LOOP probability, or (iii) reduce LOOP         room operators. IF emergent equipment outage occurs the TSO will notify the control or SBO coping capability) under               room. The Switchyard coordinator or lead system engineer will be notified. A risk existing, imminent, or worsening               assessment evaluation will be performed and if applicable, restrict feeders as required.
The Switchyard Coordinator or Lead System Engineer will be notified.They will perform a risk evaluation and if applicable restrict feeders as required.
degraded grid reliability conditions?
The feeder or equipment outage will be run through the plant risk program. These actions are required by Procedure and must be performed.
6(d) If there is an overriding need to         Yes.
6(f) De scribe how NPP operators and The Licensed Operators and Work Control Personnel at IPEC were provided training on maintenance personnel are trained and the applicable procedure that addresses Offsite Power Continuous Monitoring and tested to assure they can accomplish Notification.
perform grid-risk-sensitive maintenance       Guidance is described in site procedures. The Switchyard coordinator or lead system activities under existing or imminent         engineer will be notified. A risk assessment evaluation will be performed and if applicable conditions of degraded grid reliability, or restrict feeders as required.
This procedure establishes monitoring, and notification responsibilities of the the actions described in your answers to Buchanan Substation, as well as the interface between the IPEC and Con Edison's question 6(e). Energy Control Center. The most recent training occurred in Cycle 3 of 2005.There was no testing associated with this training.6(g) If there is no effective coordination Not applicable between the NPP operator and the TSO regarding transmission system maintenance or NPP maintenance activities, please explain why you believe you comply with the provisions of 10 CFR 50.65(a)(4).
continue grid-risk-sensitive maintenance when grid conditions worsen, do you           Additionally, mitigative actions such as feeder restrictions and protected equipment will be implement appropriate risk management implemented.
6(h) If you do not consider and Not applicable effectively implement appropriate risk management actions during the conditions described above, explain why you believe you effectively addressed the relevant provisions of the associated NRC-endorsed industry guidance.
actions? If so; describe the actinnq that you would take. (These actions could         l
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 21 of 26 us I s&#xa3; I -P i;,: -l, V(i) You m i iay, as an aiternailve LO questions 6(g) and 6(h) describe what actions you intend to take to ensure that the increase in risk that may result from grid-risk-sensitive maintenance activities is managed in accordance with 10 CFR 50.65(a)(4).
 
Not appilcaDie.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 20 of 26 f.
No alternative actions required.
Include adteai-iel I     quipi mer it pi vzuttutI I
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 22 of 26 I .. Ue U -Offsite power restoration procedures in accordance with 10 CFR 50.63 as developed in Section 2 of RG 1.155 Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.7.-Pibcedures for identifying local power sources' that could be made available to resupply your plant following a LOOP event.Note: Section 2, 'Offsite Power," of RG 1.155 (ADAMS Accession No. ML003740034) states: Procedures should include the actions necessary to restore offsite power and use nearby power sources when offsite power is unavailable.
                                                .!    --.      -i:                                                                          Iss and compensatory measures to limit or minimize risk.)
As a minimum, the following potential causes for loss of offsite power should be considered:
6(e) Describe the actions associated           Emergent maintenance or declining grid condition guidance is described in site with questions 6(a) through 6(d) above         procedures. The operator will perform appropriate actions as required by Technical that would be taken, state whether each         Specifications. The Switchyard Coordinator or Lead System Engineer will be notified.
-Grid under-voltage and collapse-Weather-induced power loss-Preferred power distribution system faults that could result in the loss of normal power to essential switchgear buses 7(a) Briefly describe any agreement made with the TSO to identify local power sources that could be made available to re-supply power to your plant following a LOOP event.IPEC has no agreement with local power sources. The NYISO and the TSO have restoration plans which identify how power will be restored to the NPPs as a priority load.The TSO is responsible for coordinating the restoration of off-site power to the NPP. The NPP is considered a critical facility and restoration of power is a priority.4 7(b) Are your NPP operators trained and tested on identifying and using local power sources to resupply your plant following a LOOP event? If so, describe how.Yes.Continuing Licensed Operator Re-qualification Training includes electrical bus and power supply training.
action is governed by documented               They will perform a risk evaluation and if applicable restrict feeders as required. The procedures and identify the procedures,         feeder or equipment outage will be run through the plant risk program. These actions are and explain why these actions are               required by Procedure and must be performed.
Also included is training on applicable Abnormal Operating procedures, which address re-energizing plant electrical systems following a LOOP.I This includes items such as nearby or onsite gas turbine generators, portable generators, hydro generators, and black-smttZOI *I..MIJVwII EVICTS ILO.
effective and will be consistently accomplished.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 23 of 26 g!le t. MIa .- I 7 (c) if you nave not established an agreement with your plant's TSO to identify local power sources that could be made available to resupply power to your plant following a LOOP event, explain why you believe you comply with the provisions of 10 CFR 50.63, or describe what actions you intend to take to establish compliance.
6(f) De scribe how NPP operators and            The Licensed Operators and Work Control Personnel at IPEC were provided training on maintenance personnel are trained and         the applicable procedure that addresses Offsite Power Continuous Monitoring and tested to assure they can accomplish            Notification. This procedure establishes monitoring, and notification responsibilities of the the actions described in your answers to        Buchanan Substation, as well as the interface between the IPEC and Con Edison's question 6(e).                                Energy Control Center. The most recent training occurred in Cycle 3 of 2005.
!Not appiicabie.
There was no testing associated with this training.
The NYISO has agreements with area black-start capable units in accordance with NYISO bulk power restoration plan. The NYISO restoration plan identifies restoring power to the NPPs as a priority, and the TSO is responsible for coordinating the restoration of off-site power to the NPP. The NPP is considered a critical facility and restoration of power is a priority.
6(g) If there is no effective coordination    Not applicable between the NPP operator and the TSO regarding transmission system maintenance or NPP maintenance activities, please explain why you believe you comply with the provisions of 10 CFR 50.65(a)(4).
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 24 of 26 Losses of offsite power caused by grid failures at a frequency of equal to or greater than once in 20 site-years in accordance with Table 4 of Regulatory Guide 1.155 for complying with 10 CFR 50.63 Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.8. Maintaining SBO coping capabilities in accordance with 10 CFR 50.63.8(a) Has your NPP experienced a total Yes, a LOOP caused by grid failure occurred during August 2003.LOOP caused by grid failure since the plant's coping duration was initially determined under 10 CFR 50.63?8(b) If so, have you reevaluated the No. See additional information in the response to Question 8(d) below.NPP using the guidance in Table 4 of RG 1.155 to determine if your NPP should be assigned to the P3 offsite power design characteristic group?8(c) If so, what were the results of this Both Units 2 and 3 remain 8 hour coping plants.reevaluation, and did the initially determined coping duration for the NPP need to be adjusted?8(d) If your NPP has experienced a total Per RG 1.155 Table 4, Sites that expect to experience a total loss of offsite power caused LOOP caused by grid failure since the by grid failures at a frequency equal to or greater than 20 site-years are considered to be plant's coping duration was initially an Offsite Power Design Characteristic Group 'P3", unless the site has a procedure to determined under 10 CFR 50.63 and recover AC power from reliable alternate (non-emergency)
6(h) If you do not consider and                Not applicable effectively implement appropriate risk management actions during the conditions described above, explain why you believe you effectively addressed the relevant provisions of the associated NRC-endorsed industry guidance.
AC power sources within has not been reevaluated using the approximately one-half hour following a grid failure are considered.
 
guidance in Table 4 of RG 1.155, explain why you believe you comply with Both IP2 and IP3 are already considered as Offsite Power Design Characteristic UP3" with the provisions of 10 CFR 50.63 as 8 hour coping duration.
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 21 of 26 I us s&#xa3;                              I -P  i;,:    -l, V(i) You miiay, as an aiternailve LO      Not appilcaDie. No alternative actions required.
This classification already accounts for a frequency of grid related stated above, or describe what actions loss of offsite power events greater than once per 20 years. Therefore, no reevaluation of you intend to take to ensure that the coping time for either plant is required as a result of a LOOP subsequent to existing NPP maintains its SBO coping evaluations.
questions 6(g) and 6(h) describe what actions you intend to take to ensure that the increase in risk that may result from grid-risk-sensitive maintenance activities is managed in accordance with 10 CFR 50.65(a)(4).
capabilities in accordance with 10 CFR l_l geM Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 25 of 26-_: ro _ -S _. -The IP-RTP-04-00811 Station Blackout Report (Tenera Report), dated March 1990 documents IP2 as Offsite Power Design Characteristic
 
'P3" with an 8 hour coping duration.
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 22 of 26 I .. Ue                                  U              -
This is based on past loss of offsite experience at the site, the probabilities of severe weather, and the independence of offsite power supplies.
Offsite power restoration procedures in accordance with 10 CFR 50.63 as developed in Section 2 of RG 1.155 Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.
The factor used for determining coping duration is the high EDG reliability.
7.-Pibcedures for identifying local power sources' that could be made available to resupply your plant following a LOOP event.
A target reliability of 0.95 gives IP2 a coping duration category of 8 hours.Indian Point Unit 3 NRC Letter Docket No 50-286, dated June 9, 1992 Supplemental Safety Evaluation (SSE)Station Blackout Rule 10 CFR 50.63 states IP3 is an Offsite Power Design Characteristic
Note: Section 2, 'Offsite Power," of RG 1.155 (ADAMS Accession No. ML003740034) states:
'P3" with a minimum required coping duration of 8 hours.
Procedures should include the actions necessary to restore offsite power and use nearby power sources when offsite power is unavailable. As a minimum, the following potential causes for loss of offsite power should be considered:
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 26 of 26 Actions to ensure compliance 9: If y-ou-determine th-at any-actio-n is-warranted to bring your NPP into compliance with NRC regulatory requirements, including TSs, GDC 17, 10 CFR 50.65(a)(4), 10 CFR 50.63, 10 CFR 55.59 or 10 CFR 50.120, describe the schedule for implementing it.Areas of non-compliance were entered in the Corrective Action Process and will drive the actions necessary to implement changes to bring the condition into compliance and will include a detailed schedule.CR-IP2-2006-01450 was initiated to change operations procedure to give the Operators direct guidance that when notified by the TO of the Real-time Contingency Analysis (RTCA) alarm, the Offsite Power Supply will be Inoperable and TS actions will be entered. Additionally, the 133kV criteria will be deleted from the procedure.}}
- Grid under-voltage and collapse
- Weather-induced power loss
- Preferred power distribution system faults that could result in the loss of normal power to essential switchgear buses 7(a) Briefly describe any agreement            IPEC has no agreement with local power sources. The NYISO and the TSO have made with the TSO to identify local            restoration plans which identify how power will be restored to the NPPs as a priority load.
power sources that could be made              The TSO is responsible for coordinating the restoration of off-site power to the NPP. The available to re-supply power to your          NPP is considered a critical facility and restoration of power is a priority.
plant following a LOOP event.
4 7(b) Are your NPP operators trained and        Yes.
tested on identifying and using local         Continuing Licensed Operator Re-qualification Training includes electrical bus and power power sources to resupply your plant          supply training. Also included is training on applicable Abnormal Operating procedures, following a LOOP event? If so, describe        which address re-energizing plant electrical systems following a LOOP.
how.
I    This includes items such as nearby or onsite gas turbine generators, portable generators, hydro generators, and black-smttZOI
                      *I..MIJVwII EVICTSILO.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 23 of 26 g!le t.
7(c) if you nave not established an      !
                                              .-    MIa Not appiicabie.
I agreement with your plant's TSO to identify local power sources that could    The NYISO has agreements with area black-start capable units in accordance with NYISO be made available to resupply power to    bulk power restoration plan. The NYISO restoration plan identifies restoring power to the your plant following a LOOP event,        NPPs as a priority, and the TSO is responsible for coordinating the restoration of off-site explain why you believe you comply with    power to the NPP. The NPP is considered a critical facility and restoration of power is a the provisions of 10 CFR 50.63, or        priority.
describe what actions you intend to take to establish compliance.
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 24 of 26 Losses of offsite power caused by grid failures at a frequency of equal to or greater than once in 20 site-years in accordance with Table 4 of Regulatory Guide 1.155 for complying with 10 CFR 50.63 Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.
: 8. Maintaining SBO coping capabilities in accordance with 10 CFR 50.63.
8(a) Has your NPP experienced a total      Yes, a LOOP caused by grid failure occurred during August 2003.
LOOP caused by grid failure since the plant's coping duration was initially determined under 10 CFR 50.63?
8(b) If so, have you reevaluated the        No. See additional information in the response to Question 8(d) below.
NPP using the guidance in Table 4 of RG 1.155 to determine if your NPP should be assigned to the P3 offsite power design characteristic group?
8(c) If so, what were the results of this  Both Units 2 and 3 remain 8 hour coping plants.
reevaluation, and did the initially determined coping duration for the NPP need to be adjusted?
8(d) If your NPP has experienced a total Per RG 1.155 Table 4, Sites that expect to experience a total loss of offsite power caused LOOP caused by grid failure since the       by grid failures at a frequency equal to or greater than 20 site-years are considered to be plant's coping duration was initially      an Offsite Power Design Characteristic Group 'P3", unless the site has a procedure to determined under 10 CFR 50.63 and           recover AC power from reliable alternate (non-emergency) AC power sources within has not been reevaluated using the          approximately one-half hour following a grid failure are considered.
guidance in Table 4 of RG 1.155, explain why you believe you comply with Both IP2 and IP3 are already considered as Offsite Power Design Characteristic UP3" with the provisions of 10 CFR 50.63 as          8 hour coping duration. This classification already accounts for a frequency of grid related stated above, or describe what actions      loss of offsite power events greater than once per 20 years. Therefore, no reevaluation of you intend to take to ensure that the       coping time for either plant is required as a result of a LOOP subsequent to existing NPP maintains its SBO coping               evaluations.
capabilities in accordance with 10 CFR l_l
 
Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 25 of 26 geM  -_:  ro -S _ _.
The IP-RTP-04-00811 Station Blackout Report (Tenera Report), dated March 1990 documents IP2 as Offsite Power Design Characteristic 'P3" with an 8 hour coping duration. This is based on past loss of offsite experience at the site, the probabilities of severe weather, and the independence of offsite power supplies. The factor used for determining coping duration is the high EDG reliability. A target reliability of 0.95 gives IP2 a coping duration category of 8 hours.
Indian Point Unit 3 NRC Letter Docket No 50-286, dated June 9, 1992 Supplemental Safety Evaluation (SSE)
Station Blackout Rule 10 CFR 50.63 states IP3 is an Offsite Power Design Characteristic
    'P3" with a minimum required coping duration of 8 hours.
 
Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 26 of 26 Actions to ensure compliance 9: If y-ou-determine th-at any-actio-n is-warranted to bring your NPP into compliance with NRC regulatory requirements, including TSs, GDC 17, 10 CFR 50.65(a)(4), 10 CFR 50.63, 10 CFR 55.59 or 10 CFR 50.120, describe the schedule for implementing it.
Areas of non-compliance were entered in the Corrective Action Process and will drive the actions necessary to implement changes to bring the condition into compliance and will include a detailed schedule.
CR-IP2-2006-01450 was initiated to change operations procedure to give the Operators direct guidance that when notified by the TO of the Real-time Contingency Analysis (RTCA) alarm, the Offsite Power Supply will be Inoperable and TS actions will be entered. Additionally, the 133kV criteria will be deleted from the procedure.}}

Latest revision as of 07:34, 14 March 2020

Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power
ML061010632
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 04/03/2006
From: Dacimo F
Entergy Nuclear Northeast
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-06-002, NL-06-043
Download: ML061010632 (29)


Text

Entergy Nuclear Northeast Indian Point Energy Center 450 Broadway, GSB IEnlerg <y 0 P.O. Box 249 Buchanan, NY 10511-0:249 Tel 914 734 6700 Fred Dacimo Site Vice President Administration April 3, 2006 Re: Indian Point Units 2 & 3 Dockets 50-247 & 50-286 NL-06-043 U.S. Nuclear Regulatory Commission ATTN:Document Control Desk 115!55 Rockville Pike Rocville, Maryland 20852

Subject:

Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power

Reference:

1. NRC Generic Letter 2006-02, GridReliability and the Impact on Plant Risk and the Operabilityof Offsite Power, dated February 1,2006

Dear Sir or Madam:

The NRC issued Generic Letter 2006-02 (Reference 1) to request information for determining compliance with regulatory requirements governing electric power sources. Specifically, the NRC is requesting information regarding (1) use of protocols between the nuclear power plant (NP]') and the transmission system operator (TSO), independent system operator (ISO), or reliability coordinator/authority (RC/RA) including transmission load flow analysis tools (analysis tools) by TSOs to assist NPPs in monitoring grid conditions to determine the operability of offsite power systems under plant Technical Specification (TS); (2) use of NPP/TSO protocols and analysis tools by TSOs to assist NPPs in monitoring grid conditions for consideration in maintenance risk assessments; (3) offsite power restoration procedures in accordance with Section 2 of NRC Regulatory Guide (RG) 1.155, "Station Blackout;" and, (4) losses of offsite power caused by grid failures at a frequency equal to or greater than once in 20 site-years in accordance with RG 1.155. The requested information is being provided under the requirements of 10 CFR 50.54(f).

Attaihment 1 to this letter provides the Entergy Nuclear Operations, Inc. (ENO) response for Indian Point Unit 2 and 3 to Generic Letter 2006-02. Generic Letter 2006-02 discusses compliance with General Design Criterion (GDC) 17 and several other 10CFR50 requirements in several locations. The exact extent of the compliance of IP2 and IP3 to the GDC are desc:ibed in each plant's Updated Final Safety Analysis Report.

A4{/

Sorae of the questions in Generic Letter 2006-02 seek information, procedures and activities concerning grid reliability which is provided by the TSO and/or ISO. ENO has not independently verified all information provided by:

  • Consolidated Edison Company of New York, Inc.

Thi; letter contains no new commitments. Should you or your staff have any questions regarding this response, please contact Mr. Patric W. Conroy, Manager, Licensing at (914) 734-6668.

I declare under penalty of perjury that the foregoing is true and correct. Executed on

3 2006.

V ru styours, R. Dacimo Site Vice President Indian Point Energy Center : Response to Generic Letter 2006-02, Grid Reliability and the Impact On Plant Risk and the Operability of Offsite Power cc:

Mr. Samuel J. Collins, Regional Administrator, Region I Mr. John Boska, NRR Senior Project Manager IPEC NRC Resident Inspector's Office, Indian Point Unit 2 IPEC NRC Resident Inspector's Office, Indian Point Unit 3 Mr. ?aul Eddy, New York State Department of Public Service Mr. Peter R. Smith, President NYSERDA

Attachment 1 to NL-06-043 RESPONSE TO GENERIC LETTER 2006-02, GRID RELIABILITY AND THE IMPACT ON PLANT RISK AND THE OPERABILITY OF OFFSITE POWER (26 Pages)

ENTERGY NUCLEAR OPERATIONS, INC.

Indian Point Nuclear Generating Unit No. 2 Docket No. 50-247 Indian Point Nuclear Generating Unit No. 3 Docket No. 50-286

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page I of 26 Note The following provides a description of the IPEC off-site power system at Indian Point.

Unit 2: Offsite power is supplied from the offsite transmission network to the plant by two electrically and physically separated circuits (a 138kV circuit and a 13.8kV circuit). All offsite power enters the plant via 6.9kV buses Nos. 5 and 6 which are normally connected to the 138kV offsite circuit but have the ability to be connected to the 13.8kV offsite circuit. The 138kV offsite circuit satisfies the requirement in GDC 17 that at least one of the two required circuits can, within a few seconds, provide power to safety-related equipment following a loss-of-coolant accident. The 13.8kV offsite circuit is considered a delayed access circuit because operator action is normally required to supply offsite power to the plant using the 13.8kV offsite source.

Unit 3:Offsite power is supplied to the plant from the transmission network by two electrically and physically separated circuits, the 138kV or normal circuit and the 13.8kV or alternate circuit. Each of the offsite circuits from the Buchanan substation into the plant is required to be supported by a physically independent circuit from the offsite network into the Buchanan substation. All offsite power enters the plant via 6.9kV buses Nos. 5 and 6 which are connected to the 138kV (normal) offsite circuit and have the ability to be connected to the 13.8kV (alternate) offsite circuit. The arrangement satisfies the requirement that at least one of the two required circuits can within a few seconds; provide power to safety-related equipment following a loss-of-coolant accident. Operator action is required to supply offsite power to the plant using the 13.8kV (alternate) offsite source.

The key points to highlight here are as follows:

1. Both units' safeguards loads are powered from the 480V System. The connection to the offsite 138kV and 13.8kV circuits are via the six buses of the 6.9kV System. The arrangement of these six 6.9kV buses allows various alignments to both the 138kV and 13.8kV system and the 480V safeguards buses follow these alignments accordingly. Two of the six 6.9kV buses and consequently two of the associated 480V safeguards trains are directly connected to the 138kV offsite circuit, but can also be connected to the 13.8kV offsite circuit via manual transfer.
2. As described above, both units have two of the three available trains of safeguards loads connected directly to the preferred offsite circuit (138kV), via two of the six buses of the 6.9kV System, during normal operation and as such, there is no transfer action involved. Normal operation includes start-up, hot shutdown, cold shutdown, etc. The third train would be auto-transferred to the preferred offsite circuit during a unit trip from power operation (Mode 1) condition. Both plants design basis requires two of three safeguards trains to mitigate a loss of coolant accident.
3. There is no auto-transfer to the alternate 13.8kV offsite circuit from the 138kV circuit. This transfer, when needed, is manually performed at the 6.9kV System voltage level, and controlled by plant operating procedures. The procedures call for the Transmission Owner (TO)

(i.e., ConEd) to be notified whenever the 13.8kV offsite circuit is to be used for plant operating load. This is because the 13.8kV offsite circuit is a local distribution circuit that also powers residential and commercial loads and the TO maintained voltage level is based on the load on the circuit. The higher the load, the higher the voltage that the TO maintains. The 13.8kV offsite circuit is controlled by a TO procedure and based on the load on the circuit, the circuit voltage is set accordingly. The lowest specified voltage permitted on this circuit is 13.4KV. TO notifications (to and from IPEC) are based on this value as well.

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 2 of 26 Roth the I 3RIA/ ~

and the I13.R.A/! cir-uine are m0nfit^Ir by bi Siaiiur- procedures. However only the 138kV offsite circuit is monitored by the On-line AC Contingency Monitoring Program. The 13.8kV offsite circuit is monitored by the TO from its Energy Control Center via a Real-time State Estimator (RTISE) Voltage Profile display. This display provides voltage monitoring and alarming functions and the operations procedure contains the necessary notification responsibilities and notification voltages for both the 138kV and 13.8kV offsite circuits.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 3 of 26 r.MWAT*VMAI Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA and the use of analysis tools by TSOs to assist NPP licensee in monitoring grid conditions to determine the operability of offsite power systems under plant TS.

GDC 17, 10 CFR Part 50, Appendix A, requires that licensees minimize the probability of the loss of power from the transmission network given a loss of the power generated by the nuclear power unit(s).

1. Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA to assist the NPP licensee in monitoring grid conditions to determine the operability of offsite power systems under plant TS.

I(a) Do you have a formal agreement or protocol with your TSO? In the New York Reliability Coordinator Area the New York Independent System Operator (NYISO) has operational authority over the bulk power system. The Transmission Owners (TO) have operational authority over the non-bulk power system. The NYISO operates the bulk power system in accordance with NERC, NPCC and New York State Reliability Council (NYSRC) criteria. Established communications protocols are between the NYISO and the Transmission Owners (TO). Communications to the generating resources are through the TOs. The associated TO monitors the localized grid conditions and coordinates issues such as off site power operability with the NPP. In this document TSO refers to the TO.

Yes, IPEC has a number of formal agreements with the NYISO and TOs (which also performs the TSO function for IPEC as follows:

  • IPEC Unit 3 Interconnection Agreement with the Consolidated Edison Company of New York, Inc.

(Con Ed)

  • IPEC Unit 2 Indian Point Continuing Site Agreement with Consolidated Edison Company of New York, Inc.
  • NYISO Customer & Guest Application Form of Service Agreement for NYISO Market Administration and Control Area Service Tariff
  • Transaction Form between Entergy-IPEC and Con Edison for 138kV and 13.8kV monitoring and notification services The NYISO and TSO agreements require all parties to operate per NYISO and/or TSO procedures and documents, therefore the NYISO and TSO procedures and documents are considered part of the formal agreements.

Compliance with GDC-17, as documented in the IPEC license basis and plant Technical Specifications, is not

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 4 of 26 II *I.

picuicatcu on such an agreemeni.

I (b) Describe any grid conditions that would The TSO is required to notify IPEC as soon as practical per good utility practice whenever an impaired or trigger a notification from the TSO to the potentially degraded grid condition is recognized by the TSO. Specific examples of known potentially NPP licensee and degrading conditions identified in the agreement include:

1. De-energizing, switching or in-service work on critical transmission lines if there is a time period required for the 2. Potentially damaging inclement weather notification 3. Solar Magnetic Disturbances
4. Post-contingency voltage alarm for the 138kV transmission system after 30-minutes.
5. Areal-time 13.8kV degraded voltage condition below a normal system schedule voltage after 30-minutes
6. Prior to any 138kV feeder, which could impact IPEC being removed or restored to service
7. When the TSO 138kV or 13.8kV monitoring and alarm capability are out of service and have not been restored after 30-minutes.
8. Other system or equipment conditions determine by the TSO to be of importance to IPEC.

I (c) Describe any grid conditions that would Grid conditions and status are the primary responsibility of ISO and TSO.

cause the NPP licensee to contact the TSO.

Relative to this question, "grid conditions' is assumed to be IPEC changes that impact the TSO real-time post Describe the procedures associated with such contingency analysis capability. IPEC typically notified ISO and/or TSO for changes in the following grid a communication. If you do not have conditions:

procedures, describe how you assess grid conditions that may cause the NPP licensee to 0 Unit power capability changes contact the TSO. 0 Unit Startup and Shutdown 0 Modifications resulting in changes to generator electrical characteristics S Breaker alignment and offsite voltage verification 0 MVAR Loading 0 Post-trip off-site voltage criteria 0 Changes in IPEC post trip station and accident loading

.0 Loss of preferred 138KV Offsite Power Supply 0 Loss of 13.8KV Offsite Power Supply 0 Status of 13.8kv and 138kv 0 Maintenance activities directly affecting Switchyard components

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 5 of 26 I 5 I a Mvieihod of voitage controi, automatic or manual.

EDG Surveillance Testing 0 Load tap changer position / Auto-Manual Mode I(d) Describe how NPP operators are trained The Licensed Operators at IPEC have had training on site procedure that addresses offsite power continuous and tested on the use of monitoring and notification. This procedure establishes monitoring, and notification responsibilities of the Buchanan Substation, as well as the interface between the IPEC and Con Edison's Energy Control Center. The the procedures or most recent training occurred in Cycle 3 of 2005.

assessing grid conditions in question I (c).

Typically, IPEC operators are trained and tested, using procedures, on the following:

  • System Restoration Typically, IPEC operators are trained, using procedures, on the following:
  • System Restoration e Degraded voltage conditions
  • Voltage (number for inadequate grid capacity)
  • VARs
  • Breaker status
  • Notification of the ISO and/or TSO of changed conditions.

1(e) If you do not have a formal agreement or As previously stated, IPEC does have a formal agreement with the TSO. Prompt notification from the TSO protocol with your TSO, describe why you (after 30-minutes) and a pre-trip analysis of whether the post-trip voltage will be below acceptable values are believe you continue to comply with the included in Indian Point Energy Center Offsite Power Continuous Monitoring And Notification procedure.

provisions of GDC 17 as stated above, or Additionally TSO procedure describes Con Edison responsibility to notify IPEC of low voltage issues as it describe what actions you intend to take to relates to the 138kV and 13.8kV systems. The procedure requires the TSO to notify both IP2 & IP3 Control assure compliance with GDC 17. Rooms after 30-minutes if the real-time analysis tool determines the post IPEC trip voltage would be below the value specified by IPEC. In addition, the TSO will notify IPEC after 30-minutes if the 13.8kV system voltage is below the normal system voltage schedule.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 6 of 26

!.'11 EMM - -sI~l, Comluianut: wit CiiGC-i, kir2 and ii;3 are not a GDU plants, the FSARs describe to what extent 1P2 and IP3 were reviewed to the draft GDCs or its equivalent is not predicated on this agreement).

I(f) If you have an existing formal As previously stated, IPEC does have formal agreements with the TSO. These agreements require the TSO to interconnection agreement or protocol that notify IPEC as soon as practicable per good utility practice, upon receipt of a potential post-trip degraded ensures adequate communication and voltage alarm.

coordination between the NPP licensee and the TSO, describe whether this agreement or protocol requires that you be promptly notified when the conditions of the surrounding grid could result in degraded voltage (i.e., below TS nominal trip setpoint value requirements; including NPP licensees using allowable value in its TSs) or LOOP after a trip of the reactor unit(s).

I(g) Describe the low switchyard voltage These are the Switchyard voltage conditions that will initiate operation of IPEC degraded voltage protection conditions that would initiate operation of i. 138 kv Offsite Power Source <133kv plant degraded voltage protection. ii. 13.8kv Offsite Power Source <13.4kv Note: The design of these systems is described in front of this attachment.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 7 of 26

2. Use of criteria and methodologies to assess whether the offsite power system will become inoperable as a result of a trip of your NPP.

2(a) Does your NPP's TSO use any Yes. The TSO, uses a State Estimator and a Contingency Evaluation Program to analyze analysis tools, an online analytical real time and contingency voltage levels and thermal loading for IPEC 138kV off-site transmission system studies program, or sources.

other equivalent predictive methods to determine the grid conditions that would The 138kV transmission system program and related actions are summarized as follows:

make the NPP offsite power system inoperable during various Real-Time Contingency Analysis Program: The program and related actions are contingencies? summarized as follows; the program utilizes real-time transmission system information If available to you, please provide a brief and nuclear generating unit specific shutdown loads and minimum voltage description of the analysis tool that is requirements. The program creates a model by combining real-time telemetry with used by the TSO. the network model. The network model includes the nuclear power plant facilities.

The State Estimator is then used to provide a consistent power flow that is used to run the contingencies. The contingency case assumes the simultaneous loss of the generator and the addition of load at the appropriate bus. An alarm is issued if the prescribed voltage limits are violated.

The 13.8kV distribution system is monitored on a real-time voltage basis. If the voltage drops below a predetermined 13.8kV system voltage value, IPEC is notified. This approach is determined to be acceptable because the 13.8kV off-site source is a manually aligned supply and the predetermined notification value is at the lower limit of the 13.8kV systems normal voltage schedule. Therefore, the TSO will make all reasonable efforts to maintain the voltage schedule.

2(b) Does your NPP's TSO use an Yes. The TSO uses the real-time analysis tool described in 2(a), in conjunction with analysis tool as the basis for notifying procedures, as the basis for determining when conditions warrant IPEC notification of the the NPP licensee when such a condition 138kV system.

is identified? If not, how does the TSO determine if conditions on the grid As described above the TSO use real-time voltage monitoring, in conjunction with warrant NPP licensee notification? procedures, as basis to determining when conditions warrant IPEC notification of the 13.8kV system.

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043

-- - Page 8 of 26 II yOum J I vJ UQ~Oc am CA am mGl yoia LvuI, l

I 'es. IFI S aIai-Liine ayaiSis ivoi for ihe i35KV, in conjunction witn i-'E; plant load would the analysis tool identify a flow studies, have the capability to determine if the trip of their IPEC plants would result in condition in which a trip of the NPP a switchyard voltage which would actuate the associated unit's degraded voltage would result in switchyard voltages protection logic and initiate separation from the offsite power source.

(immediate and/or long-term) falling below TS nominal trip setpoint value The 13.8kV source is a manually aligned distribution system, which the TSO has local requirements (including NPP licensees resources available to adjust system voltage. Prior to IPEC aligning the 480VAC safety using allowable value in its TSs) and buses to the 13.8 kV system (via the 6.9 kV system), communication between the TSO consequent actuation of plant degraded and IPEC is required to ensure the adequacy of the 13.8 kV system voltage to support voltage protection? accident loads.

If not, discuss how such a condition would be identified on the grid.

2(d) If your TSO uses an analysis tool, The TSO 138kV real-time analysis tool presently resolves the IPEC Unit 2 and IPEC Unit how frequently does the analysis tool 3 trip contingencies every minute for the steady state conditions.

program update?

2(e) Provide details of analysis tool- The 138kV IPEC Unit 2 and IPEC Unit 3 contingencies results (see response to item 2(a))

identified contingency conditions that are automatically compared to off-site post trip voltage limits. If any limit is violated, an would trigger an NPP licensee alarm is generated and IPEC is notified if not cleared after 30 minutes notification from the TSO.

2(f) If an interface agreement exists Yes. IPEC would be notified by the TSO when:

between the TSO and the NPP licensee, does it require that the NPP licensee be

  • When all three 138 kV monitoring and alarm systems are out of service and have notified of periods when the TSO is not been restored within 30 minutes.

unable to determine if offsite power

  • When the 13.8 kV monitoring and alarm systems are out of service and have not voltage and capacity could be been restored within 30 minutes.

inadequate?

Loss of the voltage prediction tool alone has no impact on operability. If notified by the If so, how does the NPP licensee TSO that the Low Voltage Contingency Alarm is inoperable, then the IPEC Operators determine that the offsite power would perform the following:

remain operable when such a 1. Contact the TSO once per shift to verify imminent/expected degraded voltage notification is received? conditions do not exist.

l 2. Minimize large electrical load changes

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 9 of 26 li]Zs1Me g I M5 M-. . M M J. Mtintraize iutaidriance and testing of the electrical distribution system. i

4. Terminate maintenance or testing on critical components of the electrical distribution system as soon as possible.
5. Limit MVAR Output (OP2 only) 2(g) After an unscheduled inadvertent No. Verification of the post trip 138kV switchyard voltage real-time analysis results against trip of the NPP, are the resultant actual post trip voltage is not performed. Since the real-time analysis tool uses real time switchyard voltages verified by system data and assumed worst case station loads a comparison of values would be procedure to be bounded by the difficult even if the real-time analysis predicted values were available which they are not; voltages predicted by the analysis tool?

2(h) If an analysis tool is not available to This question is not applicable to IPEC. The TSO has a real-time analysis tool presently in the NPP licensee's TSO, do you know if use for the 138kV system as discussed above.

there are any plans for the TSO to obtain one? If so, when? The TSO has no plans to install a real-time contingency monitor for the 13.8 kV off-site power source.

2(i) If an analysis tool is not available, Not Applicable for the 138kV transmission lines, TSO uses real-time analysis tool as does your TSO perform periodic studies discussed above.

to verify that adequate offsite power capability, including adequate NPP post- IPEC performs periodic station load flow studies to ensure that the minimum 13.8kV trip switchyard voltages (immediate scheduled voltage is adequate to support voltage requirements.

and/or long-term), will be available to the NPP licensee over the projected timeframe of the study?

(a) Are the key assumptions and parameters of these periodic studies translated into TSO guidance to ensure that the transmission system is operated within the bounds of the analyses?

(b) If the bounds of the analyses are exceeded, does this condition trigger the notification provisions discussed in question 1 above?

[l ______ I ___ ___________

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 we]

S

  • tii.!

I I-. ..

I M*1111 P-r --

AA  ! t! _ e- -

Page IUof26 I.

I - /i\ shoe I WS I OWL LW7, IJI 7LDU UV iivti apPICIavult: I I O0KV arIU 13.0 KV Oystems i

not have access to the results of an analysis tool, or your TSO does not perform and make available to you periodic studies that determine the adequacy of offsite power capability, please describe why you believe you comply with the provisions of GDC 17 as stated above, or describe what compensatory actions you intend to take to ensure that the offsite power system will be sufficiently reliable and remain operable with high probability following a trip of your NPP.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 11 of 26 W~ 0 1'lll 3.Use of criteria and methodologies to-assess whether the NPP's offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.

3(a) If the TSO notifies the NPP IPEC would declare the 138kV off-site source "inoperable". The TSO has real-time operator that monitor capability for the 138kV source and IPEC is notified by the TSO if the loss of the unit would result in an unacceptable off-site post-trip voltage. There are no identified

  • a trip of the NPP, or system conditions where the loss of a transmission line or large supply would result in the
  • the loss of the most critical trip of the generator.

transmission line or

  • the largest supply to the grid would result in switchyard voltages (immediate and/or long-term) below TS nominal trip setpoint value requirements (including NPP licensees using allowable value in its TSs) and would actuate plant degraded voltage protection, is the NPP offsite power system declared inoperable under the plant TSs? If not, why not? 3(b) If onsite safety-related equipment IPEC is not designed for double sequencing events. LOCA with a Delayed LOOP is (e.g., emergency diesel generators or outside the design basis for both IP2 and IP3.

safety-related motors) is lost when subjected to a double sequencing (LOCA with delayed LOOP event) as a result of the anticipated system performance and is incanihie of performing its safety functions as a

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 12 of 26 I _SUIL e'=,

%J;IsV-0JU ju n IVLJ al 1I W IIC!J llcy I". !- in

' M actuation signal during this condition, is the equipment considered inoperable?

If not, why not?

3(c) Describe your evaluation of onsite Indian Point Units 2 and 3 are designed to a GDC that postulates a LOCA concurrent with safety-related equipment to determine a LOOP. Neither plant models a LOCA with Delayed LOOP scenario in its voltage profile whether it will operate as designed and loading analyses, because this event is outside the design basis of both units.

during the condition described in question 3(b).

3(d) If the NPP licensee is notified by This condition is addressed by our site procedures. Under these circumstances we would the TSO of other grid conditions that enter the applicable site procedure for offsite power continuous monitoring and may impair the capability or availability notification, a Technical Specification action statement would not be entered until an of offsite power, are any plant TS action applicable system, structure or component was declared inoperable.

statements entered? If so, please identify them.

3(e) If you believe your plant TSs do not Not applicable.

require you to declare your offsite power Based on responses, we declare offsite power or applicable equipment inoperable under system or safety-related equipment circumstances as described above.

inoperable in any of these circumstances, explain why you believe you comply with the provisions of GDC 17 and your plant TSs, or describe what compensatory actions you intend to take to ensure that the offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.

3(f) Describe if and how NPP operators The Licensed Operators have been trained on the applicable site procedure for offsite are trained and tested on the power continuous monitoring and notification. This procedure contains the requirements compensatory actions mentioned in your for declaring off-site power inoperable and entering the appropriate Technical answers to questions 3(a) through (e). Specifications.

For events such as LOCAs followed later hy a I nap event the Opnnraors confinuing training includes the sequencing or manual loading of safeguards equipment. The

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 13 of 26 le _I! *- II  ; *  ! ! e I

I McUiMe111iiL to IIIrIIudiIy Iad safeguards equipment is contingent on whether or not tile Safeguards signal has been reset. The site's Westinghouse owner's group Emergency Operating Procedures address these situations. The licensed operators are tested on these procedures and in dynamic simulator evaluations, as applicable.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 14of26 WIinISTAJ*WAO

4. Use of criteria and methodologies to assess whether the offsite power system will remain operable following a trip of your NPP.

4(a) Do the NPP operators have any Yes, procedural guidance for abnormal situations related to this equipment is available to guidance or procedures in plant TS IPEC operators in Annunciator Response Procedures.

bases sections, the final safety analysis report, or plant procedures regarding The operators are trained and tested on systems such as the main generator voltage situations in which the condition of plant- regulator and tap changers.

controlled or -monitored equipment (e.g., voltage regulators, auto tap changing transformers, capacitors, static VAR compensators, main generator voltage regulators) can adversely affect the operability of the NPP offsite power system? If so, describe how the operators are trained and tested on the guidance and procedures.

4(b) If your TS bases sections, the final Not applicable.

safety analysis report, and plant procedures do not provide guidance regarding situations in which the condition of plant-controlled or -

monitored equipment can adversely affect the operability of the NPP offsite power system, explain why you believe you comply with the provisions of GDC 17 and the plant TSs, or describe what actions you intend to take to provide such guidance or procedures.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 15 of 26 Use of NPP licensee/TSO protocols and analysis tool by TSOs to assist NPP licensees in monitoring grid conditions for consideration in maintenance risk assessments The Maintenance Rule (10 CFR 50.65(a)(4)) requires that licensees assess and manage the increase in risk that may result from proposed maintenance activities before performing them.

5. Performance of grid reliability evaluations as part of the maintenance risk assessments required by 10 CFR 50.65(a)(4).

5(a) Is a quantitative or qualitative grid Yes reliability evaluation performed at your NPP as part of the maintenance risk IPEC performs qualitative risks assessment as required by 10 CFR 50.65 and IPEC assessment required by 10 CFR Plant Technical Specification. The program is implemented by IPECNPP On-Line Risk 50.65(a)(4) before performing grid-risk- Assessment and Outage Risk Assessment procedures.

sensitive maintenance activities? This These procedures require plant risk assessment before removing equipment from includes surveillances, post-maintenance service for planned maintenance activities, or upon discovery of equipment out of service testing, and preventive and corrective that is unplanned.

maintenance that could increase the probability of a plant trip or LOOP or The IPECNPP On-Line Risk Assessment procedure requires an evaluation of current impact LOOP or SBO coping capability, and anticipated grid conditions before removing risk significant equipment from service.

for example, before taking a risk- The Equipment Out of Service (EOOS) Monitor is a computer based program that is significant piece of equipment (such as used to calculate Core Damage Frequency and conditional Core Damage Frequency for an EDG, a battery, a steam-driven pump, the plant equipment configuration and testing activities for both planned and unplanned an alternate AC power source) configurations.

out-of-service? The IPECNPP Work Management procedure requires a risk plan development for activities that would increase grid instability in combination with external events.

5(b) Is grid status monitored by some Yes means for the duration of the grid-risk-sensitive maintenance to confirm the continued validity of the risk assessment and is risk reassessed when warranted?

If not, how is the risk assessed during

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 16 of 26 WE .  !!S**!i. -- " -

I -;- J _., -s - -- &.._ __:- -- - - - n H41 u1-1f-0 ;>1o 10LV ;> tic 1 fl 1 lsL Fa1 1VV

-I.

5(c) Is there a significant variation in the Yes stress on the grid in the vicinity of your The NYISO Reliability Coordination Area is a summer peaking area. Due to high intra NPP site caused by area and inter area power flows, it would be expected that the grid would be stressed.

However, this stress is managed through facility maintenance coordination. During the seasonal loads summer peak season scheduled transmission facility maintenance is avoided in June, July and August if possible.

or Anytime that maintenance is scheduled, the schedules are managed in order to maintain maintenance activities associated with operation of the bulk power system within established operating criteria.

critical transmission elements?

Is there a seasonal variation (or the No, based on the limited number of LOOP occurrences in the NYISO region over the potential for a seasonal variation) in the past 10 years, no seasonal variation can be established. IPEC last experienced a LOOP frequency in the local transmission transmission system related LOOP on August 14, 2003.

region?

If the answer to either question is yes, discuss the time of year when the variations occur and their magnitude.

5(d) Are known time-related variations in No. However, Con Edison the TSO by procedure does not schedule feeder outages the probability of a LOOP at your plant between May 1 and September 15 due to summer loading concerns. IPEC will not site considered in the grid-risk-sensitive schedule maintenance activities during this time. IPEC will schedule emergent activities maintenance evaluation? If not, what is to address issues that could pose a threat to grid stability.

your basis for not considering them?

5(e) Do you have contacts with the TSO Yes.

to determine current and anticipated grid conditions as part of the grid reliability TSO Communication contacts are available for assessment of grid conditions before and evaluation performed before conducting during the performance of grid-risk sensitive maintenance activities.

grid-risk-sensitive maintenance activities?

5(f) Describe any formal agreement or Site level procedures provide the guidance on scheduling. The procedure for protocol that you have with your TSO to performance of the offsite power continuous monitoring and notification contains assure that you are promptly alerted to a jguidelines for risk management of feeder outages. This would include the ability to

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 IMMUNE~)Page 17 of26 us., -S. -I l...- - -n -__

VV'jIQVI III

_-. A__L A __, ,

UalIU .,UIIUILIuII tIaL IdL t II y

CIIyI l

restiict wor'Korku feoeers iquriiiiit oi q deum o U WIairitefrince on grid equipment. Tne Hiant during a maintenance activity. models grid feeder outage in the risk assessment Program EOOS.

Notification occurs whether or not maintenance is on-going. The TSO is required to notify IPEC whenever an impaired or potentially degraded grid condition is recognized by the TSO. Specific examples of known potentially degrading conditions identified in the agreement include:

1. De-energizing, switching or in-service work on critical transmission lines.
2. Potentially damaging inclement weather.
3. Solar Magnetic Disturbances.
4. Post-contingency voltage alarm for the 138kV transmission system after 30-minutes.
5. A real-time 13.8kV degraded voltage condition below a normal system schedule voltage after 30-minutes.
6. Prior to any 138kV feeder outage which could impact IPEC being removed or restored to service
7. When the TSO 138kV or 13.8kV monitoring and alarm capability are out of service and have not been restored after 30-minutes.
8. Other system or equipment conditions determine by the TSO to be of importance to IPEC.

5(g) Do you contact your TSO periodically Yes.

for the duration of the grid-risk-sensitive Additionally the TSO is contacted before the start of grid- risk sensitive maintenance maintenance activities? activities and at the completion of the activity. Changes to grid conditions are communicated to IPEC as stated in 5(f).

5(h) If you have a formal agreement or The formal agreement with the System Operator at IPEC is described in the offsite protocol with your TSO, describe how power continuous monitoring and notification station procedure. This procedure NPP operators and maintenance establishes monitoring, and notification responsibilities of the Buchanan Substation, as personnel are trained and tested on this well as the interface between the IPEC and Con Edison's Energy Control Center. The formal agreement or protocol. Licensed Operators have had training on this procedure. The most recent training occurred in Cycle 3 of 2005.

____There was no testing associated with this training.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 18 of 26 56.6 0~ M- I Maintenance personnel do not have training on this agreement or procedure because Operations and Work Control assess the risk and conditions for performing maintenance activities.

5(i) If your grid reliability evaluation, Not applicable.

performed as part of the maintenance risk assessment required by 10 CFR 50.65(a)(4), does not consider or rely on some arrangement for communication with the TSO, explain why you believe you comply with 10 CFR 50.65(a)(4).

50) If risk is not assessed (when Not applicable warranted) based on continuing communication with the TSO throughout the duration of grid-risk-sensitive maintenance activities, explain why you believe you have effectively implemented the relevant provisions of the endorsed industry guidance associated with the maintenance rule.

5(k) With respect to questions 5(i) and Not applicable. No alternative actions required.

50), you may, as an alternative, describe what actions you intend to take to ensure that the increase in risk that may result from proposed grid-risk-sensitive activities is assessed before and during grid-risk-sensitive maintenance activities, respectively.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 19of26

6. - Use of risk assessment results, including the results of grid reliability evaluations, in managing maintenance risk, as required by 10 CFR 50.65(a)(4). -- - .

TSO does grid reliability evaluations; not NPPs. ugrid reliability evaluations" Enter AP, if notified un-normality on grid.

6(a) Does the TSO coordinate Yes.

transmission system maintenance The TSO coordinates all scheduled work activities with the plant. The Process is activities that can have an impact on the described in site level procedures.

NPP operation with the NPP operator?

6(b) Do you coordinate NPP Yes.

maintenance activities that can have an IPEC coordinates all scheduled work activities with the TSO. The plant process is impact on the transmission system with described in site procedures.

the TSO?

6(c) Do you consider and implement, if Yes.

warranted, the rescheduling of grid-risk- IPEC will reschedule activities as required to prevent challenging the stability of the local sensitive maintenance activities Grid. This would include activities which would likely cause plant trip or loss of off site (activities that could (i) increase the power. Guidance is described in site procedures. If the Grid voltage degrades to a point likelihood of a plant trip, (ii) increase where it challenges the NPP, the TSO will immediately correct it or notify the IPEC Control LOOP probability, or (iii) reduce LOOP room operators. IF emergent equipment outage occurs the TSO will notify the control or SBO coping capability) under room. The Switchyard coordinator or lead system engineer will be notified. A risk existing, imminent, or worsening assessment evaluation will be performed and if applicable, restrict feeders as required.

degraded grid reliability conditions?

6(d) If there is an overriding need to Yes.

perform grid-risk-sensitive maintenance Guidance is described in site procedures. The Switchyard coordinator or lead system activities under existing or imminent engineer will be notified. A risk assessment evaluation will be performed and if applicable conditions of degraded grid reliability, or restrict feeders as required.

continue grid-risk-sensitive maintenance when grid conditions worsen, do you Additionally, mitigative actions such as feeder restrictions and protected equipment will be implement appropriate risk management implemented.

actions? If so; describe the actinnq that you would take. (These actions could l

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 20 of 26 f.

Include adteai-iel I quipi mer it pi vzuttutI I

.! --. -i: Iss and compensatory measures to limit or minimize risk.)

6(e) Describe the actions associated Emergent maintenance or declining grid condition guidance is described in site with questions 6(a) through 6(d) above procedures. The operator will perform appropriate actions as required by Technical that would be taken, state whether each Specifications. The Switchyard Coordinator or Lead System Engineer will be notified.

action is governed by documented They will perform a risk evaluation and if applicable restrict feeders as required. The procedures and identify the procedures, feeder or equipment outage will be run through the plant risk program. These actions are and explain why these actions are required by Procedure and must be performed.

effective and will be consistently accomplished.

6(f) De scribe how NPP operators and The Licensed Operators and Work Control Personnel at IPEC were provided training on maintenance personnel are trained and the applicable procedure that addresses Offsite Power Continuous Monitoring and tested to assure they can accomplish Notification. This procedure establishes monitoring, and notification responsibilities of the the actions described in your answers to Buchanan Substation, as well as the interface between the IPEC and Con Edison's question 6(e). Energy Control Center. The most recent training occurred in Cycle 3 of 2005.

There was no testing associated with this training.

6(g) If there is no effective coordination Not applicable between the NPP operator and the TSO regarding transmission system maintenance or NPP maintenance activities, please explain why you believe you comply with the provisions of 10 CFR 50.65(a)(4).

6(h) If you do not consider and Not applicable effectively implement appropriate risk management actions during the conditions described above, explain why you believe you effectively addressed the relevant provisions of the associated NRC-endorsed industry guidance.

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 21 of 26 I us s£ I -P i;,: -l, V(i) You miiay, as an aiternailve LO Not appilcaDie. No alternative actions required.

questions 6(g) and 6(h) describe what actions you intend to take to ensure that the increase in risk that may result from grid-risk-sensitive maintenance activities is managed in accordance with 10 CFR 50.65(a)(4).

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 22 of 26 I .. Ue U -

Offsite power restoration procedures in accordance with 10 CFR 50.63 as developed in Section 2 of RG 1.155 Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.

7.-Pibcedures for identifying local power sources' that could be made available to resupply your plant following a LOOP event.

Note: Section 2, 'Offsite Power," of RG 1.155 (ADAMS Accession No. ML003740034) states:

Procedures should include the actions necessary to restore offsite power and use nearby power sources when offsite power is unavailable. As a minimum, the following potential causes for loss of offsite power should be considered:

- Grid under-voltage and collapse

- Weather-induced power loss

- Preferred power distribution system faults that could result in the loss of normal power to essential switchgear buses 7(a) Briefly describe any agreement IPEC has no agreement with local power sources. The NYISO and the TSO have made with the TSO to identify local restoration plans which identify how power will be restored to the NPPs as a priority load.

power sources that could be made The TSO is responsible for coordinating the restoration of off-site power to the NPP. The available to re-supply power to your NPP is considered a critical facility and restoration of power is a priority.

plant following a LOOP event.

4 7(b) Are your NPP operators trained and Yes.

tested on identifying and using local Continuing Licensed Operator Re-qualification Training includes electrical bus and power power sources to resupply your plant supply training. Also included is training on applicable Abnormal Operating procedures, following a LOOP event? If so, describe which address re-energizing plant electrical systems following a LOOP.

how.

I This includes items such as nearby or onsite gas turbine generators, portable generators, hydro generators, and black-smttZOI

  • I..MIJVwII EVICTSILO.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 23 of 26 g!le t.

7(c) if you nave not established an  !

.- MIa Not appiicabie.

I agreement with your plant's TSO to identify local power sources that could The NYISO has agreements with area black-start capable units in accordance with NYISO be made available to resupply power to bulk power restoration plan. The NYISO restoration plan identifies restoring power to the your plant following a LOOP event, NPPs as a priority, and the TSO is responsible for coordinating the restoration of off-site explain why you believe you comply with power to the NPP. The NPP is considered a critical facility and restoration of power is a the provisions of 10 CFR 50.63, or priority.

describe what actions you intend to take to establish compliance.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 24 of 26 Losses of offsite power caused by grid failures at a frequency of equal to or greater than once in 20 site-years in accordance with Table 4 of Regulatory Guide 1.155 for complying with 10 CFR 50.63 Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.

8. Maintaining SBO coping capabilities in accordance with 10 CFR 50.63.

8(a) Has your NPP experienced a total Yes, a LOOP caused by grid failure occurred during August 2003.

LOOP caused by grid failure since the plant's coping duration was initially determined under 10 CFR 50.63?

8(b) If so, have you reevaluated the No. See additional information in the response to Question 8(d) below.

NPP using the guidance in Table 4 of RG 1.155 to determine if your NPP should be assigned to the P3 offsite power design characteristic group?

8(c) If so, what were the results of this Both Units 2 and 3 remain 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> coping plants.

reevaluation, and did the initially determined coping duration for the NPP need to be adjusted?

8(d) If your NPP has experienced a total Per RG 1.155 Table 4, Sites that expect to experience a total loss of offsite power caused LOOP caused by grid failure since the by grid failures at a frequency equal to or greater than 20 site-years are considered to be plant's coping duration was initially an Offsite Power Design Characteristic Group 'P3", unless the site has a procedure to determined under 10 CFR 50.63 and recover AC power from reliable alternate (non-emergency) AC power sources within has not been reevaluated using the approximately one-half hour following a grid failure are considered.

guidance in Table 4 of RG 1.155, explain why you believe you comply with Both IP2 and IP3 are already considered as Offsite Power Design Characteristic UP3" with the provisions of 10 CFR 50.63 as 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> coping duration. This classification already accounts for a frequency of grid related stated above, or describe what actions loss of offsite power events greater than once per 20 years. Therefore, no reevaluation of you intend to take to ensure that the coping time for either plant is required as a result of a LOOP subsequent to existing NPP maintains its SBO coping evaluations.

capabilities in accordance with 10 CFR l_l

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 25 of 26 geM -_: ro -S _ _.

The IP-RTP-04-00811 Station Blackout Report (Tenera Report), dated March 1990 documents IP2 as Offsite Power Design Characteristic 'P3" with an 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> coping duration. This is based on past loss of offsite experience at the site, the probabilities of severe weather, and the independence of offsite power supplies. The factor used for determining coping duration is the high EDG reliability. A target reliability of 0.95 gives IP2 a coping duration category of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

Indian Point Unit 3 NRC Letter Docket No 50-286, dated June 9, 1992 Supplemental Safety Evaluation (SSE)

Station Blackout Rule 10 CFR 50.63 states IP3 is an Offsite Power Design Characteristic

'P3" with a minimum required coping duration of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 26 of 26 Actions to ensure compliance 9: If y-ou-determine th-at any-actio-n is-warranted to bring your NPP into compliance with NRC regulatory requirements, including TSs, GDC 17, 10 CFR 50.65(a)(4), 10 CFR 50.63, 10 CFR 55.59 or 10 CFR 50.120, describe the schedule for implementing it.

Areas of non-compliance were entered in the Corrective Action Process and will drive the actions necessary to implement changes to bring the condition into compliance and will include a detailed schedule.

CR-IP2-2006-01450 was initiated to change operations procedure to give the Operators direct guidance that when notified by the TO of the Real-time Contingency Analysis (RTCA) alarm, the Offsite Power Supply will be Inoperable and TS actions will be entered. Additionally, the 133kV criteria will be deleted from the procedure.

Text

Entergy Nuclear Northeast Indian Point Energy Center 450 Broadway, GSB IEnlerg <y 0 P.O. Box 249 Buchanan, NY 10511-0:249 Tel 914 734 6700 Fred Dacimo Site Vice President Administration April 3, 2006 Re: Indian Point Units 2 & 3 Dockets 50-247 & 50-286 NL-06-043 U.S. Nuclear Regulatory Commission ATTN:Document Control Desk 115!55 Rockville Pike Rocville, Maryland 20852

Subject:

Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power

Reference:

1. NRC Generic Letter 2006-02, GridReliability and the Impact on Plant Risk and the Operabilityof Offsite Power, dated February 1,2006

Dear Sir or Madam:

The NRC issued Generic Letter 2006-02 (Reference 1) to request information for determining compliance with regulatory requirements governing electric power sources. Specifically, the NRC is requesting information regarding (1) use of protocols between the nuclear power plant (NP]') and the transmission system operator (TSO), independent system operator (ISO), or reliability coordinator/authority (RC/RA) including transmission load flow analysis tools (analysis tools) by TSOs to assist NPPs in monitoring grid conditions to determine the operability of offsite power systems under plant Technical Specification (TS); (2) use of NPP/TSO protocols and analysis tools by TSOs to assist NPPs in monitoring grid conditions for consideration in maintenance risk assessments; (3) offsite power restoration procedures in accordance with Section 2 of NRC Regulatory Guide (RG) 1.155, "Station Blackout;" and, (4) losses of offsite power caused by grid failures at a frequency equal to or greater than once in 20 site-years in accordance with RG 1.155. The requested information is being provided under the requirements of 10 CFR 50.54(f).

Attaihment 1 to this letter provides the Entergy Nuclear Operations, Inc. (ENO) response for Indian Point Unit 2 and 3 to Generic Letter 2006-02. Generic Letter 2006-02 discusses compliance with General Design Criterion (GDC) 17 and several other 10CFR50 requirements in several locations. The exact extent of the compliance of IP2 and IP3 to the GDC are desc:ibed in each plant's Updated Final Safety Analysis Report.

A4{/

Sorae of the questions in Generic Letter 2006-02 seek information, procedures and activities concerning grid reliability which is provided by the TSO and/or ISO. ENO has not independently verified all information provided by:

  • Consolidated Edison Company of New York, Inc.

Thi; letter contains no new commitments. Should you or your staff have any questions regarding this response, please contact Mr. Patric W. Conroy, Manager, Licensing at (914) 734-6668.

I declare under penalty of perjury that the foregoing is true and correct. Executed on

3 2006.

V ru styours, R. Dacimo Site Vice President Indian Point Energy Center : Response to Generic Letter 2006-02, Grid Reliability and the Impact On Plant Risk and the Operability of Offsite Power cc:

Mr. Samuel J. Collins, Regional Administrator, Region I Mr. John Boska, NRR Senior Project Manager IPEC NRC Resident Inspector's Office, Indian Point Unit 2 IPEC NRC Resident Inspector's Office, Indian Point Unit 3 Mr. ?aul Eddy, New York State Department of Public Service Mr. Peter R. Smith, President NYSERDA

Attachment 1 to NL-06-043 RESPONSE TO GENERIC LETTER 2006-02, GRID RELIABILITY AND THE IMPACT ON PLANT RISK AND THE OPERABILITY OF OFFSITE POWER (26 Pages)

ENTERGY NUCLEAR OPERATIONS, INC.

Indian Point Nuclear Generating Unit No. 2 Docket No. 50-247 Indian Point Nuclear Generating Unit No. 3 Docket No. 50-286

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page I of 26 Note The following provides a description of the IPEC off-site power system at Indian Point.

Unit 2: Offsite power is supplied from the offsite transmission network to the plant by two electrically and physically separated circuits (a 138kV circuit and a 13.8kV circuit). All offsite power enters the plant via 6.9kV buses Nos. 5 and 6 which are normally connected to the 138kV offsite circuit but have the ability to be connected to the 13.8kV offsite circuit. The 138kV offsite circuit satisfies the requirement in GDC 17 that at least one of the two required circuits can, within a few seconds, provide power to safety-related equipment following a loss-of-coolant accident. The 13.8kV offsite circuit is considered a delayed access circuit because operator action is normally required to supply offsite power to the plant using the 13.8kV offsite source.

Unit 3:Offsite power is supplied to the plant from the transmission network by two electrically and physically separated circuits, the 138kV or normal circuit and the 13.8kV or alternate circuit. Each of the offsite circuits from the Buchanan substation into the plant is required to be supported by a physically independent circuit from the offsite network into the Buchanan substation. All offsite power enters the plant via 6.9kV buses Nos. 5 and 6 which are connected to the 138kV (normal) offsite circuit and have the ability to be connected to the 13.8kV (alternate) offsite circuit. The arrangement satisfies the requirement that at least one of the two required circuits can within a few seconds; provide power to safety-related equipment following a loss-of-coolant accident. Operator action is required to supply offsite power to the plant using the 13.8kV (alternate) offsite source.

The key points to highlight here are as follows:

1. Both units' safeguards loads are powered from the 480V System. The connection to the offsite 138kV and 13.8kV circuits are via the six buses of the 6.9kV System. The arrangement of these six 6.9kV buses allows various alignments to both the 138kV and 13.8kV system and the 480V safeguards buses follow these alignments accordingly. Two of the six 6.9kV buses and consequently two of the associated 480V safeguards trains are directly connected to the 138kV offsite circuit, but can also be connected to the 13.8kV offsite circuit via manual transfer.
2. As described above, both units have two of the three available trains of safeguards loads connected directly to the preferred offsite circuit (138kV), via two of the six buses of the 6.9kV System, during normal operation and as such, there is no transfer action involved. Normal operation includes start-up, hot shutdown, cold shutdown, etc. The third train would be auto-transferred to the preferred offsite circuit during a unit trip from power operation (Mode 1) condition. Both plants design basis requires two of three safeguards trains to mitigate a loss of coolant accident.
3. There is no auto-transfer to the alternate 13.8kV offsite circuit from the 138kV circuit. This transfer, when needed, is manually performed at the 6.9kV System voltage level, and controlled by plant operating procedures. The procedures call for the Transmission Owner (TO)

(i.e., ConEd) to be notified whenever the 13.8kV offsite circuit is to be used for plant operating load. This is because the 13.8kV offsite circuit is a local distribution circuit that also powers residential and commercial loads and the TO maintained voltage level is based on the load on the circuit. The higher the load, the higher the voltage that the TO maintains. The 13.8kV offsite circuit is controlled by a TO procedure and based on the load on the circuit, the circuit voltage is set accordingly. The lowest specified voltage permitted on this circuit is 13.4KV. TO notifications (to and from IPEC) are based on this value as well.

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 2 of 26 Roth the I 3RIA/ ~

and the I13.R.A/! cir-uine are m0nfit^Ir by bi Siaiiur- procedures. However only the 138kV offsite circuit is monitored by the On-line AC Contingency Monitoring Program. The 13.8kV offsite circuit is monitored by the TO from its Energy Control Center via a Real-time State Estimator (RTISE) Voltage Profile display. This display provides voltage monitoring and alarming functions and the operations procedure contains the necessary notification responsibilities and notification voltages for both the 138kV and 13.8kV offsite circuits.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 3 of 26 r.MWAT*VMAI Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA and the use of analysis tools by TSOs to assist NPP licensee in monitoring grid conditions to determine the operability of offsite power systems under plant TS.

GDC 17, 10 CFR Part 50, Appendix A, requires that licensees minimize the probability of the loss of power from the transmission network given a loss of the power generated by the nuclear power unit(s).

1. Use of protocols between the NPP licensee and the TSO, ISO, or RC/RA to assist the NPP licensee in monitoring grid conditions to determine the operability of offsite power systems under plant TS.

I(a) Do you have a formal agreement or protocol with your TSO? In the New York Reliability Coordinator Area the New York Independent System Operator (NYISO) has operational authority over the bulk power system. The Transmission Owners (TO) have operational authority over the non-bulk power system. The NYISO operates the bulk power system in accordance with NERC, NPCC and New York State Reliability Council (NYSRC) criteria. Established communications protocols are between the NYISO and the Transmission Owners (TO). Communications to the generating resources are through the TOs. The associated TO monitors the localized grid conditions and coordinates issues such as off site power operability with the NPP. In this document TSO refers to the TO.

Yes, IPEC has a number of formal agreements with the NYISO and TOs (which also performs the TSO function for IPEC as follows:

  • IPEC Unit 3 Interconnection Agreement with the Consolidated Edison Company of New York, Inc.

(Con Ed)

  • IPEC Unit 2 Indian Point Continuing Site Agreement with Consolidated Edison Company of New York, Inc.
  • NYISO Customer & Guest Application Form of Service Agreement for NYISO Market Administration and Control Area Service Tariff
  • Transaction Form between Entergy-IPEC and Con Edison for 138kV and 13.8kV monitoring and notification services The NYISO and TSO agreements require all parties to operate per NYISO and/or TSO procedures and documents, therefore the NYISO and TSO procedures and documents are considered part of the formal agreements.

Compliance with GDC-17, as documented in the IPEC license basis and plant Technical Specifications, is not

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 4 of 26 II *I.

picuicatcu on such an agreemeni.

I (b) Describe any grid conditions that would The TSO is required to notify IPEC as soon as practical per good utility practice whenever an impaired or trigger a notification from the TSO to the potentially degraded grid condition is recognized by the TSO. Specific examples of known potentially NPP licensee and degrading conditions identified in the agreement include:

1. De-energizing, switching or in-service work on critical transmission lines if there is a time period required for the 2. Potentially damaging inclement weather notification 3. Solar Magnetic Disturbances
4. Post-contingency voltage alarm for the 138kV transmission system after 30-minutes.
5. Areal-time 13.8kV degraded voltage condition below a normal system schedule voltage after 30-minutes
6. Prior to any 138kV feeder, which could impact IPEC being removed or restored to service
7. When the TSO 138kV or 13.8kV monitoring and alarm capability are out of service and have not been restored after 30-minutes.
8. Other system or equipment conditions determine by the TSO to be of importance to IPEC.

I (c) Describe any grid conditions that would Grid conditions and status are the primary responsibility of ISO and TSO.

cause the NPP licensee to contact the TSO.

Relative to this question, "grid conditions' is assumed to be IPEC changes that impact the TSO real-time post Describe the procedures associated with such contingency analysis capability. IPEC typically notified ISO and/or TSO for changes in the following grid a communication. If you do not have conditions:

procedures, describe how you assess grid conditions that may cause the NPP licensee to 0 Unit power capability changes contact the TSO. 0 Unit Startup and Shutdown 0 Modifications resulting in changes to generator electrical characteristics S Breaker alignment and offsite voltage verification 0 MVAR Loading 0 Post-trip off-site voltage criteria 0 Changes in IPEC post trip station and accident loading

.0 Loss of preferred 138KV Offsite Power Supply 0 Loss of 13.8KV Offsite Power Supply 0 Status of 13.8kv and 138kv 0 Maintenance activities directly affecting Switchyard components

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 5 of 26 I 5 I a Mvieihod of voitage controi, automatic or manual.

EDG Surveillance Testing 0 Load tap changer position / Auto-Manual Mode I(d) Describe how NPP operators are trained The Licensed Operators at IPEC have had training on site procedure that addresses offsite power continuous and tested on the use of monitoring and notification. This procedure establishes monitoring, and notification responsibilities of the Buchanan Substation, as well as the interface between the IPEC and Con Edison's Energy Control Center. The the procedures or most recent training occurred in Cycle 3 of 2005.

assessing grid conditions in question I (c).

Typically, IPEC operators are trained and tested, using procedures, on the following:

  • System Restoration Typically, IPEC operators are trained, using procedures, on the following:
  • System Restoration e Degraded voltage conditions
  • Voltage (number for inadequate grid capacity)
  • VARs
  • Breaker status
  • Notification of the ISO and/or TSO of changed conditions.

1(e) If you do not have a formal agreement or As previously stated, IPEC does have a formal agreement with the TSO. Prompt notification from the TSO protocol with your TSO, describe why you (after 30-minutes) and a pre-trip analysis of whether the post-trip voltage will be below acceptable values are believe you continue to comply with the included in Indian Point Energy Center Offsite Power Continuous Monitoring And Notification procedure.

provisions of GDC 17 as stated above, or Additionally TSO procedure describes Con Edison responsibility to notify IPEC of low voltage issues as it describe what actions you intend to take to relates to the 138kV and 13.8kV systems. The procedure requires the TSO to notify both IP2 & IP3 Control assure compliance with GDC 17. Rooms after 30-minutes if the real-time analysis tool determines the post IPEC trip voltage would be below the value specified by IPEC. In addition, the TSO will notify IPEC after 30-minutes if the 13.8kV system voltage is below the normal system voltage schedule.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 6 of 26

!.'11 EMM - -sI~l, Comluianut: wit CiiGC-i, kir2 and ii;3 are not a GDU plants, the FSARs describe to what extent 1P2 and IP3 were reviewed to the draft GDCs or its equivalent is not predicated on this agreement).

I(f) If you have an existing formal As previously stated, IPEC does have formal agreements with the TSO. These agreements require the TSO to interconnection agreement or protocol that notify IPEC as soon as practicable per good utility practice, upon receipt of a potential post-trip degraded ensures adequate communication and voltage alarm.

coordination between the NPP licensee and the TSO, describe whether this agreement or protocol requires that you be promptly notified when the conditions of the surrounding grid could result in degraded voltage (i.e., below TS nominal trip setpoint value requirements; including NPP licensees using allowable value in its TSs) or LOOP after a trip of the reactor unit(s).

I(g) Describe the low switchyard voltage These are the Switchyard voltage conditions that will initiate operation of IPEC degraded voltage protection conditions that would initiate operation of i. 138 kv Offsite Power Source <133kv plant degraded voltage protection. ii. 13.8kv Offsite Power Source <13.4kv Note: The design of these systems is described in front of this attachment.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 7 of 26

2. Use of criteria and methodologies to assess whether the offsite power system will become inoperable as a result of a trip of your NPP.

2(a) Does your NPP's TSO use any Yes. The TSO, uses a State Estimator and a Contingency Evaluation Program to analyze analysis tools, an online analytical real time and contingency voltage levels and thermal loading for IPEC 138kV off-site transmission system studies program, or sources.

other equivalent predictive methods to determine the grid conditions that would The 138kV transmission system program and related actions are summarized as follows:

make the NPP offsite power system inoperable during various Real-Time Contingency Analysis Program: The program and related actions are contingencies? summarized as follows; the program utilizes real-time transmission system information If available to you, please provide a brief and nuclear generating unit specific shutdown loads and minimum voltage description of the analysis tool that is requirements. The program creates a model by combining real-time telemetry with used by the TSO. the network model. The network model includes the nuclear power plant facilities.

The State Estimator is then used to provide a consistent power flow that is used to run the contingencies. The contingency case assumes the simultaneous loss of the generator and the addition of load at the appropriate bus. An alarm is issued if the prescribed voltage limits are violated.

The 13.8kV distribution system is monitored on a real-time voltage basis. If the voltage drops below a predetermined 13.8kV system voltage value, IPEC is notified. This approach is determined to be acceptable because the 13.8kV off-site source is a manually aligned supply and the predetermined notification value is at the lower limit of the 13.8kV systems normal voltage schedule. Therefore, the TSO will make all reasonable efforts to maintain the voltage schedule.

2(b) Does your NPP's TSO use an Yes. The TSO uses the real-time analysis tool described in 2(a), in conjunction with analysis tool as the basis for notifying procedures, as the basis for determining when conditions warrant IPEC notification of the the NPP licensee when such a condition 138kV system.

is identified? If not, how does the TSO determine if conditions on the grid As described above the TSO use real-time voltage monitoring, in conjunction with warrant NPP licensee notification? procedures, as basis to determining when conditions warrant IPEC notification of the 13.8kV system.

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043

-- - Page 8 of 26 II yOum J I vJ UQ~Oc am CA am mGl yoia LvuI, l

I 'es. IFI S aIai-Liine ayaiSis ivoi for ihe i35KV, in conjunction witn i-'E; plant load would the analysis tool identify a flow studies, have the capability to determine if the trip of their IPEC plants would result in condition in which a trip of the NPP a switchyard voltage which would actuate the associated unit's degraded voltage would result in switchyard voltages protection logic and initiate separation from the offsite power source.

(immediate and/or long-term) falling below TS nominal trip setpoint value The 13.8kV source is a manually aligned distribution system, which the TSO has local requirements (including NPP licensees resources available to adjust system voltage. Prior to IPEC aligning the 480VAC safety using allowable value in its TSs) and buses to the 13.8 kV system (via the 6.9 kV system), communication between the TSO consequent actuation of plant degraded and IPEC is required to ensure the adequacy of the 13.8 kV system voltage to support voltage protection? accident loads.

If not, discuss how such a condition would be identified on the grid.

2(d) If your TSO uses an analysis tool, The TSO 138kV real-time analysis tool presently resolves the IPEC Unit 2 and IPEC Unit how frequently does the analysis tool 3 trip contingencies every minute for the steady state conditions.

program update?

2(e) Provide details of analysis tool- The 138kV IPEC Unit 2 and IPEC Unit 3 contingencies results (see response to item 2(a))

identified contingency conditions that are automatically compared to off-site post trip voltage limits. If any limit is violated, an would trigger an NPP licensee alarm is generated and IPEC is notified if not cleared after 30 minutes notification from the TSO.

2(f) If an interface agreement exists Yes. IPEC would be notified by the TSO when:

between the TSO and the NPP licensee, does it require that the NPP licensee be

  • When all three 138 kV monitoring and alarm systems are out of service and have notified of periods when the TSO is not been restored within 30 minutes.

unable to determine if offsite power

  • When the 13.8 kV monitoring and alarm systems are out of service and have not voltage and capacity could be been restored within 30 minutes.

inadequate?

Loss of the voltage prediction tool alone has no impact on operability. If notified by the If so, how does the NPP licensee TSO that the Low Voltage Contingency Alarm is inoperable, then the IPEC Operators determine that the offsite power would perform the following:

remain operable when such a 1. Contact the TSO once per shift to verify imminent/expected degraded voltage notification is received? conditions do not exist.

l 2. Minimize large electrical load changes

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 9 of 26 li]Zs1Me g I M5 M-. . M M J. Mtintraize iutaidriance and testing of the electrical distribution system. i

4. Terminate maintenance or testing on critical components of the electrical distribution system as soon as possible.
5. Limit MVAR Output (OP2 only) 2(g) After an unscheduled inadvertent No. Verification of the post trip 138kV switchyard voltage real-time analysis results against trip of the NPP, are the resultant actual post trip voltage is not performed. Since the real-time analysis tool uses real time switchyard voltages verified by system data and assumed worst case station loads a comparison of values would be procedure to be bounded by the difficult even if the real-time analysis predicted values were available which they are not; voltages predicted by the analysis tool?

2(h) If an analysis tool is not available to This question is not applicable to IPEC. The TSO has a real-time analysis tool presently in the NPP licensee's TSO, do you know if use for the 138kV system as discussed above.

there are any plans for the TSO to obtain one? If so, when? The TSO has no plans to install a real-time contingency monitor for the 13.8 kV off-site power source.

2(i) If an analysis tool is not available, Not Applicable for the 138kV transmission lines, TSO uses real-time analysis tool as does your TSO perform periodic studies discussed above.

to verify that adequate offsite power capability, including adequate NPP post- IPEC performs periodic station load flow studies to ensure that the minimum 13.8kV trip switchyard voltages (immediate scheduled voltage is adequate to support voltage requirements.

and/or long-term), will be available to the NPP licensee over the projected timeframe of the study?

(a) Are the key assumptions and parameters of these periodic studies translated into TSO guidance to ensure that the transmission system is operated within the bounds of the analyses?

(b) If the bounds of the analyses are exceeded, does this condition trigger the notification provisions discussed in question 1 above?

[l ______ I ___ ___________

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 we]

S

  • tii.!

I I-. ..

I M*1111 P-r --

AA  ! t! _ e- -

Page IUof26 I.

I - /i\ shoe I WS I OWL LW7, IJI 7LDU UV iivti apPICIavult: I I O0KV arIU 13.0 KV Oystems i

not have access to the results of an analysis tool, or your TSO does not perform and make available to you periodic studies that determine the adequacy of offsite power capability, please describe why you believe you comply with the provisions of GDC 17 as stated above, or describe what compensatory actions you intend to take to ensure that the offsite power system will be sufficiently reliable and remain operable with high probability following a trip of your NPP.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 11 of 26 W~ 0 1'lll 3.Use of criteria and methodologies to-assess whether the NPP's offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.

3(a) If the TSO notifies the NPP IPEC would declare the 138kV off-site source "inoperable". The TSO has real-time operator that monitor capability for the 138kV source and IPEC is notified by the TSO if the loss of the unit would result in an unacceptable off-site post-trip voltage. There are no identified

  • a trip of the NPP, or system conditions where the loss of a transmission line or large supply would result in the
  • the loss of the most critical trip of the generator.

transmission line or

  • the largest supply to the grid would result in switchyard voltages (immediate and/or long-term) below TS nominal trip setpoint value requirements (including NPP licensees using allowable value in its TSs) and would actuate plant degraded voltage protection, is the NPP offsite power system declared inoperable under the plant TSs? If not, why not? 3(b) If onsite safety-related equipment IPEC is not designed for double sequencing events. LOCA with a Delayed LOOP is (e.g., emergency diesel generators or outside the design basis for both IP2 and IP3.

safety-related motors) is lost when subjected to a double sequencing (LOCA with delayed LOOP event) as a result of the anticipated system performance and is incanihie of performing its safety functions as a

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 12 of 26 I _SUIL e'=,

%J;IsV-0JU ju n IVLJ al 1I W IIC!J llcy I". !- in

' M actuation signal during this condition, is the equipment considered inoperable?

If not, why not?

3(c) Describe your evaluation of onsite Indian Point Units 2 and 3 are designed to a GDC that postulates a LOCA concurrent with safety-related equipment to determine a LOOP. Neither plant models a LOCA with Delayed LOOP scenario in its voltage profile whether it will operate as designed and loading analyses, because this event is outside the design basis of both units.

during the condition described in question 3(b).

3(d) If the NPP licensee is notified by This condition is addressed by our site procedures. Under these circumstances we would the TSO of other grid conditions that enter the applicable site procedure for offsite power continuous monitoring and may impair the capability or availability notification, a Technical Specification action statement would not be entered until an of offsite power, are any plant TS action applicable system, structure or component was declared inoperable.

statements entered? If so, please identify them.

3(e) If you believe your plant TSs do not Not applicable.

require you to declare your offsite power Based on responses, we declare offsite power or applicable equipment inoperable under system or safety-related equipment circumstances as described above.

inoperable in any of these circumstances, explain why you believe you comply with the provisions of GDC 17 and your plant TSs, or describe what compensatory actions you intend to take to ensure that the offsite power system and safety-related components will remain operable when switchyard voltages are inadequate.

3(f) Describe if and how NPP operators The Licensed Operators have been trained on the applicable site procedure for offsite are trained and tested on the power continuous monitoring and notification. This procedure contains the requirements compensatory actions mentioned in your for declaring off-site power inoperable and entering the appropriate Technical answers to questions 3(a) through (e). Specifications.

For events such as LOCAs followed later hy a I nap event the Opnnraors confinuing training includes the sequencing or manual loading of safeguards equipment. The

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 13 of 26 le _I! *- II  ; *  ! ! e I

I McUiMe111iiL to IIIrIIudiIy Iad safeguards equipment is contingent on whether or not tile Safeguards signal has been reset. The site's Westinghouse owner's group Emergency Operating Procedures address these situations. The licensed operators are tested on these procedures and in dynamic simulator evaluations, as applicable.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 14of26 WIinISTAJ*WAO

4. Use of criteria and methodologies to assess whether the offsite power system will remain operable following a trip of your NPP.

4(a) Do the NPP operators have any Yes, procedural guidance for abnormal situations related to this equipment is available to guidance or procedures in plant TS IPEC operators in Annunciator Response Procedures.

bases sections, the final safety analysis report, or plant procedures regarding The operators are trained and tested on systems such as the main generator voltage situations in which the condition of plant- regulator and tap changers.

controlled or -monitored equipment (e.g., voltage regulators, auto tap changing transformers, capacitors, static VAR compensators, main generator voltage regulators) can adversely affect the operability of the NPP offsite power system? If so, describe how the operators are trained and tested on the guidance and procedures.

4(b) If your TS bases sections, the final Not applicable.

safety analysis report, and plant procedures do not provide guidance regarding situations in which the condition of plant-controlled or -

monitored equipment can adversely affect the operability of the NPP offsite power system, explain why you believe you comply with the provisions of GDC 17 and the plant TSs, or describe what actions you intend to take to provide such guidance or procedures.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 15 of 26 Use of NPP licensee/TSO protocols and analysis tool by TSOs to assist NPP licensees in monitoring grid conditions for consideration in maintenance risk assessments The Maintenance Rule (10 CFR 50.65(a)(4)) requires that licensees assess and manage the increase in risk that may result from proposed maintenance activities before performing them.

5. Performance of grid reliability evaluations as part of the maintenance risk assessments required by 10 CFR 50.65(a)(4).

5(a) Is a quantitative or qualitative grid Yes reliability evaluation performed at your NPP as part of the maintenance risk IPEC performs qualitative risks assessment as required by 10 CFR 50.65 and IPEC assessment required by 10 CFR Plant Technical Specification. The program is implemented by IPECNPP On-Line Risk 50.65(a)(4) before performing grid-risk- Assessment and Outage Risk Assessment procedures.

sensitive maintenance activities? This These procedures require plant risk assessment before removing equipment from includes surveillances, post-maintenance service for planned maintenance activities, or upon discovery of equipment out of service testing, and preventive and corrective that is unplanned.

maintenance that could increase the probability of a plant trip or LOOP or The IPECNPP On-Line Risk Assessment procedure requires an evaluation of current impact LOOP or SBO coping capability, and anticipated grid conditions before removing risk significant equipment from service.

for example, before taking a risk- The Equipment Out of Service (EOOS) Monitor is a computer based program that is significant piece of equipment (such as used to calculate Core Damage Frequency and conditional Core Damage Frequency for an EDG, a battery, a steam-driven pump, the plant equipment configuration and testing activities for both planned and unplanned an alternate AC power source) configurations.

out-of-service? The IPECNPP Work Management procedure requires a risk plan development for activities that would increase grid instability in combination with external events.

5(b) Is grid status monitored by some Yes means for the duration of the grid-risk-sensitive maintenance to confirm the continued validity of the risk assessment and is risk reassessed when warranted?

If not, how is the risk assessed during

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 16 of 26 WE .  !!S**!i. -- " -

I -;- J _., -s - -- &.._ __:- -- - - - n H41 u1-1f-0 ;>1o 10LV ;> tic 1 fl 1 lsL Fa1 1VV

-I.

5(c) Is there a significant variation in the Yes stress on the grid in the vicinity of your The NYISO Reliability Coordination Area is a summer peaking area. Due to high intra NPP site caused by area and inter area power flows, it would be expected that the grid would be stressed.

However, this stress is managed through facility maintenance coordination. During the seasonal loads summer peak season scheduled transmission facility maintenance is avoided in June, July and August if possible.

or Anytime that maintenance is scheduled, the schedules are managed in order to maintain maintenance activities associated with operation of the bulk power system within established operating criteria.

critical transmission elements?

Is there a seasonal variation (or the No, based on the limited number of LOOP occurrences in the NYISO region over the potential for a seasonal variation) in the past 10 years, no seasonal variation can be established. IPEC last experienced a LOOP frequency in the local transmission transmission system related LOOP on August 14, 2003.

region?

If the answer to either question is yes, discuss the time of year when the variations occur and their magnitude.

5(d) Are known time-related variations in No. However, Con Edison the TSO by procedure does not schedule feeder outages the probability of a LOOP at your plant between May 1 and September 15 due to summer loading concerns. IPEC will not site considered in the grid-risk-sensitive schedule maintenance activities during this time. IPEC will schedule emergent activities maintenance evaluation? If not, what is to address issues that could pose a threat to grid stability.

your basis for not considering them?

5(e) Do you have contacts with the TSO Yes.

to determine current and anticipated grid conditions as part of the grid reliability TSO Communication contacts are available for assessment of grid conditions before and evaluation performed before conducting during the performance of grid-risk sensitive maintenance activities.

grid-risk-sensitive maintenance activities?

5(f) Describe any formal agreement or Site level procedures provide the guidance on scheduling. The procedure for protocol that you have with your TSO to performance of the offsite power continuous monitoring and notification contains assure that you are promptly alerted to a jguidelines for risk management of feeder outages. This would include the ability to

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 IMMUNE~)Page 17 of26 us., -S. -I l...- - -n -__

VV'jIQVI III

_-. A__L A __, ,

UalIU .,UIIUILIuII tIaL IdL t II y

CIIyI l

restiict wor'Korku feoeers iquriiiiit oi q deum o U WIairitefrince on grid equipment. Tne Hiant during a maintenance activity. models grid feeder outage in the risk assessment Program EOOS.

Notification occurs whether or not maintenance is on-going. The TSO is required to notify IPEC whenever an impaired or potentially degraded grid condition is recognized by the TSO. Specific examples of known potentially degrading conditions identified in the agreement include:

1. De-energizing, switching or in-service work on critical transmission lines.
2. Potentially damaging inclement weather.
3. Solar Magnetic Disturbances.
4. Post-contingency voltage alarm for the 138kV transmission system after 30-minutes.
5. A real-time 13.8kV degraded voltage condition below a normal system schedule voltage after 30-minutes.
6. Prior to any 138kV feeder outage which could impact IPEC being removed or restored to service
7. When the TSO 138kV or 13.8kV monitoring and alarm capability are out of service and have not been restored after 30-minutes.
8. Other system or equipment conditions determine by the TSO to be of importance to IPEC.

5(g) Do you contact your TSO periodically Yes.

for the duration of the grid-risk-sensitive Additionally the TSO is contacted before the start of grid- risk sensitive maintenance maintenance activities? activities and at the completion of the activity. Changes to grid conditions are communicated to IPEC as stated in 5(f).

5(h) If you have a formal agreement or The formal agreement with the System Operator at IPEC is described in the offsite protocol with your TSO, describe how power continuous monitoring and notification station procedure. This procedure NPP operators and maintenance establishes monitoring, and notification responsibilities of the Buchanan Substation, as personnel are trained and tested on this well as the interface between the IPEC and Con Edison's Energy Control Center. The formal agreement or protocol. Licensed Operators have had training on this procedure. The most recent training occurred in Cycle 3 of 2005.

____There was no testing associated with this training.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 18 of 26 56.6 0~ M- I Maintenance personnel do not have training on this agreement or procedure because Operations and Work Control assess the risk and conditions for performing maintenance activities.

5(i) If your grid reliability evaluation, Not applicable.

performed as part of the maintenance risk assessment required by 10 CFR 50.65(a)(4), does not consider or rely on some arrangement for communication with the TSO, explain why you believe you comply with 10 CFR 50.65(a)(4).

50) If risk is not assessed (when Not applicable warranted) based on continuing communication with the TSO throughout the duration of grid-risk-sensitive maintenance activities, explain why you believe you have effectively implemented the relevant provisions of the endorsed industry guidance associated with the maintenance rule.

5(k) With respect to questions 5(i) and Not applicable. No alternative actions required.

50), you may, as an alternative, describe what actions you intend to take to ensure that the increase in risk that may result from proposed grid-risk-sensitive activities is assessed before and during grid-risk-sensitive maintenance activities, respectively.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 19of26

6. - Use of risk assessment results, including the results of grid reliability evaluations, in managing maintenance risk, as required by 10 CFR 50.65(a)(4). -- - .

TSO does grid reliability evaluations; not NPPs. ugrid reliability evaluations" Enter AP, if notified un-normality on grid.

6(a) Does the TSO coordinate Yes.

transmission system maintenance The TSO coordinates all scheduled work activities with the plant. The Process is activities that can have an impact on the described in site level procedures.

NPP operation with the NPP operator?

6(b) Do you coordinate NPP Yes.

maintenance activities that can have an IPEC coordinates all scheduled work activities with the TSO. The plant process is impact on the transmission system with described in site procedures.

the TSO?

6(c) Do you consider and implement, if Yes.

warranted, the rescheduling of grid-risk- IPEC will reschedule activities as required to prevent challenging the stability of the local sensitive maintenance activities Grid. This would include activities which would likely cause plant trip or loss of off site (activities that could (i) increase the power. Guidance is described in site procedures. If the Grid voltage degrades to a point likelihood of a plant trip, (ii) increase where it challenges the NPP, the TSO will immediately correct it or notify the IPEC Control LOOP probability, or (iii) reduce LOOP room operators. IF emergent equipment outage occurs the TSO will notify the control or SBO coping capability) under room. The Switchyard coordinator or lead system engineer will be notified. A risk existing, imminent, or worsening assessment evaluation will be performed and if applicable, restrict feeders as required.

degraded grid reliability conditions?

6(d) If there is an overriding need to Yes.

perform grid-risk-sensitive maintenance Guidance is described in site procedures. The Switchyard coordinator or lead system activities under existing or imminent engineer will be notified. A risk assessment evaluation will be performed and if applicable conditions of degraded grid reliability, or restrict feeders as required.

continue grid-risk-sensitive maintenance when grid conditions worsen, do you Additionally, mitigative actions such as feeder restrictions and protected equipment will be implement appropriate risk management implemented.

actions? If so; describe the actinnq that you would take. (These actions could l

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 20 of 26 f.

Include adteai-iel I quipi mer it pi vzuttutI I

.! --. -i: Iss and compensatory measures to limit or minimize risk.)

6(e) Describe the actions associated Emergent maintenance or declining grid condition guidance is described in site with questions 6(a) through 6(d) above procedures. The operator will perform appropriate actions as required by Technical that would be taken, state whether each Specifications. The Switchyard Coordinator or Lead System Engineer will be notified.

action is governed by documented They will perform a risk evaluation and if applicable restrict feeders as required. The procedures and identify the procedures, feeder or equipment outage will be run through the plant risk program. These actions are and explain why these actions are required by Procedure and must be performed.

effective and will be consistently accomplished.

6(f) De scribe how NPP operators and The Licensed Operators and Work Control Personnel at IPEC were provided training on maintenance personnel are trained and the applicable procedure that addresses Offsite Power Continuous Monitoring and tested to assure they can accomplish Notification. This procedure establishes monitoring, and notification responsibilities of the the actions described in your answers to Buchanan Substation, as well as the interface between the IPEC and Con Edison's question 6(e). Energy Control Center. The most recent training occurred in Cycle 3 of 2005.

There was no testing associated with this training.

6(g) If there is no effective coordination Not applicable between the NPP operator and the TSO regarding transmission system maintenance or NPP maintenance activities, please explain why you believe you comply with the provisions of 10 CFR 50.65(a)(4).

6(h) If you do not consider and Not applicable effectively implement appropriate risk management actions during the conditions described above, explain why you believe you effectively addressed the relevant provisions of the associated NRC-endorsed industry guidance.

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 21 of 26 I us s£ I -P i;,: -l, V(i) You miiay, as an aiternailve LO Not appilcaDie. No alternative actions required.

questions 6(g) and 6(h) describe what actions you intend to take to ensure that the increase in risk that may result from grid-risk-sensitive maintenance activities is managed in accordance with 10 CFR 50.65(a)(4).

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 22 of 26 I .. Ue U -

Offsite power restoration procedures in accordance with 10 CFR 50.63 as developed in Section 2 of RG 1.155 Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.

7.-Pibcedures for identifying local power sources' that could be made available to resupply your plant following a LOOP event.

Note: Section 2, 'Offsite Power," of RG 1.155 (ADAMS Accession No. ML003740034) states:

Procedures should include the actions necessary to restore offsite power and use nearby power sources when offsite power is unavailable. As a minimum, the following potential causes for loss of offsite power should be considered:

- Grid under-voltage and collapse

- Weather-induced power loss

- Preferred power distribution system faults that could result in the loss of normal power to essential switchgear buses 7(a) Briefly describe any agreement IPEC has no agreement with local power sources. The NYISO and the TSO have made with the TSO to identify local restoration plans which identify how power will be restored to the NPPs as a priority load.

power sources that could be made The TSO is responsible for coordinating the restoration of off-site power to the NPP. The available to re-supply power to your NPP is considered a critical facility and restoration of power is a priority.

plant following a LOOP event.

4 7(b) Are your NPP operators trained and Yes.

tested on identifying and using local Continuing Licensed Operator Re-qualification Training includes electrical bus and power power sources to resupply your plant supply training. Also included is training on applicable Abnormal Operating procedures, following a LOOP event? If so, describe which address re-energizing plant electrical systems following a LOOP.

how.

I This includes items such as nearby or onsite gas turbine generators, portable generators, hydro generators, and black-smttZOI

  • I..MIJVwII EVICTSILO.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 23 of 26 g!le t.

7(c) if you nave not established an  !

.- MIa Not appiicabie.

I agreement with your plant's TSO to identify local power sources that could The NYISO has agreements with area black-start capable units in accordance with NYISO be made available to resupply power to bulk power restoration plan. The NYISO restoration plan identifies restoring power to the your plant following a LOOP event, NPPs as a priority, and the TSO is responsible for coordinating the restoration of off-site explain why you believe you comply with power to the NPP. The NPP is considered a critical facility and restoration of power is a the provisions of 10 CFR 50.63, or priority.

describe what actions you intend to take to establish compliance.

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 24 of 26 Losses of offsite power caused by grid failures at a frequency of equal to or greater than once in 20 site-years in accordance with Table 4 of Regulatory Guide 1.155 for complying with 10 CFR 50.63 Pursuant to 10 CFR 50.63, the NRC requires that each NPP licensed to operate be able to withstand an SBO for a specified duration and recover from the SBO. NRC RG 1.155 gives licensees guidance on developing their approaches for complying with 10 CFR 50.63.

8. Maintaining SBO coping capabilities in accordance with 10 CFR 50.63.

8(a) Has your NPP experienced a total Yes, a LOOP caused by grid failure occurred during August 2003.

LOOP caused by grid failure since the plant's coping duration was initially determined under 10 CFR 50.63?

8(b) If so, have you reevaluated the No. See additional information in the response to Question 8(d) below.

NPP using the guidance in Table 4 of RG 1.155 to determine if your NPP should be assigned to the P3 offsite power design characteristic group?

8(c) If so, what were the results of this Both Units 2 and 3 remain 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> coping plants.

reevaluation, and did the initially determined coping duration for the NPP need to be adjusted?

8(d) If your NPP has experienced a total Per RG 1.155 Table 4, Sites that expect to experience a total loss of offsite power caused LOOP caused by grid failure since the by grid failures at a frequency equal to or greater than 20 site-years are considered to be plant's coping duration was initially an Offsite Power Design Characteristic Group 'P3", unless the site has a procedure to determined under 10 CFR 50.63 and recover AC power from reliable alternate (non-emergency) AC power sources within has not been reevaluated using the approximately one-half hour following a grid failure are considered.

guidance in Table 4 of RG 1.155, explain why you believe you comply with Both IP2 and IP3 are already considered as Offsite Power Design Characteristic UP3" with the provisions of 10 CFR 50.63 as 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> coping duration. This classification already accounts for a frequency of grid related stated above, or describe what actions loss of offsite power events greater than once per 20 years. Therefore, no reevaluation of you intend to take to ensure that the coping time for either plant is required as a result of a LOOP subsequent to existing NPP maintains its SBO coping evaluations.

capabilities in accordance with 10 CFR l_l

Attachment I Docket Nos. 50-247 and 50-286 NL-06-043 Page 25 of 26 geM -_: ro -S _ _.

The IP-RTP-04-00811 Station Blackout Report (Tenera Report), dated March 1990 documents IP2 as Offsite Power Design Characteristic 'P3" with an 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> coping duration. This is based on past loss of offsite experience at the site, the probabilities of severe weather, and the independence of offsite power supplies. The factor used for determining coping duration is the high EDG reliability. A target reliability of 0.95 gives IP2 a coping duration category of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

Indian Point Unit 3 NRC Letter Docket No 50-286, dated June 9, 1992 Supplemental Safety Evaluation (SSE)

Station Blackout Rule 10 CFR 50.63 states IP3 is an Offsite Power Design Characteristic

'P3" with a minimum required coping duration of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

Attachment 1 Docket Nos. 50-247 and 50-286 NL-06-043 Page 26 of 26 Actions to ensure compliance 9: If y-ou-determine th-at any-actio-n is-warranted to bring your NPP into compliance with NRC regulatory requirements, including TSs, GDC 17, 10 CFR 50.65(a)(4), 10 CFR 50.63, 10 CFR 55.59 or 10 CFR 50.120, describe the schedule for implementing it.

Areas of non-compliance were entered in the Corrective Action Process and will drive the actions necessary to implement changes to bring the condition into compliance and will include a detailed schedule.

CR-IP2-2006-01450 was initiated to change operations procedure to give the Operators direct guidance that when notified by the TO of the Real-time Contingency Analysis (RTCA) alarm, the Offsite Power Supply will be Inoperable and TS actions will be entered. Additionally, the 133kV criteria will be deleted from the procedure.