| number = ML17233A106
| number = ML17233A106
| issue date = 09/22/2017
| issue date = 09/22/2017
| title = Amendment - Vegp Unit 4 LAR 17-004
| title = Amendment - VEGP Unit 4 LAR 17-004
| author name = Hoellman J
| author name = Hoellman J
| author affiliation = NRC/NRO/DNRL/LB4
| author affiliation = NRC/NRO/DNRL/LB4
| addressee name = Whitley B H
| addressee name = Whitley B
| addressee affiliation = City of Dalton, GA, Georgia Power Co, MEAG Power, Oglethorpe Power Corp, Southern Nuclear Operating Co, Inc
| addressee affiliation = City of Dalton, GA, Georgia Power Co, MEAG Power, Oglethorpe Power Corp, Southern Nuclear Operating Co, Inc
| docket = 05200025, 05200026
| docket = 05200025, 05200026
Line 19: Line 19:


=Text=
=Text=
{{#Wiki_filter: SOUTHERN NUCLEAR OPERATING COMPANY, INC. GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MEAG POWER SPVM, LLC MEAG POWER SPVJ, LLC MEAG POWER SPVP, LLC CITY OF DALTON, GEORGIA   VOGTLE ELECTRIC GENERATING PLANT, UNIT 4 DOCKET NO. 52-026 AMENDMENT TO FACILITY COMBINED LICENSE   Amendment No. 86 License No. NPF-92 1. The Nuclear Regulatory Commission (the Commission) has found that:
{{#Wiki_filter:SOUTHERN NUCLEAR OPERATING COMPANY, INC.
A. The application for amendment by Southern Nuclear Operating Company (licensee), dated February 24, 2017, as supplemented by letter dated August 7, 2017, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; B. The facility will be constructed and will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations, and all applicable requirements have been satisfied.
GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MEAG POWER SPVM, LLC MEAG POWER SPVJ, LLC MEAG POWER SPVP, LLC CITY OF DALTON, GEORGIA VOGTLE ELECTRIC GENERATING PLANT, UNIT 4 DOCKET NO. 52-026 AMENDMENT TO FACILITY COMBINED LICENSE Amendment No. 86 License No. NPF-92
2 2. Accordingly, the license is amended to authorize changes to the Updated Final Safety Analysis Report (UFSAR) as described in the licensee's application dated February 24, 2017, as supplemented by letter dated August 7, 2017. The license is also amended by changes to Appendix A, Technical Specifications, and Appendix C of the Facility Combined License as indicated in the attachment to this license amendment. Paragraph 2.D(8) of Facility Combined License No. NPF-92 is hereby amended to read as follows:
: 1. The Nuclear Regulatory Commission (the Commission) has found that:
  (8) Incorporation The Technical Specifications, Environmental Protection Plan, and ITAAC in Appendices A, B, and C, respectively of this license, as revised through Amendment No. 86, are hereby incorporated into this license.
A. The application for amendment by Southern Nuclear Operating Company (licensee), dated February 24, 2017, as supplemented by letter dated August 7, 2017, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; B. The facility will be constructed and will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations, and all applicable requirements have been satisfied.
: 3. This license amendment is effective as of the date of its issuance and shall be implemented within 30 days of the date of issuance. The licensee shall submit the changes authorized by this amendment with the next update of the UFSAR in accordance with 10 CFR 50.71(e). FOR THE NUCLEAR REGULATORY COMMISSION: /RA/   Jennifer Dixon-Herrity, Chief Licensing Branch 4 Division of New Reactor Licensing Office of New Reactors Date of Issuance: September 22, 2017  
 
2
: 2. Accordingly, the license is amended to authorize changes to the Updated Final Safety Analysis Report (UFSAR) as described in the licensees application dated February 24, 2017, as supplemented by letter dated August 7, 2017. The license is also amended by changes to Appendix A, Technical Specifications, and Appendix C of the Facility Combined License as indicated in the attachment to this license amendment. Paragraph 2.D(8) of Facility Combined License No. NPF-92 is hereby amended to read as follows:
(8) Incorporation The Technical Specifications, Environmental Protection Plan, and ITAAC in Appendices A, B, and C, respectively of this license, as revised through Amendment No. 86, are hereby incorporated into this license.
: 3. This license amendment is effective as of the date of its issuance and shall be implemented within 30 days of the date of issuance. The licensee shall submit the changes authorized by this amendment with the next update of the UFSAR in accordance with 10 CFR 50.71(e).
FOR THE NUCLEAR REGULATORY COMMISSION:
                                              /RA/
Jennifer Dixon-Herrity, Chief Licensing Branch 4 Division of New Reactor Licensing Office of New Reactors Date of Issuance: September 22, 2017


==Attachment:==
==Attachment:==
Page 7 of the Facility Combined License and affected pages of Appendix A and Appendix C to the Facility Combined License


}}
Page 7 of the Facility Combined License and affected pages of Appendix A and Appendix C to the Facility Combined License}}

Latest revision as of 19:03, 8 March 2020

Amendment - VEGP Unit 4 LAR 17-004
ML17233A106
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 09/22/2017
From: Jordan Hoellman
NRC/NRO/DNRL/LB4
To: Whitley B
City of Dalton, GA, Georgia Power Co, MEAG Power, Oglethorpe Power Corp, Southern Nuclear Operating Co
HOELLMAN J/415-5481
Shared Package
ML17233A104 List:
References
CAC RP9612, LAR 17-004
Download: ML17233A106 (2)


Text

SOUTHERN NUCLEAR OPERATING COMPANY, INC.

GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MEAG POWER SPVM, LLC MEAG POWER SPVJ, LLC MEAG POWER SPVP, LLC CITY OF DALTON, GEORGIA VOGTLE ELECTRIC GENERATING PLANT, UNIT 4 DOCKET NO.52-026 AMENDMENT TO FACILITY COMBINED LICENSE Amendment No. 86 License No. NPF-92

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment by Southern Nuclear Operating Company (licensee), dated February 24, 2017, as supplemented by letter dated August 7, 2017, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; B. The facility will be constructed and will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations, and all applicable requirements have been satisfied.

2

2. Accordingly, the license is amended to authorize changes to the Updated Final Safety Analysis Report (UFSAR) as described in the licensees application dated February 24, 2017, as supplemented by letter dated August 7, 2017. The license is also amended by changes to Appendix A, Technical Specifications, and Appendix C of the Facility Combined License as indicated in the attachment to this license amendment. Paragraph 2.D(8) of Facility Combined License No. NPF-92 is hereby amended to read as follows:

(8) Incorporation The Technical Specifications, Environmental Protection Plan, and ITAAC in Appendices A, B, and C, respectively of this license, as revised through Amendment No. 86, are hereby incorporated into this license.

3. This license amendment is effective as of the date of its issuance and shall be implemented within 30 days of the date of issuance. The licensee shall submit the changes authorized by this amendment with the next update of the UFSAR in accordance with 10 CFR 50.71(e).

FOR THE NUCLEAR REGULATORY COMMISSION:

/RA/

Jennifer Dixon-Herrity, Chief Licensing Branch 4 Division of New Reactor Licensing Office of New Reactors Date of Issuance: September 22, 2017

Attachment:

Page 7 of the Facility Combined License and affected pages of Appendix A and Appendix C to the Facility Combined License