(One intermediate revision by the same user not shown) |
Line 19: |
Line 19: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs, Region I 2100 Renaissance Blvd., King of Prussia, Pa. 19406 E-mail: opa1@nrc.gov Site: www.nrc.gov Blog: http://public-blog.nrc-gateway.gov No. I-12-025 May 17, 2012 Contact: Diane Screnci, (610) 337-5330 Email: opa1.resource@nrc.gov Neil Sheehan, (610) 337-5331 NRC ISSUES CONFIRMATORY ACTION LETTER ON COMMITMENTS TO ADDRESS SEABROOK NUCLEAR PLANT CONCRETE DEGRADATION The Nuclear Regulatory Commission staff has issued a Confirmatory Action Letter (CAL) to NextEra Energy Seabrook, LLC, confirming regulatory commitments made by the company to address concrete degradation at the Seabrook nuclear power plant. NextEra owns the plant, which is located in Seabrook, N.H. | | {{#Wiki_filter:NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs, Region I 2100 Renaissance Blvd., King of Prussia, Pa. 19406 E-mail: opa1@nrc.gov Site: www.nrc.gov Blog: http://public-blog.nrc-gateway.gov No. I-12-025 May 17, 2012 |
| | |
| | ==Contact:== |
| | Diane Screnci, (610) 337-5330 Email: opa1.resource@nrc.gov Neil Sheehan, (610) 337-5331 NRC ISSUES CONFIRMATORY ACTION LETTER ON COMMITMENTS TO ADDRESS SEABROOK NUCLEAR PLANT CONCRETE DEGRADATION The Nuclear Regulatory Commission staff has issued a Confirmatory Action Letter (CAL) to NextEra Energy Seabrook, LLC, confirming regulatory commitments made by the company to address concrete degradation at the Seabrook nuclear power plant. NextEra owns the plant, which is located in Seabrook, N.H. |
| In the license renewal application for the Seabrook plant, NextEra identified concrete degradation at the facility in the form of alkali silica reaction, or ASR. A gel resulting from ASR can expand and cause micro-cracks in the concrete. At Seabrook, certain below-grade concrete structures have experienced groundwater infiltration, which in turn has induced ASR. | | In the license renewal application for the Seabrook plant, NextEra identified concrete degradation at the facility in the form of alkali silica reaction, or ASR. A gel resulting from ASR can expand and cause micro-cracks in the concrete. At Seabrook, certain below-grade concrete structures have experienced groundwater infiltration, which in turn has induced ASR. |
| Based on its review to date, the NRC has determined the affected structures remain capable of performing their safety-related functions. However, in a letter sent to the company, the agency states that the information is needed to enable the NRC staff to ensure that adequate corrective actions are being taken to address the condition. The company is required to provide the NRC with a written response if it does not think it will be able to fulfill the regulatory commitments by the dates specified, and if the company proposes to change any of the commitments. | | Based on its review to date, the NRC has determined the affected structures remain capable of performing their safety-related functions. However, in a letter sent to the company, the agency states that the information is needed to enable the NRC staff to ensure that adequate corrective actions are being taken to address the condition. The company is required to provide the NRC with a written response if it does not think it will be able to fulfill the regulatory commitments by the dates specified, and if the company proposes to change any of the commitments. |
Line 28: |
Line 31: |
| A copy of the CAL will be available in the NRCs electronic documents system at: | | A copy of the CAL will be available in the NRCs electronic documents system at: |
| http://adams.nrc.gov/wba. | | http://adams.nrc.gov/wba. |
| ###
| |
| News releases are available through a free listserv subscription or by clicking on the EMAIL UPDATES link on the NRC homepage (www.nrc.gov). E-mail notifications are sent to subscribers when news releases are posted to NRC's website. For the latest news, follow the NRC on www.twitter.com/NRCgov.}} | | News releases are available through a free listserv subscription or by clicking on the EMAIL UPDATES link on the NRC homepage (www.nrc.gov). E-mail notifications are sent to subscribers when news releases are posted to NRC's website. For the latest news, follow the NRC on www.twitter.com/NRCgov.}} |
Latest revision as of 16:13, 6 February 2020
|
---|
Category:Press Release
MONTHYEARML23166A0212023-03-10010 March 2023 News Release-I-23-002: NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant 2022 Performance ML22346A0552022-11-23023 November 2022 News Release-I-22-016: NRC Schedules Decommissioning Webinar for Nuclear Power Plant Emergency Preparedness and Security Requirements ML22346A0562022-11-21021 November 2022 News Release-I-22-015: NRC Names New Resident Inspector at Salem Nuclear Power Plant ML22346A0572022-11-10010 November 2022 News Release-I-22-014: West Virginia Hospital to Take Corrective Actions Under Settlement Agreement with NRC ML22305A5512022-10-14014 October 2022 News Release-I-22-013: NRC Imposes Civil Penalty to Pennsylvania Company ML22270A0832022-09-14014 September 2022 News Release-I-22-012: NRC Names New Resident Inspector at Peach Bottom Nuclear Power Plant ML22255A0872022-09-0909 September 2022 News Release-I-22-011: NRC to Conduct Pre-Decisional Enforcement Conference with a Connecticut Medical Facility ML22217A0572022-08-0505 August 2022 News Release-I-22-010: New NRC Senior Resident Inspector Assigned to Calvert Cliffs Nuclear Power Plant ML22215A2132022-07-28028 July 2022 News Release-I-22-009: NRC Names New Resident Inspector at Ginna Nuclear Power Plant Press Release-I-22-008, NRC Names New Resident Inspector at Limerick Nuclear Power Plant2022-06-22022 June 2022 Press Release-I-22-008: NRC Names New Resident Inspector at Limerick Nuclear Power Plant ML22153A1262022-05-26026 May 2022 News Release-I-22-007: NRC Schedules Webinar to Discuss 2021 Safety Performance at Maryland, New Jersey, New York, Pennsylvania Nuclear Power Plants ML22131A1432022-05-0606 May 2022 News Release-I-22-006: NRC to Hold Public Meeting to Discuss Seabrook Station 2021 Safety Performance ML22131A1422022-05-0202 May 2022 News Release-I-22-005: NRC Proposes $3,500 Defense Health Agency Fine for Loss of Medical Purpose Radioactive Material ML22083A0522022-03-18018 March 2022 News Release-I-22-004: NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant 2021 Performance ML22063A4642022-03-0202 March 2022 News Release-I-22-003: NRC Proposes $25,600 Fine for Pennsylvania Company ML22028A0502022-01-26026 January 2022 News Release-I-22-002: NRC Issues Confirmatory Order, $50,000 Civil Penalty to HDI Over Security-Related Violations at Oyster Creek Nuclear Power Plant Press Release-I-22-001, NRC Names New Senior Resident Inspector at Salem Nuclear Power Plant2022-01-10010 January 2022 Press Release-I-22-001: NRC Names New Senior Resident Inspector at Salem Nuclear Power Plant Press Release-I-21-010, NRC Proposes $150,000 Civil Penalty for Violations at New Jersey Nuclear Power Plant Undergoing Decommissioning2021-12-22022 December 2021 Press Release-I-21-010: NRC Proposes $150,000 Civil Penalty for Violations at New Jersey Nuclear Power Plant Undergoing Decommissioning Press Release-I-21-009, NRC Issues Confirmatory Action Letter to West Virginia Hospital2021-11-19019 November 2021 Press Release-I-21-009: NRC Issues Confirmatory Action Letter to West Virginia Hospital Press Release-I-21-007, NRC to Hold Public Meeting to Receive Comments on Indian Point Nuclear Power Plant Decommissioning Activities Report2021-07-19019 July 2021 Press Release-I-21-007: NRC to Hold Public Meeting to Receive Comments on Indian Point Nuclear Power Plant Decommissioning Activities Report Press Release-I-21-006, NRC Proposes $3,750 Fine for Connecticut Hospital Violations2021-06-0202 June 2021 Press Release-I-21-006: NRC Proposes $3,750 Fine for Connecticut Hospital Violations Press Release-I-21-005, NRC Schedules Webinar to Discuss 2020 Safety Performance at Maryland, New Jersey, New York and Pennsylvania Nuclear Power Plants2021-06-0101 June 2021 Press Release-I-21-005: NRC Schedules Webinar to Discuss 2020 Safety Performance at Maryland, New Jersey, New York and Pennsylvania Nuclear Power Plants Press Release-I-21-004, NRC to Hold Virtual Meeting to Discuss 2020 Performance of Seabrook Nuclear Power Plant2021-05-24024 May 2021 Press Release-I-21-004: NRC to Hold Virtual Meeting to Discuss 2020 Performance of Seabrook Nuclear Power Plant Press Release-I-21-003, NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant Performance2021-03-11011 March 2021 Press Release-I-21-003: NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant Performance Press Release-I-21-002, NRC Names New Senior Resident Inspector at Indian Point Unit 3 Nuclear Power Plant2021-02-17017 February 2021 Press Release-I-21-002: NRC Names New Senior Resident Inspector at Indian Point Unit 3 Nuclear Power Plant Press Release-I-21-001, NRC Proposes $8,500 Civil Penalty to Puerto Rico Firm for Apparent Violation Involving Nuclear Gauges2021-01-14014 January 2021 Press Release-I-21-001: NRC Proposes $8,500 Civil Penalty to Puerto Rico Firm for Apparent Violation Involving Nuclear Gauges Press Release-I-21-011, NRC Names New Resident Inspector for Nine Mile Point Nuclear Plant2020-12-28028 December 2020 Press Release-I-21-011: NRC Names New Resident Inspector for Nine Mile Point Nuclear Plant Press Release-I-20-023, NRC Names New Resident Inspector at Millstone Station2020-12-0707 December 2020 Press Release-I-20-023: NRC Names New Resident Inspector at Millstone Station Press Release-I-20-022, NRC Resident Inspector Newly Assigned to Calvert Cliffs Nuclear Power Plant2020-11-12012 November 2020 Press Release-I-20-022: NRC Resident Inspector Newly Assigned to Calvert Cliffs Nuclear Power Plant Press Release-I-20-021, NRC Names New Senior Resident Inspector at Seabrook Station2020-10-20020 October 2020 Press Release-I-20-021: NRC Names New Senior Resident Inspector at Seabrook Station Press Release-I-20-020, NRC Names New Resident Inspector at Beaver Valley Nuclear Power Plant2020-10-14014 October 2020 Press Release-I-20-020: NRC Names New Resident Inspector at Beaver Valley Nuclear Power Plant Press Release-I-20-019, NRC Names New Senior Resident Inspector at Susquehanna Nuclear Power Plant2020-09-28028 September 2020 Press Release-I-20-019: NRC Names New Senior Resident Inspector at Susquehanna Nuclear Power Plant Press Release-I-20-018, NRC to Hold Virtual Meeting to Discuss 2019 Performance of Indian Point Nuclear Power Plant2020-09-0101 September 2020 Press Release-I-20-018: NRC to Hold Virtual Meeting to Discuss 2019 Performance of Indian Point Nuclear Power Plant Press Release-I-20-017, NRC Names New Senior Resident Inspector at Beaver Valley Nuclear Power Plant2020-08-18018 August 2020 Press Release-I-20-017: NRC Names New Senior Resident Inspector at Beaver Valley Nuclear Power Plant Press Release-I-20-016, New NRC Senior Resident Inspector Assigned to Hope Creek Nuclear Power Plant2020-07-0909 July 2020 Press Release-I-20-016: New NRC Senior Resident Inspector Assigned to Hope Creek Nuclear Power Plant Press Release-I-20-015, NRC Senior Resident Inspector Newly Assigned to Limerick Nuclear Power Plant2020-07-0606 July 2020 Press Release-I-20-015: NRC Senior Resident Inspector Newly Assigned to Limerick Nuclear Power Plant Press Release-I-20-014, NRC Proposes $7,500 Fine to Puerto Rico Firm for Apparent Violation Involving Nuclear Gauges2020-06-25025 June 2020 Press Release-I-20-014: NRC Proposes $7,500 Fine to Puerto Rico Firm for Apparent Violation Involving Nuclear Gauges Press Release-I-20-013, NRC Names Resident Inspector at FitzPatrick Nuclear Power Plant2020-06-24024 June 2020 Press Release-I-20-013: NRC Names Resident Inspector at FitzPatrick Nuclear Power Plant Press Release-I-20-012, NRC to Hold Virtual Meeting to Discuss 2019 Performance of FitzPatrick, Nine Mile Point and Ginna Nuclear Power Plants2020-06-15015 June 2020 Press Release-I-20-012: NRC to Hold Virtual Meeting to Discuss 2019 Performance of FitzPatrick, Nine Mile Point and Ginna Nuclear Power Plants Press Release-I-20-011, NRC Names New Senior Resident Inspector at Indian Point Nuclear Power Plant2020-06-0505 June 2020 Press Release-I-20-011: NRC Names New Senior Resident Inspector at Indian Point Nuclear Power Plant Press Release-I-20-010, NRC Names New Resident Inspector at Hope Creek Nuclear Power Plant2020-06-0404 June 2020 Press Release-I-20-010: NRC Names New Resident Inspector at Hope Creek Nuclear Power Plant ML20149K5522020-05-28028 May 2020 Press Release I-20-009: NRC Names New Senior Resident Inspector at Peach Bottom Nuclear Power Plant Press Release-I-20-008, NRC Schedules Webinar to Discuss 2019 Safety Performance at Pennsylvania and Maryland Nuclear Power Plants2020-05-27027 May 2020 Press Release-I-20-008: NRC Schedules Webinar to Discuss 2019 Safety Performance at Pennsylvania and Maryland Nuclear Power Plants Press Release-I-20-007, NRC to Hold Virtual Meeting to Discuss 2019 Performance of Salem and Hope Creek Nuclear Power Plants2020-05-21021 May 2020 Press Release-I-20-007: NRC to Hold Virtual Meeting to Discuss 2019 Performance of Salem and Hope Creek Nuclear Power Plants Press Release-I-20-006, NRC to Hold Virtual Meeting to Discuss 2019 Performance of Seabrook Nuclear Power Plant2020-05-20020 May 2020 Press Release-I-20-006: NRC to Hold Virtual Meeting to Discuss 2019 Performance of Seabrook Nuclear Power Plant Press Release-I-20-005, NRC Proposes $7,500 Fine for West Virginia Engineering Firm2020-04-27027 April 2020 Press Release-I-20-005: NRC Proposes $7,500 Fine for West Virginia Engineering Firm Press Release-I-20-004, NRC Proposes $7,500 Civil Penalty for Company Violations at Puerto Rico Facility2020-04-24024 April 2020 Press Release-I-20-004: NRC Proposes $7,500 Civil Penalty for Company Violations at Puerto Rico Facility Press Release-I-20-003, NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant Performance2020-04-0808 April 2020 Press Release-I-20-003: NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant Performance Press Release-I-20-002, NRC to Conduct Public Webinar on April 21 to Discuss Indian Point Nuclear Power Plant Decommissioning Topics2020-04-0707 April 2020 Press Release-I-20-002: NRC to Conduct Public Webinar on April 21 to Discuss Indian Point Nuclear Power Plant Decommissioning Topics Press Release-I-20-001, NRC Names New Resident Inspector at R.E. Ginna Nuclear Power Plant2020-01-0909 January 2020 Press Release-I-20-001: NRC Names New Resident Inspector at R.E. Ginna Nuclear Power Plant 2023-03-10
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs, Region I 2100 Renaissance Blvd., King of Prussia, Pa. 19406 E-mail: opa1@nrc.gov Site: www.nrc.gov Blog: http://public-blog.nrc-gateway.gov No. I-12-025 May 17, 2012
Contact:
Diane Screnci, (610) 337-5330 Email: opa1.resource@nrc.gov Neil Sheehan, (610) 337-5331 NRC ISSUES CONFIRMATORY ACTION LETTER ON COMMITMENTS TO ADDRESS SEABROOK NUCLEAR PLANT CONCRETE DEGRADATION The Nuclear Regulatory Commission staff has issued a Confirmatory Action Letter (CAL) to NextEra Energy Seabrook, LLC, confirming regulatory commitments made by the company to address concrete degradation at the Seabrook nuclear power plant. NextEra owns the plant, which is located in Seabrook, N.H.
In the license renewal application for the Seabrook plant, NextEra identified concrete degradation at the facility in the form of alkali silica reaction, or ASR. A gel resulting from ASR can expand and cause micro-cracks in the concrete. At Seabrook, certain below-grade concrete structures have experienced groundwater infiltration, which in turn has induced ASR.
Based on its review to date, the NRC has determined the affected structures remain capable of performing their safety-related functions. However, in a letter sent to the company, the agency states that the information is needed to enable the NRC staff to ensure that adequate corrective actions are being taken to address the condition. The company is required to provide the NRC with a written response if it does not think it will be able to fulfill the regulatory commitments by the dates specified, and if the company proposes to change any of the commitments.
The NRC staff held a public meeting with Seabrook plant management on April 23rd to discuss the companys actions to date on the issue. NextEra committed to provide additional information to the NRC regarding its upcoming testing, evaluations and other activities in response to the concrete degradation. May 3rd and 10th letters from NextEra to the NRC listed regulatory commitments to be completed and the dates for those activities. They include:
Submitting a root cause assessment and an evaluation of the impact of ASR at Seabrook by May 25, 2012 Revising the prompt operability determination for the B electrical tunnel exterior wall by May 25, 2012
Submitting the corrective action plan for continued assessment of ASR in concrete structures at Seabrook, including the development of remedial actions to mitigate ASR effects, where warranted, by June 8, 2012 Revising the prompt operability determination for several other ASR-affected structures by June 30, 2012 Completing short- and long-term concrete aggregate expansion testing by June 30, 2012, and June 30, 2013, respectively, with results available to the NRC approximately 30 days after completion Submitting the technical details of the testing planned at the companys contracted research and development facility, the University of Texas, by June 30, 2012 Updating the plan for the monitoring of structures for ASR by July 15, 2012 Performing initial six-month crack measurements and indexing at 20 locations in areas exhibiting the highest crack indices by July 15, 2012 Completing an anchor test program by Dec. 31, 2012 Issuance of the CAL does not preclude the NRC from taking additional steps, including enforcement actions, for any violations of agency requirements that are identified.
A copy of the CAL will be available in the NRCs electronic documents system at:
http://adams.nrc.gov/wba.
News releases are available through a free listserv subscription or by clicking on the EMAIL UPDATES link on the NRC homepage (www.nrc.gov). E-mail notifications are sent to subscribers when news releases are posted to NRC's website. For the latest news, follow the NRC on www.twitter.com/NRCgov.