| number = ML101320279 | | number = ML101320279 | ||
| issue date = 05/11/2010 | | issue date = 05/11/2010 | ||
| title = | | title = Notification of NRC Initial Operator Licensing Examination 05000285/2010301 | ||
| author name = Haire M | | author name = Haire M | ||
| author affiliation = NRC/RGN-IV/DRS/OB | | author affiliation = NRC/RGN-IV/DRS/OB | ||
| addressee name = Bannister D | | addressee name = Bannister D | ||
| addressee affiliation = Omaha Public Power District | | addressee affiliation = Omaha Public Power District | ||
| docket = 05000285 | | docket = 05000285 | ||
Line 14: | Line 14: | ||
| page count = 4 | | page count = 4 | ||
}} | }} | ||
See also: [[ | See also: [[see also::IR 05000285/2010301]] | ||
=Text= | =Text= | ||
{{#Wiki_filter:May 11, 2010 | {{#Wiki_filter:UNITED STATES | ||
NU CLE AR RE G UL AT O RY C O M M I S S I O N | |||
R E GI ON I V | |||
612 EAST LAMAR BLVD , SU ITE 400 | |||
AR LIN GTON , TEXAS 76011-4125 | |||
SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF NRC INITIAL OPERATOR LICENSING EXAMINATION 05000285/2010301 | May 11, 2010 | ||
David J. Bannister, Vice President | |||
and Chief Nuclear Officer | |||
were made for the administration of licensing examinations at Fort Calhoun Station during the week of September 20, 2010. | Omaha Public Power District | ||
444 South 16th St. Mall | |||
Reactors, | Omaha, NE 68102-2247 | ||
SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF NRC INITIAL OPERATOR | |||
To meet the above schedule, it will be necessary for your staff to furnish the examination outlines by July 2, 2010. | LICENSING EXAMINATION 05000285/2010301 | ||
submitted to the NRC for review and approval. | Dear Mr. Bannister: | ||
In a telephone conversation on May 7, 2010, between Messrs. Thomas Giebelhausen, | |||
Manager, Operations Training and Simulator, and Brian Larson, Chief Examiner, arrangements | |||
were made for the administration of licensing examinations at Fort Calhoun Station during the | |||
week of September 20, 2010. | |||
As agreed during the telephone conversation, your staff will prepare the examinations based on | |||
the guidelines in NUREG-1021, Operator Licensing Examination Standards for Power | |||
Reactors, Revision 9, Supplement 1, and NUREG-1122, Knowledge and Abilities Catalog for | |||
Nuclear Power Plant Operators, Revision 2, Supplement 1. The NRCs regional office will | |||
discuss with your staff any changes that might be necessary before the examinations are | |||
administered. | |||
To meet the above schedule, it will be necessary for your staff to furnish the examination | |||
outlines by July 2, 2010. The written examinations, operating tests, and supporting reference | |||
materials identified in Attachment 3 to ES-201 will be due by July 30, 2010. Pursuant to | |||
Title 10, Section 55.40(b)(3), of the Code of Federal Regulations, an authorized representative | |||
of the facility licensee shall approve the outlines, examinations, and tests before they are | |||
submitted to the NRC for review and approval. All materials shall be complete and ready-to- | |||
use. We request that any personal, proprietary, sensitive unclassified, or safeguards | |||
information in your response be contained in a separate enclosure and appropriately marked. | |||
Any delay in receiving the required examination and reference materials, or the submittal of | |||
inadequate or incomplete materials, may cause the examinations to be rescheduled. In | |||
addition, your support for on-site validation of the examinations is required during the week of | |||
August 16, 2010. | |||
Omaha Public Power District -2- | |||
Omaha Public Power District - 2 - | Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in | ||
effect while the written examinations and operating tests are being administered. | |||
To permit timely NRC review and evaluation, your staff should submit preliminary reactor | |||
approval number 3150-0090), medical certifications (OMB approval number 3150-0024), and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first examination date. | operator and senior operator license applications (Office of Management and Budget (OMB) | ||
approval number 3150-0090), medical certifications (OMB approval number 3150-0024), and | |||
waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first | |||
examination date. If the applications are not received at least 30 days before the examination | |||
date, a postponement may be necessary. Signed applications certifying that all training has | |||
been completed should be submitted at least 14 days before the first examination date. | |||
This letter contains information collections that are subject to the Paperwork Reduction Act of | |||
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under | |||
approval number 3150-0018, which expires on February 28, 2013. The public reporting burden | |||
for this collection of information is estimated to average 50 hours per response, including the | |||
time for reviewing instructions, gathering and maintaining the data needed, and completing and | |||
reviewing the collection of information. Send comments regarding this burden estimate or any | |||
other aspect of these information collections, including suggestions for reducing the burden, to | |||
the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory | |||
Commission, Washington, DC 20555-0001, or by Internet electronic mail to | |||
INFOCOLLECTS@NRC.GOV. | |||
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an | |||
information collection unless it displays a currently valid OMB control number. | |||
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its | |||
enclosures will be available electronically for public inspection in the NRCs Public Document | |||
Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide | |||
Documents Access and Management System (ADAMS). ADAMS is accessible from the | |||
electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading- | |||
rm/adams.html. | |||
Thank you for your cooperation in this matter. Mr. Giebelhausen has been advised of the | |||
policies and guidelines referenced in this letter. If you have any questions regarding the NRCs | |||
examination procedures and guidelines, please contact Mr. Larson at 817-860-8172, or myself | |||
at 817-860-8159. | |||
Sincerely, | |||
/RA/ | |||
Mark S. Haire, Chief | |||
Operations Branch | |||
Division of Reactor Safety | |||
Docket: 50-285 | |||
License: DPR-40 | |||
Omaha Public Power District -3- | |||
DISTRIBUTION: | |||
Jeffrey A. Reinhart | |||
Site Vice President | |||
Omaha Public Power District | |||
Fort Calhoun Station FC-2-4 Adm. | |||
P.O. Box 550 | |||
Fort Calhoun, NE 68023-0550 | |||
Mr. Thomas C. Matthews | |||
Manager - Nuclear Licensing | |||
Omaha Public Power District | |||
Fort Calhoun Station FC-2-4 Adm. | |||
P.O. Box 550 | |||
Fort Calhoun, NE 68023-0550 | |||
David A. Repka | |||
Winston & Strawn | |||
1700 K Street, NW | |||
Washington, DC 20006-3817 | |||
Chairman | |||
Washington County Board of Supervisors | |||
P.O. Box 466 | |||
Blair, NE 68008 | |||
Ms. Julia Schmitt, Manager | |||
Radiation Control Program | |||
Nebraska Health & Human Services | |||
Division of Public Health | |||
P.O. Box 95026 | |||
Lincoln, NE 68509-5026 | |||
Ms. Melanie Rasmussen | |||
Radiation Control Program Officer | |||
Bureau of Radiological Health | |||
Iowa Department of Public Health | |||
Lucas State Office Building, 5th Floor | |||
321 East 12th Street | |||
Des Moines, IA 50319 | |||
Chief, Technological Hazards Branch | |||
FEMA, Region VII | |||
9221 Ward Parkway | |||
Suite 300 | |||
Kansas City, MO 64114-3372 | |||
Omaha Public Power District -4- | |||
Electronic distribution by RIV: | |||
Regional Administrator (Elmo.Collins@nrc.gov) | |||
Acting Deputy Regional Administrator (Art.Howell@nrc.gov) | |||
DRP Director (Dwight.Chamberlain@nrc.gov) | |||
DRP Deputy Director (Anton.Vegel@nrc.gov) | |||
Omaha Public Power District | DRS Director (Roy.Caniano@nrc.gov) | ||
DRS Deputy Director (Troy.Pruett@nrc.gov) | |||
Senior Resident Inspector (John.Kirkland@nrc.gov) | |||
Resident Inspector (Jacob.Wingebach@nrc.gov) | |||
Branch Chief, DRP/E (Jeff.Clark@nrc.gov) | |||
Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov) | |||
FCS Administrative Assistant (Berni.Madison@nrc.gov) | |||
Public Affairs Officer (Victor.Dricks@nrc.gov) | |||
Public Affairs Officer (Lara.Uselding@nrc.gov) | |||
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov) | |||
Project Manager (Alan.Wang@nrc.gov) | |||
RITS Coordinator (Marisa.Herrera@nrc.gov) | |||
Regional Counsel (Karla.Fuller@nrc.gov) | |||
DRS Deputy Director (Troy.Pruett@nrc.gov) Senior Resident Inspector (John.Kirkland@nrc.gov) Resident Inspector (Jacob.Wingebach@nrc.gov) Branch Chief, DRP/E (Jeff.Clark@nrc.gov) Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov) | Congressional Affairs Officer (Jenny.Weil@nrc.gov) | ||
FCS Administrative Assistant (Berni.Madison@nrc.gov) Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov) Branch Chief, DRS/TSB (Michael.Hay@nrc.gov) Project Manager (Alan.Wang@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov) Regional Counsel (Karla.Fuller@nrc.gov) | OEMail Resource | ||
Congressional Affairs Officer (Jenny.Weil@nrc.gov) OEMail Resource | SUNSI Review Completed Y ADAMS: Yes No Initials: BTL | ||
Publicly Available Non-Publicly Available Sensitive Non-Sensitive | |||
ML | |||
SOE:OB C:OB | |||
BLarson MHaire | |||
SUNSI Review Completed | /RA/ /RA/ | ||
5/6/2010 5/11/2010 | |||
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax | |||
}} | }} |
Latest revision as of 19:23, 13 November 2019
ML101320279 | |
Person / Time | |
---|---|
Site: | Fort Calhoun |
Issue date: | 05/11/2010 |
From: | Mark Haire Operations Branch IV |
To: | Bannister D Omaha Public Power District |
References | |
50-285/10-301 | |
Download: ML101320279 (4) | |
See also: IR 05000285/2010301
Text
UNITED STATES
NU CLE AR RE G UL AT O RY C O M M I S S I O N
R E GI ON I V
612 EAST LAMAR BLVD , SU ITE 400
AR LIN GTON , TEXAS 76011-4125
May 11, 2010
David J. Bannister, Vice President
and Chief Nuclear Officer
Omaha Public Power District
444 South 16th St. Mall
Omaha, NE 68102-2247
SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF NRC INITIAL OPERATOR
LICENSING EXAMINATION 05000285/2010301
Dear Mr. Bannister:
In a telephone conversation on May 7, 2010, between Messrs. Thomas Giebelhausen,
Manager, Operations Training and Simulator, and Brian Larson, Chief Examiner, arrangements
were made for the administration of licensing examinations at Fort Calhoun Station during the
week of September 20, 2010.
As agreed during the telephone conversation, your staff will prepare the examinations based on
the guidelines in NUREG-1021, Operator Licensing Examination Standards for Power
Reactors, Revision 9, Supplement 1, and NUREG-1122, Knowledge and Abilities Catalog for
Nuclear Power Plant Operators, Revision 2, Supplement 1. The NRCs regional office will
discuss with your staff any changes that might be necessary before the examinations are
administered.
To meet the above schedule, it will be necessary for your staff to furnish the examination
outlines by July 2, 2010. The written examinations, operating tests, and supporting reference
materials identified in Attachment 3 to ES-201 will be due by July 30, 2010. Pursuant to
Title 10, Section 55.40(b)(3), of the Code of Federal Regulations, an authorized representative
of the facility licensee shall approve the outlines, examinations, and tests before they are
submitted to the NRC for review and approval. All materials shall be complete and ready-to-
use. We request that any personal, proprietary, sensitive unclassified, or safeguards
information in your response be contained in a separate enclosure and appropriately marked.
Any delay in receiving the required examination and reference materials, or the submittal of
inadequate or incomplete materials, may cause the examinations to be rescheduled. In
addition, your support for on-site validation of the examinations is required during the week of
August 16, 2010.
Omaha Public Power District -2-
Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor
operator and senior operator license applications (Office of Management and Budget (OMB)
approval number 3150-0090), medical certifications (OMB approval number 3150-0024), and
waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first
examination date. If the applications are not received at least 30 days before the examination
date, a postponement may be necessary. Signed applications certifying that all training has
been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under
approval number 3150-0018, which expires on February 28, 2013. The public reporting burden
for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the
time for reviewing instructions, gathering and maintaining the data needed, and completing and
reviewing the collection of information. Send comments regarding this burden estimate or any
other aspect of these information collections, including suggestions for reducing the burden, to
the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001, or by Internet electronic mail to
INFOCOLLECTS@NRC.GOV.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an
information collection unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosures will be available electronically for public inspection in the NRCs Public Document
Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide
Documents Access and Management System (ADAMS). ADAMS is accessible from the
electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-
rm/adams.html.
Thank you for your cooperation in this matter. Mr. Giebelhausen has been advised of the
policies and guidelines referenced in this letter. If you have any questions regarding the NRCs
examination procedures and guidelines, please contact Mr. Larson at 817-860-8172, or myself
at 817-860-8159.
Sincerely,
/RA/
Mark S. Haire, Chief
Operations Branch
Division of Reactor Safety
Docket: 50-285
License: DPR-40
Omaha Public Power District -3-
DISTRIBUTION:
Jeffrey A. Reinhart
Site Vice President
Omaha Public Power District
Fort Calhoun Station FC-2-4 Adm.
P.O. Box 550
Fort Calhoun, NE 68023-0550
Mr. Thomas C. Matthews
Manager - Nuclear Licensing
Omaha Public Power District
Fort Calhoun Station FC-2-4 Adm.
P.O. Box 550
Fort Calhoun, NE 68023-0550
David A. Repka
Winston & Strawn
1700 K Street, NW
Washington, DC 20006-3817
Chairman
Washington County Board of Supervisors
P.O. Box 466
Blair, NE 68008
Ms. Julia Schmitt, Manager
Radiation Control Program
Nebraska Health & Human Services
Division of Public Health
P.O. Box 95026
Lincoln, NE 68509-5026
Ms. Melanie Rasmussen
Radiation Control Program Officer
Bureau of Radiological Health
Iowa Department of Public Health
Lucas State Office Building, 5th Floor
321 East 12th Street
Des Moines, IA 50319
Chief, Technological Hazards Branch
FEMA, Region VII
9221 Ward Parkway
Suite 300
Kansas City, MO 64114-3372
Omaha Public Power District -4-
Electronic distribution by RIV:
Regional Administrator (Elmo.Collins@nrc.gov)
Acting Deputy Regional Administrator (Art.Howell@nrc.gov)
DRP Director (Dwight.Chamberlain@nrc.gov)
DRP Deputy Director (Anton.Vegel@nrc.gov)
DRS Director (Roy.Caniano@nrc.gov)
DRS Deputy Director (Troy.Pruett@nrc.gov)
Senior Resident Inspector (John.Kirkland@nrc.gov)
Resident Inspector (Jacob.Wingebach@nrc.gov)
Branch Chief, DRP/E (Jeff.Clark@nrc.gov)
Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov)
FCS Administrative Assistant (Berni.Madison@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)
Project Manager (Alan.Wang@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource
SUNSI Review Completed Y ADAMS: Yes No Initials: BTL
Publicly Available Non-Publicly Available Sensitive Non-Sensitive
SOE:OB C:OB
BLarson MHaire
/RA/ /RA/
5/6/2010 5/11/2010
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax