| issue date = 02/09/2017 | | issue date = 02/09/2017 | ||
| title = 2017 Clinton Power Station Initial Licensed Operator Examination Form ES-301-3 | | title = 2017 Clinton Power Station Initial Licensed Operator Examination Form ES-301-3 | ||
| author name = Zoia C | | author name = Zoia C | ||
| author affiliation = NRC/RGN-III/DRS/OB | | author affiliation = NRC/RGN-III/DRS/OB | ||
| addressee name = | | addressee name = | ||
Line 14: | Line 14: | ||
| document type = License-Operator, Part 55 Examination Related Material | | document type = License-Operator, Part 55 Examination Related Material | ||
| page count = 1 | | page count = 1 | ||
}} | }} | ||
=Text= | |||
{{#Wiki_filter:Facility: Clinton Date of Examinalion:1130/17 Operating Test Number: 2017-301 lntals | |||
: 1. GENERAL CRITERIA a b. c# | |||
,ú + | |||
: a. The operating test conforms with the prevously approved outline; changes are consistent with sampling requirements (e.9., 10 CFR 55.45, operational importance, safety function distribution). 6 qq | |||
: b. There is no day-to-day repetition between this and other operating tests to be administered during this examination. qq | |||
,{ | |||
: c. The operating test shall not duplicate items from the applicants' audit test(s)(see Section D.1.a). | |||
,l | |||
+w | |||
: d. Overlap with the written examination and between different parts of the operating test is within acceptable limits. + car | |||
: e. It appears lhat the operating test will differentiate between competent and less-than-competent applicants at the designated license level. | |||
I fr + 1 | |||
: 2. WALK-THROUGH CRITERIA /.. | |||
Each JPM includes the following, as applicable: | |||
a initial conditions a ntiating cues a references and tools, including associated procedures a and specific system response and other examiner cues statements descrbng important observatons to be made by the applicant criteria for successful completion of the task identification of critcal steps and their associated performance standards restrictions on the sequence of steps, if applicable | |||
ø r ry | |||
: b. Ensure that any changes from the previously approved systems and administrative walk-through outlines (Forms ES-301 -1 and 2) have not caused the test to devate from any of the acceptance criteria (e.9., item distribution, bank use, repetition from the last 2 NRC examinatons) specified on those forms and Form ES-201-2. { + a | |||
: 3. SIMULATOR CRITERIA The associated simulator operating tests (scenario sets) have been reviewed in accordance with Form ES-301-4 and a copy is attached. | |||
ø + ry | |||
/ Signature Date | |||
: a. Author 10120116 | |||
: b. Facility Reviewer (.) 10120/16 | |||
: c. NRC Chief Examiner (#) c tlfi lun | |||
: d. NRC Supervisor r/,t I zor: | |||
NOTE: - The facilig signature is not applicable for NRO-developed tests | |||
# lndependent NRC reviewer initial items in Column "c"; chief examiner concurrence is required. | |||
ES-301, Page 24 of 27}} |
Latest revision as of 05:34, 30 October 2019
ML17108A467 | |
Person / Time | |
---|---|
Site: | Clinton ![]() |
Issue date: | 02/09/2017 |
From: | Chuck Zoia Operations Branch III |
To: | Exelon Generation Co, Exelon Nuclear |
Shared Package | |
ML16308A466 | List: |
References | |
50-461/17-301 | |
Download: ML17108A467 (1) | |
Text
Facility: Clinton Date of Examinalion:1130/17 Operating Test Number: 2017-301 lntals
- 1. GENERAL CRITERIA a b. c#
,ú +
- a. The operating test conforms with the prevously approved outline; changes are consistent with sampling requirements (e.9., 10 CFR 55.45, operational importance, safety function distribution). 6 qq
- b. There is no day-to-day repetition between this and other operating tests to be administered during this examination. qq
,{
- c. The operating test shall not duplicate items from the applicants' audit test(s)(see Section D.1.a).
,l
+w
- d. Overlap with the written examination and between different parts of the operating test is within acceptable limits. + car
- e. It appears lhat the operating test will differentiate between competent and less-than-competent applicants at the designated license level.
I fr + 1
- 2. WALK-THROUGH CRITERIA /..
Each JPM includes the following, as applicable:
a initial conditions a ntiating cues a references and tools, including associated procedures a and specific system response and other examiner cues statements descrbng important observatons to be made by the applicant criteria for successful completion of the task identification of critcal steps and their associated performance standards restrictions on the sequence of steps, if applicable
ø r ry
- b. Ensure that any changes from the previously approved systems and administrative walk-through outlines (Forms ES-301 -1 and 2) have not caused the test to devate from any of the acceptance criteria (e.9., item distribution, bank use, repetition from the last 2 NRC examinatons) specified on those forms and Form ES-201-2. { + a
- 3. SIMULATOR CRITERIA The associated simulator operating tests (scenario sets) have been reviewed in accordance with Form ES-301-4 and a copy is attached.
ø + ry
/ Signature Date
- a. Author 10120116
- b. Facility Reviewer (.) 10120/16
- c. NRC Chief Examiner (#) c tlfi lun
- d. NRC Supervisor r/,t I zor:
NOTE: - The facilig signature is not applicable for NRO-developed tests
- lndependent NRC reviewer initial items in Column "c"; chief examiner concurrence is required.
ES-301, Page 24 of 27