Line 3: |
Line 3: |
| | issue date = 04/06/2012 | | | issue date = 04/06/2012 |
| | title = Email from T. Scarbrough to J. Kim, Et Al, VY Steam Dryer Inspection Reports | | | title = Email from T. Scarbrough to J. Kim, Et Al, VY Steam Dryer Inspection Reports |
| | author name = Scarbrough T G | | | author name = Scarbrough T |
| | author affiliation = NRC/NRO | | | author affiliation = NRC/NRO |
| | addressee name = Kim J S, Basavaraju C, Cheruvenki G | | | addressee name = Kim J, Basavaraju C, Cheruvenki G |
| | addressee affiliation = NRC/NRR | | | addressee affiliation = NRC/NRR |
| | docket = 05000271 | | | docket = 05000271 |
|
---|
Category:E-Mail
MONTHYEARML21075A1582021-03-15015 March 2021 E-mail from T. Silko to J. Parrott, NMSS, Vermont Yankee on the State of Vermont Comments on the Review of the Draft Final SER and EA for 20.2002 Alternate Disposal Request ML21006A0242020-12-22022 December 2020 E-mail from J. Parrott to J. Tierney and N. Creed Vermont Yankee Request to NRC for Alternate Disposal of Wastewater ML20358A0702020-12-22022 December 2020 E-mail Acceptance Review for Request for Indirect License Transfer (License DPR-28, Docket No. 50-271) ML20175A2122020-06-23023 June 2020 Acceptance Review of Request for Alternate Disposal of Wastes Under 10 CFR 20.2002 (License DPR-28, Docket No. 50-271) ML19289A1292019-10-11011 October 2019 Email from Daniel Doyle to Mark Leyse Status of PRM-50-93 and PRM-50-95 ML19288A0292019-10-11011 October 2019 NRC Acceptance Review - Northstar Request for Exemption from 10 CFR 20, App G, Section Iii.E (License DPR-28, Docket No. 50-271) ML19198A2512019-06-20020 June 2019 Alternate Disposal Request - Rail Shipments (License DPR-28, Docket No. 50-271) ML19059A1782019-02-28028 February 2019 Acceptance Review Results for Relief Request No. EN-19-RR-1 to Use ASME Code Case N-831-1 for Entergy Fleet ML18289A3622018-10-11011 October 2018 Email from Daniel Doyle to Mark Leyse Status of PRM-50-93 and PRM-50-95 ML18127A5582018-04-25025 April 2018 Email to State of Vermont on Vermont Yankee Nuclear Power Station - Forthcoming Issuance of a License Amendment Regarding the Requirement for the VYNPS to Have a Cyber Security Plan ML18045A0862018-01-25025 January 2018 Email Request for Review of the Draft Safety Evaluation for Implementation of a Revised Emergency Plan at Vermont Yankee to Reflect an ISFSI-only Configuration ML17353A0092017-12-18018 December 2017 E-Mail from William Irwin, Vermont Department of Health to Y. Chen/Dsfm Response: Draft Environmental Assessment: Exemption Request for Vermont Yankee Independent Spent Fuel Storage Installation ML17289A4222017-10-16016 October 2017 E-Mail from Y. J. Chen to W. Irwin Draft Environmental Assessment Exemption Request for Vermont Yankee Independent Spent Fuel Storage Installation ML17257A0022017-09-14014 September 2017 Email to VY Shpo W Ltr Re VYNPS Exemption Load Campaign - Sept 2017 ML17229B4842017-08-16016 August 2017 Request for Supplemental Documentation to Support Review of the Physical Security Plan ML17219A0472017-08-0303 August 2017 8/03/2017, E-Mail from Y. J. Chen/Nmss to T. B. Silko/Vermont Yankee Regarding Need for Additional Information Entergy'S Exemption Request for Vermont Yankee ISFSI, Dated May 16, 2017 (ML17142A358) ML17144A0452017-05-23023 May 2017 5/23/2017, E-Mail to I. William/Vermont Dept. of Health from Y. Chen/Nrc Response: Draft Environment Assessment: Exemption Request for Vermont Yankee Independent Spent Fuel Storage Installation (W/Attachment Ltr to Address Comments on EA) ML17080A4752017-03-16016 March 2017 3/16/2017, E-Mail from I. William/Vermont Department of Health to Yen-Ju Chen/Dsfm/Sflb, Providing Comments on Draft Environmental Assessment for Entergy/Vermont Yankee'S Exemption from Requirement of 10 CFR 72.7 for CoC No. 72-1014, Amendm ML17055A6262017-02-24024 February 2017 Cover Email from VY Shpo W Concurrence on No Effects Determination ML17040A3372017-02-0909 February 2017 Email and Letter to Vermont Shpo ISFSI Exemption No Effects Determination ML17038A4682017-02-0707 February 2017 2/07/2017, E-mail from Yen-Ju Chen/NRC-DSFM to W. Irwin/Vermont Dept. of Health Draft Environment Assessment for Entergy/Vermont Yankee'S Exemption from Requirement of 10 CFR 72.7 for Certificate of Compliance No. 72-1014, Amendment 10 ML17012A2472017-01-11011 January 2017 E-mail - State of Vermont Comments Regarding Vermont Yankee'S 10 CFR 20.2002 Request ML16349A2492016-12-13013 December 2016 E-Mail to T. B. Silko/Entergy from Yen-Ju Chen/Dsfm Regarding Need for Supplemental Information for Entergy'S Exemption Request for Vermont Yankee ISFSI, Dated November 9, 2016 (ML16319A102) ML17013A2502016-12-12012 December 2016 Email Requesting Review of Draft EA and SER for Vermont Yankee Request to NRC for Alternate Disposal of Waste ML16231A0282016-08-11011 August 2016 Response to NRC Questions Related to Request for 20.2002 Disposal of Contaminated Water ML16231A2192016-07-28028 July 2016 Follow-up Questions Related to Entergy Request for 20.2002 Disposal of Contaminated Water ML16069A0952016-03-0303 March 2016 Request for 20.2002 Disposal, Request for Additional Information ML16053A5152016-02-17017 February 2016 Comment (037) of Emma Stamas on ANPR-26, 50, 52, 73, and 140 - Regulatory Improvements for Decommissioning Power Reactors ML15329A1802015-11-24024 November 2015 E-mail from J. Whited Draft RAIs Re Duke License Amendment Request to Adopt TSTF-523 (CAC Nos. MF6413 Through MF6422) ML15295A2132015-10-21021 October 2015 NRR E-mail Capture - VY RAI for Off-site Insurance Exemption (10 CFR 140.11) - MF3980 ML15289A6002015-09-24024 September 2015 La 3 - Vermont Yankee Draft Responses or Edits 9 24 15.docx ML15289A6012015-09-23023 September 2015 La 3 - Nrr_Vermont Yankee Nuclear Power Station Decommissioning Status.Docx ML15288A3532015-09-21021 September 2015 La 3 - VY Dtf LAR - Status ML15257A6172015-09-14014 September 2015 La 3 - Testing the New Profile for Vermont Yankee La 3 - Public ML15195A3592015-07-14014 July 2015 NRR E-mail Capture - Acceptance Review for Vermont Yankee Amendment -Revise Cyber Security Plan Implementation ML15289A0022015-06-17017 June 2015 La 3 - Question from Ma ML15289A5982015-06-0909 June 2015 La 3 - FW: Docket No. 50-271 (Vermont Yankee); June 5 2015 Letter from Vermont, Vynpc, and Gmp to NRC Attached ML15289A0072015-06-0505 June 2015 La 3 - Information Regarding Vermont Yankee Decommissioning Trust Fund Exemption ML15289A2432015-06-0404 June 2015 La 3 - FW: Docket No. 50-271 (Vermont Yankee); June 4 2015 Vermont Letter to NRC Attached ML15289A0062015-06-0404 June 2015 La 3 - FW: Information Regarding Vermont Yankee Decommissioning Trust Fund Exemption ML15288A3592015-06-0101 June 2015 La 3 - Vermont Yankee LA3 - Availability for Oral Argument ML15288A3602015-06-0101 June 2015 La 3 - Vermont Yankee LA3 - Availability for Oral Argument ML15288A3622015-06-0101 June 2015 La 3 - Vermont Yankee LA3 - Availability for Oral Argument ML15288A4822015-05-22022 May 2015 La 3 - Vermont Reply to NRC & Entergy Answers Re VY LA-3 ML15289A0042015-05-19019 May 2015 La 3 - New Proposal Dates for Phone Call with VT ML15289A0052015-05-11011 May 2015 La 3 - ML Numbers for Disbursement Letters for Vermont Yankee ML15289A5992015-05-0808 May 2015 La 3 - Call with State of VT ML15289A0032015-05-0707 May 2015 La 3 - Other than for Comanche Peak, ML15289A1252015-05-0606 May 2015 La 3 - FRN Review - VY Dtf Exemption ML15128A0232015-04-27027 April 2015 NRR E-mail Capture - Petitioners Response to Request for Comments on the Proposed Director'S Decision on the 2.206 Petition Regarding Financial Qualifications of Entergy 2021-03-15
[Table view] |
Text
A17 .'Cheruvenki, Ganesh From: Scarbrough, Thomas Sent: Friday, April 06, 2012 942 AM To: Kim, James; Cheruvenki, Ganesh; Basavaraju, Chakrapani; Jessup, William; Sheng, Simon Cc: Guzman, Richard
Subject:
RE: VY Steam Dryer Inspection Reports I can attend for about an hour early in the morning on April 11, 12, or 13 in Rockville.
If I am not available, please continue with the plan without me.My next availability would be the week of April 23.Thanks.Tom From: Kim, James W 39 Sent: Thursday, Aprit12 3:39 PM To: Cheruvenki, Ganesh; Basavaraju, Chakrapani; Jessup, William; Scarbrough, Thomas; Sheng, Simon Cc: Guzman, Richard
Subject:
RE: VY Steam Dryer Inspection Reports Gentlemen, I would like to propose either April 1 1 th (Wed) or 1 2 th (Thursday).
Please let me know ASAP.Thanks Jim Kim p.s. As of April 9, 2012, Rich Guzman will be a new Vermont Yankee Project Manager and any future communications regarding Vermont Yankee should be directed to Rich Guzman. He is located at O-8H5 and his phone number is 301-415-1030.
From: Kim, James Sent: Wednesday, April 04, 2012 11:21 AM To: Kim, James; Cheruvenki, Ganesh Cc: Basavaraju, Chakrapani; Jessup, William; Scarbrough, Thomas; Sheng, Simon
Subject:
RE: VY Steam Dryer Inspection Reports Gentlemen, GE is planning to bring down the reports to a local office in Rockville for you to review the reports. Please provide me with a couple of dates for next week that are good for you to review the reports.Thanks Jim Kim From: Kim, James Sent: Tuesday, February 28, 2012 9:05 AM To: Cheruvenki, Ganesh Cc: Basavaraju, Chakrapani; Jessup, William; Scarbrough, Thomas; Sheng, Simon
Subject:
VY Steam Dryer Inspection Reports Gentlemen, VY is working with GE representative, Patricia Campbell, concerning the logistics of gathering and bring down the inspection reports and INRs. Please let me know what dates are good for you to review the reports. The earliest date they can bring the reports is the week of March 2 6 th.Thanks Jim Kim From: Kim, James Sent: Monday, February 27, 2012 8:45 AM To: Cheruvenki, Ganesh Cc: Basavaraju, Chakrapani; Jessup, William; Scarbrough, Thomas; Sheng, Simon
Subject:
RE: Inspections--Steam dryer--Today's meeting at 1.00 pm at 09B6.Gentlemen, VY has provided the final counts for GE reports and INRs regarding the steam dryer inspections.
There are 3 RF024 evaluations, I RF025 evaluation, 2 RF026 evaluations, 1 RF027 evaluation and 1 RF028 evaluation to make 8 in all.There are 4 INR's from GE for RF024, 7 INF's from AREVA for RF025, 17 INR's from GE for RF026, 24 INR's from AREVA for RF027, 23 INR's from AREVA for RF028 and 1 INR from GE for RF029. These INR's and INF's from GE and AREVA are just for the steam dryer and note that there are sometimes more than one indication per INR or INF.Thanks Jim Kim From: Cheruvenki, Ganesht\bL Sent: Thursday, February 23,)0'12 2:23 PM To: Kim, James Cc: Basavaraju, Chakrapani; Jessup, William; Scarbrough, Thomas; Sheng, Simon
Subject:
RE: Inspections--Steam dryer--Today's meeting at 1.00 pm at 09B6..Jim, Please inform the licensee that disposition of the detected flaws is critical for our review. If Simon is not satisfied, we may have to reject the request.From: Sheng, Simon Sent: Thursday, February 23, 2012 2:09 PM To: Cheruvenki, Ganesh Cc: Kim, James; Basavaraju, Chakrapani; Jessup, William; Scarbrough, Thomas
Subject:
RE: Inspections--Steam dryer--Today's meeting at 1.00 pm at 09B6.Ganesh, I am more interested in reports documenting disposition of the detected flaws. Do these 20 or so inspection reports also contain information regarding disposition of the detected flaws? Or GE has separate reports to document the disposition?
Simon 2 From: Cheruvenki, Ganesh Sent: Thursday, February 23, 2012 1:48 PM To: Kim, James; Basavaraju, Chakrapani; Scarbrough, Thomas; Jessup, William; Sheng, Simon
Subject:
RE: Inspections--Steam dryer--Today's meeting at 1.00 pm at 09B6.It is OK with me. At least Pani/Tom and Simon should be present.From: Kim, James Sent: Thursday, February 23, 2012 10:32 AM To: Cheruvenki, Ganesh; Basavaraju, Chakrapani; Scarbrough, Thomas; Jessup, William; Sheng, Simon
Subject:
RE: Inspections--Steam dryer--Today's meeting at 1.00 pm at 09B6.Gentlemen, VY has proposed that both GE and VY representatives are willing to bring the inspections reports (approx. 20 GE proprietary inspection reports) to NRC for tech staff to review the steam dryer inspection reports and answer any questions NRC tech staff may have. Please let me know if this approach is acceptable.
Thanks Jim Kim From: Cheruvenki, Ganesh Sent: Tuesday, February 21, 2012 8:59 AM To: Basavaraju, Chakrapani; Scarbrough, Thomas; Jessup, William; Sheng, Simon Cc: Kim, James
Subject:
Inspections--Steam dryer--Today's meeting at 1.00 pm at 09B6.Importance:
High Pani, Tom, Simon and Billy.Here is my draft report on the inspection results (RF-26, 27 and 28) of the steam dryer and it contains status of new indications.
I still think we need to see the GE evaluation report which can provide information on the.licensee's justification for using less frequent inspections.