| facility = Paducah Gaseous Diffusion Plant
| facility = Paducah Gaseous Diffusion Plant
| Organization =  
| Organization =  
| license number = Gdp-1
| license number = GDP-1
| region = 2
| region = 2
| state = Kentucky
| state = Kentucky
Line 16: Line 16:
| event date = 12/06/2007 15:50 CST
| event date = 12/06/2007 15:50 CST
| last update date = 12/07/2007
| last update date = 12/07/2007
| title = Unplanned Safety System Actuation And Contamination Event
| title = Unplanned Safety System Actuation and Contamination Event
| event text = On 12/06/2007 at 1550 [CST] the C-337 unit 5 cell 3 PGLD (process gas leak detection) head in the C-337 unit 5 cell 3 housing actuated and would not clear. Response to the alarm by operators revealed a haze above the cell indicating a UF6 release inside the cell housing. While the operators were responding to the unit 5 Cell 3 alarm, two other PGLD heads actuated in C-337 unit 5 cell 5. To stop the release both cells 3 and 5 were taken below atmospheric pressure. Investigation indicated that a UF6 release had occurred. The amount of material released has not been determined.
| event text = On 12/06/2007 at 1550 [CST] the C-337 unit 5 cell 3 PGLD (process gas leak detection) head in the C-337 unit 5 cell 3 housing actuated and would not clear. Response to the alarm by operators revealed a haze above the cell indicating a UF6 release inside the cell housing. While the operators were responding to the unit 5 Cell 3 alarm, two other PGLD heads actuated in C-337 unit 5 cell 5. To stop the release both cells 3 and 5 were taken below atmospheric pressure. Investigation indicated that a UF6 release had occurred. The amount of material released has not been determined.
The actuated PGLD heads are Q safety system components. At the time of the incident the cell was operating in a mode which required the system to be operational. This is being reported based on SAR 6.9 Table 1, J2 (unplanned actuation of a Q safety system) and 10 CFR 76.120 (c) (1) (i) (unplanned contamination event).
The actuated PGLD heads are Q safety system components. At the time of the incident the cell was operating in a mode which required the system to be operational. This is being reported based on SAR 6.9 Table 1, J2 (unplanned actuation of a Q safety system) and 10 CFR 76.120 (c) (1) (i) (unplanned contamination event).

Latest revision as of 19:30, 24 November 2018

ENS 43828 +/-
Where
Paducah Gaseous Diffusion Plant
Paducah, Kentucky (NRC Region 2)
License number: GDP-1
Reporting
10 CFR 76.120(c)(1)

Other Unspec Reqmnt
Time - Person (Reporting Time:+17.87 h0.745 days <br />0.106 weeks <br />0.0245 months <br />)
Opened: Billy Wallace
15:42 Dec 7, 2007
NRC Officer: Howie Crouch
Last Updated: Dec 7, 2007
43828 - NRC Website