W3P84-0431, Discusses Activities & Commitments to Be Completed Prior to Fuel Load.Listed Open Items Will Be Completed Prior to 840430
| ML20081C187 | |
| Person / Time | |
|---|---|
| Site: | Waterford |
| Issue date: | 03/08/1984 |
| From: | Cook K LOUISIANA POWER & LIGHT CO. |
| To: | Knighton G Office of Nuclear Reactor Regulation |
| References | |
| W3P84-0431, W3P84-431, NUDOCS 8403120168 | |
| Download: ML20081C187 (6) | |
Text
,
LOUISIANA / i 2 OuAnO~oe sincer P O 'N E R & L I G H T/ P O BOX 6008 e NEW ORLEANS. LOUISIANA 7017A. (504) 366 2345 NEdYS March 8, 1984 W3P84-0431 3-A1.01.04 Director of Nuclear Reactor Regulation Attention:
Mr. G. W. Knighton, Chief Licensing Branch No. 3 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D. C. 20555
SUBJECT:
Waterford SES Unit 3 Docket No. 50-382 Activities and Commitments to be Completed Prior to Fuel Load
Dear Sir:
The construction and preoperational testing phases of Louisiana Power & Light Company's Waterford Steam Electric Station Unit 3 are nearing completion and final preparations for initial core loading are in progress.
A thorough assessment of project completion plans has been made and the baseline plant configuration to safely support initial t'ucl loading has been established using the FSAR, NRC Safety Evaluation Report and Supplements, and the Final Environmental Statement as guidance. Attachment I identifies
(
the plant systems which LP6L intends to have constructed, tested, and trans-ferred from Construction /Startup to Plant Staff control prior to fuel load.
Systems which are required by Technical Specifications will be determined OPERABLE by satisfying the applicable Surveillance Requirements and will assure that fuel load and subsequent plant testing and operations will have no adverse impact on the health and well being of the general public and plant personnel.
Licensing-related activities and commitments, which presently are not completed but are considered to be necessary for fuel load, have been identified and are being tracked to completion utilizing LP&L's Licensing Commitment Tracking System. The items contained on these reports receive on-going management review, are updated frequently, and are giver. high visibility throughout the Nuclear Operations organization. These reports have been provided to both the NRC Project Manager and Sr. Resident Inspector for Waterford 3.
We will continue to provide updated reports on a reutine basis until Fuel Load. Additional items, not contained on the prior to fuel load reports, are considered requisite to criticality, low power physics testing, or power escalation sequence testing. As sach they are tracked and receive frequent management reviews to ensure that they are completed prior to their required need.
/
8403120168 840308 PDR ADOCK 05000382 A
PDR m
i
.m
't Mr. G. W. Knighten W3784-0431 Page Two it is LP&L's plan.to complete essentially all open items required prior to fuel load by not later than April 30, 1984. Thus it is expected that LP&L will be ready for receipt of the Operating License for Waterford 3 on that date.
If after your review of the attached information you have any questions or wish to discuss this matter further, please do not hesitate to contact me.
Very truly yours, K. W. Cook
~,
Nuclear 92pport & Licensing Manager KWC/WAC/pco
- cc.;
E. L. Blake, W. M. Stevenson, G.- L. Constable, J. II. Wilson k
AITACHMENT I BAM Boric Acid Makeup HT Heat Tracing CVC Chemical and Volume Control BM Boron Management DC 125 Vdc Electrical Distributi n ID Inverters and Distribution LVD Low Voltage Distribution SSD 480 V Station Service Distribution 4kV 4.16 kV Electrical Distribution ST Startup Transformers EG Emergency Generators ECA Emergency Diesel Air ECC Emergency Diesel Cooling EGF Emergency Diesel Fuel EGL Emergency Diesel Lube Oil CC Component Cooling Water ACC Auxiliary Component Cooling Water FP Fire Protection FPD Fire Detection RC Reactor Coolant SI Safety Injection CS Containment Spray M
-CHW Chilled Water PAS Post Accident Monitoring PRM Process Radiation Monitoring ARM Area Radiation Monitoring k:.
CB Containment Building CAR Containment 'tmosphere Release CAP Contairment Atmosphere Purge SP Sump Pumps EM Environmental Monitoring SM Seismic Menitoring RER Refrigeration PAC Process Analog Control PPS Plant Protection System ESF Engineering Safety Features Actuation System HVC Control Room HVAC HVR Reactor Auxiliary Building I;VAC SS Site Security ENI' Excore Nuclear Instrumentation
.IA Instrument Air IC Instrument Cabinets ANN Annunciators FHS Fuel Handlinb and Storage HRA Hydrogen Recombiners and Analyzers
.PSL Primary Sampling System CTB Constant Temperature Bath DFO Diesel Fuel Oil CRN Cranes SG Steam Generators MS Main Steam BD Blowdown DW Demineralized Water PMU.
Primary Makeup (2)
TW Treated Water CW Circulating Water TSW Traveling Screens and Wash EFW Emergency Feedwater CCS Containment Cooling System ANP Annulus Negative Pressure CVR Containment Vacuum Relief SBV Shield Building Ventilation RCC Reactor Cavity Cooling LWM Liquid Waste Management GWM Gaseous Waste Management INI In-core Nuclear Instrumentation MNI Movable In-core Nuclear Instrumentation
.CDC Control Element Drive Cooling PMC Plant Monitoring Computer CEC Control Element Assembly Calculator VLP Vibration and Loose Parts Monitroing LRT Leak Rate Testing CSD Control Element Drive Mechanism SVS Cable Vault and Switchgear Ventilation SSL Seconoary Sampling System CMP Communications Paging CMR Communications Radio CMS Communications Sound Powered telephones CMT Communications Telephones CMU Condensate Makeup Storage AB Auxiliary Boiler (3) g -
f*
ABC Auxiliary Boiler Condensate ABF Auxiliary Boiler Fuel ABS Auxiliary Boiler Steam AS Auxiliary Steam AE Air Evacuation
. GS Gland Steam TC Turbine Cooling CD Condensate FW Feedwater LOG Turbine Generator Lube Oil LOF Feed Pump Lube Oil 7kV 6.9 kV Electrical Distributica EH Electro-hydraulic Fluid 50 3eal Oil NG Nitrogen COL Core Operating Limits Supervisory System CPC Core Protection Calculator RMC Radiation Monitoring Computet
' EBA.
Emergency Breathing Air MT Main Transformer 4
(4)-
.