Other: ML13220A402, ML13317A969, ML15141A468, ML15272A398, W3F1-2012-0092, Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), W3F1-2012-0093, Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049), W3F1-2013-0006, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, Order Number EA-12-051, W3F1-2013-0010, (Waterford 3), Entergy Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3, W3F1-2013-0049, First Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, W3F1-2013-0050, First Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, W3F1-2014-0014, Second Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, W3F1-2014-0015, Second Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, W3F1-2014-0049, Third Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, W3F1-2014-0050, Third Six-Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Waterford Steam Electric Station, Un, W3F1-2015-0003, Fourth Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, W3F1-2015-0004, Fourth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, W3F1-2015-0068, Fifth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation
|
MONTHYEARW3F1-2012-0042, Entergys 90-Day Response to the March 12, 2012, Information Request, Action Plan for Completing Emergency Communication and Staffing Assessments2012-06-0707 June 2012 Entergys 90-Day Response to the March 12, 2012, Information Request, Action Plan for Completing Emergency Communication and Staffing Assessments Project stage: Request W3F1-2012-0092, Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2012-10-26026 October 2012 Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other W3F1-2012-0093, Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2012-10-26026 October 2012 Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) Project stage: Other W3F1-2013-0010, (Waterford 3), Entergy Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.32013-02-21021 February 2013 (Waterford 3), Entergy Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3 Project stage: Other ML1306606872013-02-28028 February 2013 CFR Part 26, Subpart I - Managing Fatigue, for Period Ending 2012 Project stage: Request W3F1-2013-0006, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, Order Number EA-12-0512013-02-28028 February 2013 Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, Order Number EA-12-051 Project stage: Other W3F1-2013-0017, (Waterford 3), Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2013-02-28028 February 2013 (Waterford 3), Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request W3F1-2013-0032, Core Operating Limits Report - Cycle 19 Revision 12013-08-26026 August 2013 Core Operating Limits Report - Cycle 19 Revision 1 Project stage: Request ML13246A3182013-08-28028 August 2013 Request for Additional Information E-mail, Overall Integrated Plan in Response to 3/12/12 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: RAI W3F1-2013-0050, First Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2013-08-28028 August 2013 First Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other W3F1-2013-0049, First Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2013-08-28028 August 2013 First Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other W3F1-2013-0055, Response to Request for Additional Information (RAI) for the Overall Integrated Plan (OIP) in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool (SFP) Instrumentation2013-09-26026 September 2013 Response to Request for Additional Information (RAI) for the Overall Integrated Plan (OIP) in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool (SFP) Instrumentation Project stage: Response to RAI ML13317A9692013-11-20020 November 2013 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Waterford Steam Electric Generating Station, Unit 3, TAC No.: MF0977 Project stage: Other ML13220A4022013-11-22022 November 2013 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 - Mitigation Strategies Project stage: Other ML13312A7872013-11-25025 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: RAI W3F1-2014-0014, Second Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-02-28028 February 2014 Second Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other W3F1-2014-0015, Second Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2014-02-28028 February 2014 Second Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other W3F1-2014-0050, Third Six-Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Waterford Steam Electric Station, Un2014-08-28028 August 2014 Third Six-Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Waterford Steam Electric Station, Unit 3 Project stage: Other W3F1-2014-0049, Third Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2014-08-28028 August 2014 Third Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other W3F1-2015-0003, Fourth Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-02-26026 February 2015 Fourth Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other W3F1-2015-0004, Fourth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2015-02-26026 February 2015 Fourth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other ML15141A4682015-05-27027 May 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other W3F1-2015-0068, Fifth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2015-08-27027 August 2015 Fifth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other W3F1-2015-0073, Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-08-31031 August 2015 Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request ML15245A3442015-10-0404 October 2015 Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Approval ML15272A3982015-10-0606 October 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other 2013-08-28
[Table View] |
Text
W3F1-2012-0092 October 26, 2012 U.S. Nuclear Regulatory Commission Attn: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
Subject:
Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
Waterford Steam Electric Station, Unit 3 (Waterford 3)
Docket No. 50-382 License No. NPF-38
Dear Sir or Madam:
On March 12, 2012, the NRC issued an order (Reference 1) to Waterford Steam Electric Station, Unit 3 (Waterford 3). Reference 1 was immediately effective and directs Waterford 3 to have a reliable indication of the water level in associated spent fuel storage pools. Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final interim staff guidance (Reference 2) was issued August 29, 2012. The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2. This report confirms that Waterford 3 has received Reference 2 and is in the process of evaluating the guidance for the purpose of providing a reliable indication of the water level in associated spent fuel storage pools as described in of Reference 1.
References:
- 1.
NRC Order Number EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ADAMS Accession Number ML12054A679)
- 2.
NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29, 2012 (ADAMS Accession Number ML12221A339)
Entergy Operations, Inc.
17265 River Road Killona, LA 70057-3093 Tel 504-739-6660 Fax 504-739-6678 djacob2@entergy.com Donna Jacobs Vice President - Operations Waterford 3
W3F1-2012-0092 Page 2 of 2 Major activities completed during this reporting period:
Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.
Planned activities for the next six months:
Development and submittal of the overall integrated plan Technical difficulties encountered that could affect the ability to provide the licensees February 28, 2013, submittal:
None at this time Project milestones schedule through completion of installation and testing:
A project milestones schedule will be provided with the overall integrated plan.
Implementation of the order will be completed for Waterford 3 prior to startup from refueling outage RF-20 (Fall 2015).
There are no new commitments contained in this submittal. Please contact Michael Mason, Licensing Manager (acting), at (504) 739-6673 if you have questions regarding this information.
I declare under penalty of perjury that the foregoing is true and correct. Executed on October 26, 2012.
Sincerely, DJ/WH cc:
Director, Office of Nuclear Reactor Regulation U. S. NRC RidsNrrMailCenter@nrc.gov Mr. Elmo E. Collins, Jr., Regional Administrator U. S. NRC, Region IV RidsRgn4MailCenter@nrc.gov NRC Program Manager for Waterford 3 Kaly.Kalyanam@nrc.gov NRC Senior Resident Inspector for Waterford 3 Marlone.Davis@nrc.gov