U-102142, Interim Potential Deficiency Rept 55-84-12 Re Installation of Concrete Expansion Anchors in Floors W/Finishing Slabs. Initially Reported on 840604.Investigation Continuing.Next Rept Will Be Submitted within 90 Days

From kanterella
(Redirected from U-102142)
Jump to navigation Jump to search
Interim Potential Deficiency Rept 55-84-12 Re Installation of Concrete Expansion Anchors in Floors W/Finishing Slabs. Initially Reported on 840604.Investigation Continuing.Next Rept Will Be Submitted within 90 Days
ML20107L257
Person / Time
Site: Clinton Constellation icon.png
Issue date: 10/26/1984
From: Hall D
ILLINOIS POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
55-84-12, U-10214, U-102142, NUDOCS 8411130464
Download: ML20107L257 (4)


Text

.

pmA

( 4F.130 1605-L

/LLINDIS POWER COMPANY ffy U-10214 CLINTON POWER STATION, P.O. BOX 678. CLINTON. ILLINOIS 61727 October 26, 1984

-Docket No. 50-461 Mr. James G. Keppler Regional Administrator Region.III U.S. Nuclear Regulatory Commission 799. Roosevelt Road Glen Ellyn, IL 60137

Subject:

Potential 10CFR50.55(e) Deficiency 55-84-12:

Installation of Concrete Expansion Anchors in Floors with Finishing Slabs

Dear Mr. Keppler:

On June 4, 1984, Illinois Power Company notified Mr. D.

Keating, NRC Region III, (Ref: IP Memorandun Y-20647 dated June 4, 1984) of a potentially reportable deficiency concerning the installation of concrete expansion anchors in floors with finish-ing slabs. This initial notification was followed by one (1) interim report (Ref: IP letter U-10177, D. P. Hall to J. G.

Keppler, dated July 13, 1984). Our investigation of this issue is continuing, and this letter is subm.itted as an interim report in accordance with the requirements of 10CFR50.55(c). Attachment A provides the details of our investigation to date.

We trust that this interim report provides you sufficient bcckground information to perform a general assessment of this potentially reportable deficiency and adequately describes our overall approach to resolve this issue.

Sincerely yours, D. P. Hall Vice President RLC/cbs (NRC) cc: URC Office Director, Office of I&E, USNRC, Washington, DC 20555 1111noia Department of Nuclear Safety INPO Pecords Center 8411130464 841026 00T 3 PDR ADOCK 05000461 S PDR

_ I@

c

. c.

ATTACHMENT A

^

Illinois Power Company n Clinton Power Station -;

g ,

~ Docket No. 50-461

Potential.10CFR50.55(e)-Deficiency 55-84-12
Installation of Concrete Expansion Anchors in Floors with Finishing Slabs

! Interim Report Statement of Potentially Reportable Deficiency Baldwin Associates Resident Engineering (BARE) provided '

Illinois Power Company (IPC) with a list, identifying supports r . installed on finisiing/ topping slabs. The concern expressed that
the installation of the concrete expansion anchors for these supports may not meet the embedment length as required by the  :

e

Sargent & Lundy (S&L) Specification. ,

L Background [

):- In February, 1984, Baldwin Associates Resident Engineering (BARE) provided Illinois Power Company with a listing of supports i?

installed;on finishing / topping slabs. . This listing identified the. support, the-length of the installed. anchor, the thickness of the finishing / topping slab, and the amount af anchor installed in-rough' concrete. Several'of the expansion anchors identified have

'an effective embedment length of zero-(0) inches (i.e., if the U thickness of the finishing / topping slab is subtracted from the required effective embedment length).

g

!~ Specification K-2944 requires the effective embedrent length

[ Lof concrete expansion anchors to be. determined from the surface l- of=the rough concrete.

t l - Illinois Power Company (IPC) requested that S&L evaluate for-

adequacy the' mechanical component supports identified by BARE.  !

i

Based'on the data submitted,'S&L has stated that none of the '

expansion anchors associated with the identified mechanical supports met the specification requirement for effective em>edment. ,

  • 1 S&L evaluated 58-installed supports for adequacy with '

regards to design loads. Of the 58 supports evaluated, 14 were ,

evaluated as inadequate for design loads. Nonconformance Reports

! (NCRs) for_these 14 installed supports will be generated when

  • L the finalized' composite drawings of the associated finishing i slabs:are reviewed..

! 'Page 1 of 4

  • w i - +- r ,-sag--,p-,,y en -g r. -er e .,r-r-s-sr- e,e-,.ge,- ,-m m m - w% # sie w, ,,re,.ey- ,_,y s.,g -e. e+ e*~, +yw,wm w w w mer.ws- ,+ w ww w m gy, ir-,++

n.

$ -3; ATTACHMENT'A (continued)

Investigation Results

~ Illinois Power has prepared-ar.d is im)lementing an inves-

. tigation plan tosdetermine the extent of this problem at Clinton Power Station (CPS). The investigation plan includes:

- 1. A review of construction procedures governing the installa- .

tion / inspection of concrete expansion anchors is being made

(

to determine adequacy and compliance.

2. - Based on the. rough as-built drawings already generated, a complete listing of all potentially affected equip-ment / components will be compiled.

-3. - A complete set'of composite as-built drawings is being generated which identifies all equipment / components in-stalled on finishing / topping slabs which utilize concrete expansion anchors for installation.

p 4.  :

The equipment / components identified by the listing" generated in item 2, will be entered into the computer in a search" ifor all documentation (i.e., NCR, FCR, etc.) that may have-addressed these components. The documents identified by'the

" search" will be reviewed to-identify those documents which address the ' problem of expansion anchor embedment.

5. All' components with expansion anchors that violate the effective embedment criteria and do not have prier approval '

documentation, will be documented on Nonconformance Reports

. (NCRs) and will be resolved in accordance with approved site procedures.

Corrective Action f

The corrective action taken on this issue to date includes:

i

1. To aid site personnel in locating finishing slabs, a  :

stencilling program was implemented. The placement of the stencilling.is'such that individuals involved with

, installation / inspection of expansion anchors can

. easily recognize areas where effective embedment would require additiona1' consideration due to the thickness of the' finishing slabs.

2. Baldwin Associatesi(BA) has issued Memo MA-31-84, dated June i' 6, 1984, reminding supervisory personnel of the requirement to install expansion anchors into the structural slab in order to achieve full embedment per S & L Specification K-2944, Form CPS-1-CEA.
Page 2 of 4 ev.. , g, w e -,- , ,e,- v ,,e- .-,--er-.co------e--+, -,.,w,-r...e-i.,.ecn.,--ve--~-,.re,m ---e.-w.-.ne.-eve %,-,-ev--w rv.,-4..m*w e - .-mg m

t e:  :. .

ATTACHMENT A (continued)

3. Several procedures and checklists have been revised to ensure proper installation and verification of the embedment

' depth:

a) QAI-710.ll, Rev. 2: Concrete Expansion Anchor Checklist, was issued on August 3, 1984, and step V specifically states the term " rough concrete (with no finishing slab)" and adds the formula for concrete embedment with finishing slabs.

b) BQAI-190-1, Rev. 4: Concrete Expansion Anchors Field Verification, was issued on August 3, 1984, and Exhibit 2, Concrete Expansion Anchor Field Verification Checklist, requires the' minimum effective embedment of expansion anchors be based on the amount of anchor length embedded in rough concrete.

c) BAP-2.16: Concrete Expansion Anchor Work - This addresses that embedment will be measured from the rough concrete surface.

d) QCI-105: Inspection / Concrete Expansion Anchor P Installation - Step 7.2.4.1 requires that embedment be measured from the surface of the rough concrete.

'4. Sargent & Lundy has 7rovided a listing, identifying all the safety-related finishing / topping slabs at CPS.

r

5. A review is being performed to identify all documents relating to installations utilizing concrete exaansion anchors on safety-related finishing / topping slais. These documents will be utilized in conjunction with the drawings to establish. adequate anchor bolt installation.
6. To date, 31-of 40 required composire as-built drawings have been generated from the individual discipline oriented rough drawings. The as-built drawings identify all equipment /

components which have utilized expansion anchors for installation and are-located on safety-related finishing slabs. Three (3) of the 40 as-built floor drawings have been finalized and QC verified. The QC review involves the verification of all anchor bolt installaticns and their dimensional location on the finishing slab. The three (3) drawings that'have been verified, represent the finishing slab in the Auxiliary Building at elevation 762'. A listing i

Page 3 of 4

7.

ATTACHMENT A (continued) of all' installations identified on the drawings has been completed. A review of dccumentation associated with these installations is being performed to identify any violation of required effective anchor embedment. Nonconformance Reports

(NCRs) will be generated to document identified violations or indeterminate conditions. These NCRs will be resolved in

-accordance with approved site procedures.

Safety Implications / Significance Illinois Power's investigation of this potentially reportable deficiency is continuing. The safety implications and significance _will be assessed after further background information is evaluated. It is anticipated that approximately five (5) months will be necessary to complete our investigation and to file a final report on the matter. Illinois Power intends to provide you an update on the investigation progress in approximately ninety (90) days.

Page 4 of 4