- 05000293/LER-2013-003, Regarding Loss of Off-Site Power Events Due to Winter Storm Nemo +
- IR 05000315/2008009 +
- ML17329A054 +
- ML18158A130 +
- RS-18-059, Eighth Six-Month Status Report for Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident +
- ML18219D351 +
- ML19277C594 +
- ML040960095 +
- ML20081B278 +
- ML20108D079 +
- ML20198T127 +
- ML20198N608 +
- 05000311/LER-1983-001, Forwards LER 83-001/03L-0.Detailed Event Analysis Encl +
- ML20237J016 +
- ML20216H603 +
- RBG-24-167, Ro:On 860808,bomb Threat Received Through State of La Natl Guard.Security Search Performed.No Bomb Found +
- 05000267/LER-1987-024, :on 871009,10,11 & 14,reactor Scram Logic & Alarm Circuitry Actuated on Neutron Flux Rate of Change High.Caused by Electrical Noise Induction in Wide Range Channels.Coil Leads Have Been Lifted +
- 05000334/LER-1997-025, :on 970807,ground in Feedwater Flow Controller Resulted in High SG Level & Subsequent Turbine Trip/Reactor Trip.Caused by Mfg Defect on Circuit Card.Formed Event Response Team +
- 05000219/LER-1987-005, :on 870116,high Flux Reactor Scram Occurred Due to Increased Recirculation Flow.Caused by Starting of Pump W/Discharge Valve Partially Open.Second Scram Occurred Due to Calibr Error.Valves Readjusted +
- 05000338/LER-1997-008, :on 971027,both EDGs Inoperable During Testing. Caused by TS Surveillance Requirement to Demonstrate Operability of Remaining EDG When One Inoperable.Required TS Actions Cleared Following 1J EDG Testing +
- 05000412/LER-1996-004-01, :on 960830,bypass Feedwater Regulating Valve Leakage Leads to Manual Reactor Trip During Shutdown for Refueling.Procedures Revised +
- 05000313/LER-1996-002-03, :on 960308,discovered That Surveillance Tests Required by TS Incomplete Because All Combinations of RPS Channel Trip Relay Contacts Not Tested Due to Procedural Deficiency.Verified Operability of RPS +
- 05000280/LER-1982-085-03, /03L-0:on 820824,RCS post-reactor Trip Specific Activity Samples Found Greater than Tech Spec Limits.Caused by Fuel Defects in Reactor Core.Acclerated Sampling Frequency Implemented Till RCS Activity Less than Tech Spec +
- 05000280/LER-1982-082-03, /03L-0:on 820713,post-reactor Trip Specific Activity Samples of RCS Indicated Dose Equivalent I-131 Level Greater than Tech Specs.Caused by Fuel Defects in Reactor Core.Accelerated Sampling Frequency Implemented +
- 05000311/LER-1981-078, Forwards LER 81-078/03L-0.Detailed Event Analysis Encl +
- 05000461/LER-1989-040, :on 891206,discovered That Mode Limitations from Surveillance Procedure Omitted,Resulting in Inoperable ATWS Recirculation Pump Trip Sys Instrumentation.Caused by Inadequate Procedure.Surveillance Revised +
- 05000334/LER-1980-101-03, /03L-0:on 801126,control Room Chlorine Detector CLA-VS-101A Failed to Meet Operating Surveillance Requirement for Drip Rate.Caused by Clogged Detector Wick & Tank Vent Failure.Vent Filter Replaced & Wick Cleaned +
- 05000397/LER-1997-001, :on 970211,reactor Water Cleanup Sys Blowdown Flow Isolation Setpoint Was Slightly Above TS Allowable Valve Occurred Due to Calculation Error.Lds Fss LD-FS-15 LD-FS-16 Were Declared Inoperable +
- 05000324/LER-2009-001, Regarding High Pressure Coolant Injection (HPCI) System Inoperable Due to Water in the HPCI Turbine Casing +
- 05000315/LER-2008-006, Regarding Manual Reactor Trip Due to Main Turbine High Vibration +
- 05000461/LER-1998-001, :on 970929,failure of Division 2 SR Battery Charger Was Noted.Caused by Deficient Supplier Soldered Connections.Insp of Division 1,2 & 4 SR Battery Chargers Are Complete & Have Been Reworked & Repaired +
- 05000313/LER-1996-002, :on 970519,surveillance Tests Required by TS Were Incomplete Because All Combinations of Contacts Not Tested Due to Procedure Deficiencies.Verified Operability of RPS +
- 05000336/LER-1996-029, :on 960715,discovered That Evaluation for Removal of Startup Rate Trip Feature Was Potentially non-conservative.Caused by Failure to Adequately Identify Design Basis Requirements.Modified Procedures +
- 05000416/LER-1982-002-01, /01T-0:on 820701,two Scrams Initiated by High Flux Spikes on Fuel Loading Chambers Connected to Source Range Monitor Noncoincident Reactor Protection Sys Logic.Probably Caused by Close Proximity of Fuel Bundles to Fuel Chamb +