ML22325A134 | 17 November 2022 | 4 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems |
IR 05000341/2021004 | 7 February 2022 | Integrated Inspection Report 05000341/2021004 |
ML21055A072 | 2 February 2021 | 3 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems |
ML20217L633 | 14 August 2020 | Documentation of the Completion of Required Actions Taken in Response to the Lessons Learned from the Fukushima Dai-Ichi Accident |
IR 05000341/2019003 | 6 November 2019 | Integrated Inspection Report 05000341/2019003 |
ML19183A023 | 31 July 2019 | Safety Evaluation Regarding Implementation of Hardened Containment Vents Capable of Operation Under Severe Accident Conditions Related to Order EA-13-109 |
IR 05000341/2017005 | 28 August 2017 | Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2017005) |
IR 05000341/2017008 | 23 February 2017 | NRC Temporary Instruction 2515/191, Mitigation Strategies, Spent Fuel Pool Instrumentation and Emergency Preparedness Inspection Report 05000341/2017008 |
ML16288A740 | 14 October 2016 | Information Request to Support Upcoming Temporary Instruction 191 Inspection at Fermi Power Plant, Unit 2 |
ML16258A040 | 29 September 2016 | Fermi, Unit 2 - Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 (CAC Nos. MF0770 and MF0771) |
IR 05000341/2016005 | 31 August 2016 | Mid-Cycle Assessment Letter for Fermi Power Plant (Report 05000341/2016005) |
NRC-16-0034, Fermi, Unit 2, Revision 20 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems | 26 May 2016 | Fermi, Unit 2, Revision 20 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems |
ML16165A460 | 26 May 2016 | Revision 20 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems |
IR 05000341/2015006 | 2 March 2016 | Annual Assessment Letter for Fermi, Unit 2 (Inspection Report 05000341/2015006) |
NRC-16-0004, Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) and Response to Request for Additional Information | 20 January 2016 | Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) and Response to Request for Additional Information |
NRC-16-0005, Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | 20 January 2016 | Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) |
ML15245A287 | 1 October 2015 | Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 |
IR 05000341/2015005 | 1 September 2015 | Mid-Cycle Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2015005) |
NRC-15-0087, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-049) | 27 August 2015 | Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-049) |
NRC-15-0086, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 27 August 2015 | Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
ML15114A445 | 5 May 2015 | Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 |
Press Release-15-030, NRC Concludes Hearing on Fermi New Reactor, Combined License to Be Issued | 30 April 2015 | Press Release-15-030: NRC Concludes Hearing on Fermi New Reactor, Combined License to Be Issued |
IR 05000341/2014001 | 4 March 2015 | Annual Assessment Letter for Fermi Power Plant, Unit 2, (Report 05000341/2014001) |
NRC-15-0003, DTE Electric Company - Fermi, Unit 2 - Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 23 February 2015 | DTE Electric Company - Fermi, Unit 2 - Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
ML15037A618 | 6 February 2015 | Memorandum and Order (Ruling on Petitions to Intervene and Requests for a Hearing) LBP-15-5 |
ML15036A212 | 4 February 2015 | M150204: Slides - Hearing on Combined License for Fermi, Unit 3; Section 189A of the Atomic Energy Act Proceeding |
M150204, M150204: Slides - Hearing on Combined License for Fermi, Unit 3; Section 189A of the Atomic Energy Act Proceeding | 4 February 2015 | M150204: Slides - Hearing on Combined License for Fermi, Unit 3; Section 189A of the Atomic Energy Act Proceeding |
ML14337A243 | 15 January 2015 | G20110262 - Final Director'S Decision - Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units |
ML14335A630 | 15 January 2015 | G20110262 - Final Response to Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units |
ML14330A259 | 20 November 2014 | Transcript of Oral Arguments in the Matter of Fermi Nuclear Power Plant, Unit 2, Monroe, Michigan on November 20, 2014, Pages 1-233 |
ML14198A141 | 27 October 2014 | G20110262/EDATS: OEDO-2011-0269 - Response LTR to Paul Gunter & Kevin Kamps Ltr. Re 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units |
ML14265A489 | 19 September 2014 | Combined Reply of Citizens' Resistance at Fermi 2 (Craft) to NRC Staff and DTE Electric Co. Answers to Craft'S Petition for Leave to Intervene and Request for a Public Hearing |
ML14255A497 | 12 September 2014 | NRC Staff'S Answer to Don'T Waste Michigan, Citizens Environment Alliance of Southwestern Ontario and Beyond Nuclear'S Petition for Leave to Intervene and Request for Hearing |
ML14255A495 | 12 September 2014 | NRC Staff Answer to Craft Petition for Leave to Intervene and Request for Public Hearing |
ML14255A474 | 12 September 2014 | Applicant DTE Electric Company Answer Opposing Petitions to Intervene |
ML14248A308 | 10 September 2014 | Assignment of Project Managers within the U.S. Nuclear Regulatory Commission, Office of Nuclear Reactor Regulation, Japan Lessons-Learned Division |
ML14245A234 | 2 September 2014 | Mid-Cycle Assessment Letter for Fermi Power Plant, Unit 2 |
ML14245A386 | 29 August 2014 | NRDC V. NRC Et. Al., No. 13-1311 (Scheduled Oral Argument November. 21, 2014) |
ML14252A138 | 29 August 2014 | Comment (11) of Michael J. Keegan on Behalf of Don'T Waste Michigan on Fermi 2 Docket Id NRC-2014-0109 License Renewal Application |
NRC-14-0059, DTE Electric Company Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 28 August 2014 | DTE Electric Company Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
ML14231B142 | 18 August 2014 | Citizens' Resistance at Fermi 2 (Craft) Petition for Leave to Intervene and Request for Public Hearing Upon DTE Electric'S Request of 20-Year License Extension for the Enrico Fermi 2 Nuclear Reactor |
ML14246A599 | 14 August 2014 | Citizens Resistance at Fermi 2 (Craft) Corrected Petition for Leave to Intervene and Request for a Public Hearing Upon DTE Electric'S Request of 20-Year License Extension for the Enrico Fermi 2 Nuclear Reactor |
ML13338A612 | 26 March 2014 | G20130229 - 2.206 Petition Closure Letter Re Revoke Operating License for General Electric Mark I and Mark II Boiling Water Reactors |
ML14083A620 | 26 March 2014 | Nuclear Regulatory Commission Audits of Licensee Responses to Reliable Spent Fuel Pool Instrumentation Order EA-12-051 |
NRC-14-0001, DTE Electric Company Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 27 February 2014 | DTE Electric Company Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
ML13309B129 | 21 November 2013 | Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation |
NRC-13-0043, DTE Electric Company First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 26 August 2013 | DTE Electric Company First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
NRC-13-0042, Response to Request for Additional Information Regarding Overall Integrated Plan in Response to Order EA-12-051, Reliable Spent Fuel Pool Instrumentation. | 19 August 2013 | Response to Request for Additional Information Regarding Overall Integrated Plan in Response to Order EA-12-051, Reliable Spent Fuel Pool Instrumentation. |
ML13210A220 | 29 July 2013 | NRR E-mail Capture - Fermi 2 - Requests for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation |
NRC-13-0006, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 28 February 2013 | Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |