ML23200A1833 August 2023Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors
ML21071A10518 March 2021Transmittal of Final North Anna Power Station, Unit 1 - Accident Sequence Precursor Report (Licensee Event Report 338-20-001)
ML21071A1062 March 2021Final ASP Analysis - North Anna 1 Degraded Upper Piston Pin Bushing (LER 338-20-001)(Enclosure)
ML21056A55725 February 2021NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Final Supplemental Response
IR 05000338/20200035 November 2020Integrated Inspection Report 05000338/2020003 and 05000339/2020003 and Exercise of Enforcement Discretion
ML20309A60830 September 20206 to Updated Final Safety Analysis Report, Chapter 6, Engineered Safety Features
IR 05000338/201901013 August 2019Reissue - North Anna Power Station, Units 1 & 2 - Design Basis Assurance Inspection (Programs) Inspection Report 05000338/2019010 and 05000339/2019010
ML19225D1308 August 2019Response to Request for Additional Information (Follow-Up) Regarding Open Phase Protection Per NRC Bulletin 2012-01 - Proposed License Amendment Request
ML19199A17818 July 2019Design Basis Assurance Inspection (Teams) Inspection Report 05000338/2019010 and 05000339/2019010
ML18334A10619 November 2018Amendment for Flood Protection Dike Modification
IR 05000338/20180026 August 2018Nuclear Regulatory Commission Integrated Inspection Report 05000338/2018002 and 05000339/2018002
ML18093A44528 March 2018Ad 2, Response to 03/12/2012 Information Request Seismic Probabilistic Risk Assessment for Recommendation 2.1
ML20311A5016 November 20172017 Q1-Q4 ROP Inspection Findings
ML17241A04524 August 2017Proposed ISI Alternatives NI-14-NDE-010 and N2-14-NDE-005 Reactor Pressure Vessel Nozzle Weld Inspections Response to Request for Additional Information
ML17033B52529 September 2016Redacted Updated Final Safety Analysis Report Chapter 6
IR 05000338/201500312 November 2015IR 05000338/2015003 and 05000339/2015003, July 1, 2015 Through September 30, 2015, North Anna Power Station, Units 1 & 2, Routine Integrated Inspection Report
IR 05000338/20150026 August 2015IR 05000338/2015002, 05000339/2015002; on 04/01/2015 - 06/30/2015; North Anna Power Station, Units 1 and 2, Maintenance Effectiveness
ML13141A27815 May 2013NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors, Generic Safety Issue (GSI)-191 Closure Option and Tempmat Insulation..
ML13045A12426 February 2013Final Accident Sequence Precursor Analysis Results
IR 05000338/201200725 September 2012IR 05000338-12-007 & 05000339-12-007, 05/21/2012 - 08/15/2012; North Anna Power Station - NRC Component Design Bases Inspection
ML12005A0392 September 2011E-mail from G. Kolcum, Region II to S. Walker, Region II, Et Al; EDG New Info (Fuel Oil Line Rub) Discovered Last Night
ML1025716271 November 2010Issuance of Amendments 260 & 241 Regarding Change to Technical Specification (TS) 3.7.12, Emergency Core Cooling System (ECCS) Pump Room Exhaust Air Cleanup System (Preacs)
ML1021800727 July 2010Additional Clarification for Preacs
ML1021800696 July 2010Response to Precas Clarification Concerns from Phone Call
ML09282015530 September 2009Updated Final Safety Analysis Report, Revision 45, Chapter 6, Engineered Safety Features
ML09273046828 September 2009Proposed License Amendment Request, TS 3.7.12 - ECCS Pump Room Exhaust Air Cleanup System (Preacs) Addition of Conditions/Action Statements
ML0917610475 August 2009ECCS Preacs Filtration Presentation
ML09205038123 July 2009License Amendment Request, One Time Extension of the Completion Time for 1 J - 480 Volt AC Distribution Subsystem
ML09064103827 February 2009Updated Supplemental Response to NRC Generic Letter 2004-02 Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors
ML09021027915 January 2009Proposed License Amendment Request TS 3.7.12 - ECCS Pump Room Exhaust Air Cleanup System (Preacs) Addition of Conditions/Action Statements
ML08065056329 February 2008Supplemental Response to NRC GL-04-002, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors
ML07352024717 December 2007Proposed License Amendment Request, One-time Risk-Informed Extension to the Completion Time for EDG Fuel Oil Storage Tank Recoating
ML07274040015 November 2007Corrective Actions for Generic Letter 2004-02
ML0606900089 March 2006IR 05000338-05-004, & IR 0500339-05-004, - North Anna Power Station Units 1 & 2, Response to Disputed Minor Violation and Four Cross-cutting Aspects Contained in NRC Integrated
ML0603704639 February 2006RAI, Response to GL-2004-02, Potential Impact to Debris Blockage on Emergency Recirculation During Design-Basis Accidents at Pressurized-Water Reactors.
ML0535402689 December 2005Response to NRC Inspection Report Nos. 05000338-05-004 & 05000339-05-04
ML0530800503 November 2005Proposed Emergency Technical Specification Change One Time Extension of the Completion Time for the Low Head Safety Injection (Lhsi) Train a
ML05305039528 October 2005IR 05000338-05-004, IR 05000339-05-004; 07/01/2005 - 09/30/2005; North Anna Power Station Units 1 & 2. Routine Integrated Resident and Regional Report. Maintenance Effectiveness - Biennial Assessment. Emergency Preparedness Baseline. Radiat
ML04356033117 December 2004Proposed Technical Specifications Change Request Increased ECCS-LHSI. AFW, Quench Spray and Chemical Addition Systems Completion Times
ML04205045723 July 2004Proposed Emergency Technical Specification Change One Time Extension of the Completion Time for the Low Head Safety Injection (Lhsi) Train a
ML02360021713 December 2002Proposed Risk-Informed Technical Specifications Change Extended Inverter Allowed Outage Time
ML02338053627 November 2002Transmittal of RAI Responses for WCAP-15622, Risk-Informed Evaluation of Extensions to AC Electrical Power System Completion Times (MUHP-3010)
ML02333045727 November 2002Transmittal of RAI Responses for WCAP-15622, Risk-Informed Evaluation of Extensions to AC Electrical Power System Completion Times. (MUHP-3010)
ML20094D01325 October 1995Application for Amends to Licenses NPF-4 & NPF-7,re Allowed Outage Time for PORV Nitrogen Accumulators & Separate Actions for PORV Inoperability
ML20101E14931 August 1995TER on Individual Plant Exam Front End Analysis
ML20105A90031 August 1992Rev 2 to PRA North Anna Power Station Svc Water Preservation Project,Part One, Final Rept
ML18149A15916 May 1986Transmits,For Concurrence,Proposed Test Protocol for Demonstrating Acceptability of Using 35% Oxygen Enriched Breathing Air W/Open Circuit self-contained Breathing Apparatus.Concurrence Requested by 860731
ML20112J58731 March 1985Rev 1 to North Anna Power Station Svc Water Sys Probabilistic Safety Assessment
ML20112J58129 March 1985Application for Amends to Licenses NPF-4 & NPF-7,revising Tech Spec 3.7.4.1 to Extend Allowable Time for Inoperability of Redundant Svc Water Headers Beyond 72 H to Facilitate Mod & Maint Activities.Fee Paid