NL-21-0019, Response to Request for Additional Information Regarding Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors | 2 March 2021 | Response to Request for Additional Information Regarding Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors |
ML19238A341 | 11 October 2019 | Documentation of the Completion of Required Actions Taken in Response to the Lessons Learned from the Fukushima Dai-Ichi Accident - Supplemental Information |
ML18249A109 | 20 September 2018 | Documentation of the Completion of Required Actions Taken in Response to Fukushima Lessons Learned |
ML17331A410 | 24 January 2018 | Staff Assessment of Flooding Focused Evaluation (Public)(Cac Nos. MF9863 and MF9864; Epids 000495/05000348/L-2017-JLD-0043 and 000495/05000364/L-2017-JLD-0043) |
ML17192A452 | 18 July 2017 | Generic Audit Plan for 50.54(f) Flooding Focused Evaluation Responses |
ML17188A224 | 18 July 2017 | Flood Hazard Mitigation Strategies Assessment Redacted |
ML17090A457 | 24 April 2017 | Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders Ea-12-049 and Ea-12-051 (CAC Nos. MF0716, MF0717, MF1429, and MF1430) |
IR 05000348/2016004 | 27 January 2017 | NRC Integrated Inspection Report 05000348/2016004 and 05000364/2016004 |
NL-16-1431, Notification of Full Compliance of Required Action for NRC Order EA-12-049 Mitigation Strategies for Beyond-Design-Basis External Events | 13 December 2016 | Notification of Full Compliance of Required Action for NRC Order EA-12-049 Mitigation Strategies for Beyond-Design-Basis External Events |
ML16288A167 | 4 November 2016 | Staff Assessment of Response to 10 CFR 50.54(f) Information Request--Flood Causing Mechanism Reevaluation (CAC Nos. MF7039 and MF7040) - Public Redacted Version |
ML16132A482 | 7 June 2016 | Staff Review of Mitigation Strategies Assessment Report of the Impact of the Reevaluated Seismic Hazard Developed in Response to the March 12, 2012, 50.54(f) Letter |
NL-16-0622, NEI 12-06, Rev. 2, Appendix H.4.1 Path 1:GMRS SSE, Mitigating Strategies Assessment (MSA) Report | 27 April 2016 | NEI 12-06, Rev. 2, Appendix H.4.1 Path 1:GMRS SSE, Mitigating Strategies Assessment (MSA) Report |
ML15253A405 | 11 March 2016 | Enclosure 1 Seven Screening Criteria |
ML15253A410 | 11 March 2016 | Enclosure 2 Screening Analysis Report |
ML15253A403 | 11 March 2016 | Recommendation for Dispositioning Proposed Generic Issue on the Effects of Downstream Dam Failures on Nuclear Power Plants |
ML15343A418 | 10 December 2015 | Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10 CFR 50.54(f) Information Request - Flood Causing Mechanism Reevaluation |
ML15287A092 | 16 October 2015 | Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50 Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review |
ML15174A257 | 1 September 2015 | Letter to Licensees Coordination of Request for Information for Flooding Hazard Reevaluations and Mitigating Strategies for Beyond-Design-Basis External Events |
NL-15-0472, Second Response to Request for Additional Information from the U.S. Army Corps of Engineers to Support Flood Hazard Reevaluation | 13 March 2015 | Second Response to Request for Additional Information from the U.S. Army Corps of Engineers to Support Flood Hazard Reevaluation |
ML14303A465 | 21 November 2014 | Response Requirements for Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Flooding Hazard Integrated Assessments for Recommendation 2.1 of the Near-Term Task Force Review of Insights from t |
ML14174A938 | 17 July 2014 | Relaxation of Response Due Dates Regarding Flooding Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of the Insights from the Fukushima Dai-Ichi Accident |
ML14128A083 | 3 June 2014 | Staff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 |
ML14111A147 | 9 May 2014 | Seismic Screening and Prioritization Results Regarding Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of Insights |
NL-14-0732, Request for Additional Information from the U.S. Army Corps of Engineers to Support Flood Hazard Reevaluation, Recommendation 2.1 | 6 May 2014 | Request for Additional Information from the U.S. Army Corps of Engineers to Support Flood Hazard Reevaluation, Recommendation 2.1 |
ML14098A475 | 16 April 2014 | Unit 1 - Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident |
ML14101A119 | 16 April 2014 | Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident |
ML14070A475 | 14 April 2014 | Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events |
NL-14-0342, Units 1 and 2, Seismic Hazard and Screening Report for CEUS Sites | 31 March 2014 | Units 1 and 2, Seismic Hazard and Screening Report for CEUS Sites |
ML14083A620 | 26 March 2014 | Nuclear Regulatory Commission Audits of Licensee Responses to Reliable Spent Fuel Pool Instrumentation Order EA-12-051 |
NL-14-0249, Joseph M. Farley Nuclear Plant, Unit 1 - Updated Seismic Recommendation 2.3 Walkdown Report | 20 February 2014 | Joseph M. Farley Nuclear Plant, Unit 1 - Updated Seismic Recommendation 2.3 Walkdown Report |
ML14030A046 | 20 February 2014 | Letter from Eric J. Leeds Supplemental Information Related to Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Seismic Hazard Reevaluations for Recommendation 2.1 |
NL-14-0249, Enclosure 1, Updated Seismic Recommendation 2.3 Walkdown Report, Enclosure 2, Updated Farley Unit 1 Seismic Walkdown Report for Resolution of Fukushima Near-Term Force Recommendation 2.3: Seismic Through Attachment 2 | 20 February 2014 | Enclosure 1, Updated Seismic Recommendation 2.3 Walkdown Report, Enclosure 2, Updated Farley Unit 1 Seismic Walkdown Report for Resolution of Fukushima Near-Term Force Recommendation 2.3: Seismic Through Attachment 2 |
NL-14-0249, Joseph M. Farley, Unit 1, Enclosure 1, Updated Seismic Recommendation 2.3 Walkdown Report, Enclosure 2, Updated Farley Unit 1 Seismic Walkdown Report for Resolution of Fukushima Near-Term Force Recommendation 2.3: Seismic Through Attachme | 20 February 2014 | Joseph M. Farley, Unit 1, Enclosure 1, Updated Seismic Recommendation 2.3 Walkdown Report, Enclosure 2, Updated Farley Unit 1 Seismic Walkdown Report for Resolution of Fukushima Near-Term Force Recommendation 2.3: Seismic Through Attachment |
ML14051A734 | 20 February 2014 | Updated Seismic Recommendation 2.3 Walkdown Report |
ML13233A205 | 29 January 2014 | Response Regarding Licensee Dose Assessment Submittal Associated with Near-Term Task Force Recommendation 9.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident |
ML13337A584 | 17 January 2014 | Interim Staff Evaluation and Audit Report Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) |
ML14009A481 | 9 January 2014 | Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Joseph M. Farley Nuclear Plant, Units 1 and 2, TAC Nos.: MF0716 and MF0717 |
ML13233A183 | 23 October 2013 | Response Regarding Licensee Phase 1 Staffing Submittal Associated with Near Term Task Force Recommendation 9.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant |
NL-13-2123, Request to Obtain U. S. Army Corps of Engineers (Usace) Information Required to Provide Response to March 12, 2012 Request for Information, Recommendation 2.1 | 26 September 2013 | Request to Obtain U. S. Army Corps of Engineers (Usace) Information Required to Provide Response to March 12, 2012 Request for Information, Recommendation 2.1 |
NL-13-1555, Enclosure 2: Updated Farley Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic | 4 September 2013 | Enclosure 2: Updated Farley Unit 2 Seismic Walkdown Report for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic |
ML13233A364 | 23 August 2013 | Establishment of Mitigation Strategies Directorate for Nuclear Regulatory Commission Review of Order EA-12-049 |
ML13151A377 | 13 June 2013 | Impact of Fukushima-Related Activities on NRC Operating Reactor Regulatory and Licensing Reviews |
ML13044A561 | 1 March 2013 | Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Re Flooding Hazard Reevaluation for Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident |
NL-13-0213, Southern Nuclear Operating Co.'S Overall Integrated Plan in Response to 3/12/2012 Commission Order Modifying Licenses with Re to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) | 27 February 2013 | Southern Nuclear Operating Co.'S Overall Integrated Plan in Response to 3/12/2012 Commission Order Modifying Licenses with Re to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) |
IR 05000348/2012005 | 31 January 2013 | IR 05000348-12-005 and 05000364-12-005; 9/01/12, - 12/31/12; Joseph M. Farley Nuclear Plant; Integrated Report |
NL-13-0161, Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 1, Integrated Assessment Approach | 28 January 2013 | Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 1, Integrated Assessment Approach |
NL-12-2266, Joseph M. Farley, Unit 1, SNCF164-RPT-01, Version 1.0, Seismic Walkdown Report, Rer SNC432467 for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Cover - Attachment 3: Seismic Walkdown Checklists, Page 58 of 561 | 26 November 2012 | Joseph M. Farley, Unit 1, SNCF164-RPT-01, Version 1.0, Seismic Walkdown Report, Rer SNC432467 for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Cover - Attachment 3: Seismic Walkdown Checklists, Page 58 of 561 |
NL-12-2267, SNCF164-RPT-02, Ver. 1.0, Farley Unit 2 Seismic Walkdown Report, Rer SNC432467 for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Cover Through Page 46 of 46 | 26 November 2012 | SNCF164-RPT-02, Ver. 1.0, Farley Unit 2 Seismic Walkdown Report, Rer SNC432467 for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Cover Through Page 46 of 46 |
NL-12-2266, SNCF164-RPT-01, Version 1.0, Seismic Walkdown Report, Rer SNC432467 for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Cover - Attachment 3: Seismic Walkdown Checklists, Page 58 of 561 | 26 November 2012 | SNCF164-RPT-01, Version 1.0, Seismic Walkdown Report, Rer SNC432467 for Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, Cover - Attachment 3: Seismic Walkdown Checklists, Page 58 of 561 |
IR 05000348/2012004 | 30 October 2012 | Integrated Inspection Report 05000348-12-004 & 05000364-12-004 |