Semantic search

Jump to navigation Jump to search
 Issue dateFromTitleProject stage
ML18333A16717 December 2018John Lamb
Special Projects and Process Branch
Acceptance Review Letter, Review of Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost EstimateAcceptance Review
ML18331A12918 December 2018John Lamb
Special Projects and Process Branch
Letter, Notice of Receipt, Public Meeting, and Request for Comment on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost EstimateMeeting
ML18331A14918 December 2018Doug Broaddus
Special Projects and Process Branch
Federal Register Notice, Notice of Receipt, Public Meeting, and Request for Comment on Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost EstimateMeeting
ML19017A16215 January 2019
30 January 2019
Summary of 1/15/2019 Public Meeting Regarding Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report, Which Includes the Site-Specific Decommissioning Cost EstimateRequest
ML19017A17330 January 2019John Lamb
Special Projects and Process Branch
Summary of 1/15/2019 Public Meeting Regarding Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report, Which Includes the Site-Specific Decommissioning Cost EstimateMeeting
ML19031C8357 February 2019John Lamb
Special Projects and Process Branch
Corrected Transcript of Pilgrim Post-Shutdown Decommissioning Activities ReportOther
ML19031B8257 February 2019John Lamb
Special Projects and Process Branch
Transcript for Public Meeting Held on January 15, 2019, in Plymouth, Massachusetts Regarding Seabrook Nuclear Power Station Post-Shutdown Decommissioning Activities Report and License Transfer ApplicationMeeting
ML19031B9927 February 2019Transcript for Public Meeting Held on January 15, 2019, in Plymouth, Massachusetts Regarding Seabrook Nuclear Power Station Post-Shutdown Decommissioning Activities Report and License Transfer ApplicationRequest
CNRO-2019-00005, Stations - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc28 March 2019Entergy
Halter M
Stations - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, IncRequest
ML19239A03726 August 2019Entergy
Halter M
E-mail from Entergy Dated August 26, 2019, Notification of Pilgrim License TransferOther
ML19224A54028 October 2019Scott Wall
Plant Licensing Branch III
Review of Post-Shutdown Decommissioning Activities Report and Site-Specific Decommissioning Cost EstimateApproval