Issue date | Title | From | To | |
---|---|---|---|---|
NRC Generic Letter 1988-07 | 7 April 1988 | NRC Generic Letter 1988-007: Modified Enforcement Policy Relating to 10 CFR 50.49 Environmental Qualification of Electrical Equipment Important to Safety for Nuclear Power Plants. | Miraglia F Office of Nuclear Reactor Regulation | |
U-601217, Responds to Generic Ltr 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping. Revised Inservice Exam Program Plan Encl | 29 July 1988 | Responds to Generic Ltr 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping. Revised Inservice Exam Program Plan Encl | Hall D Illinois Power Company | NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM) |
ML20151M761 | 29 July 1988 | Rev 2 to Inservice Exam Program Plan | Illinois Power Company | |
IR 05000461/1989005 | 3 April 1989 | Insp Rept 50-461/89-05 on 890119-0323.No Violations Noted. Major Areas Inspected:Review of Programs,Procedures, Observation of Work Activities,Data Review,Mod Activities & Licensee Action on Info Notice 88-003 | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) Ward K Danielson D | |
ML20244D659 | 12 June 1989 | Requests Addl Info Re Response to Generic Ltr 88-01.Response Needed within 60 Days of Receipt of Ltr | John Hickman Office of Nuclear Reactor Regulation | Holtzscher D Illinois Power Company |
NRC Generic Letter 1989-21 | 19 October 1989 | NRC Generic Letter 1989-021: Request for Information Concerning Status of Implementation of Unresolved Safety Issue (USI) Requirements | Partlow J Office of Nuclear Reactor Regulation | |
ML20058K119 | 31 October 1989 | Technical Evaluation Rept on Response from Illinois Power Co to Generic Ltr 88-01 Pertaining to Clinton Power Plant, Final Rept | Bates R VIKING SYSTEMS INTERNATIONAL | NRC |
ML19332D503 | 27 November 1989 | Responds to Generic Ltr 89-21 Re Status of Implementation of USI Requirements.Results of Util Review & Reporting of Status of Implementation of USIs Encl | Holtzscher D Illinois Power Company | Office of Information Resources Management |
ML20006A829 | 23 January 1990 | Forwards Rev 3 to Inservice Exam Plan. Changes to Text Described.Approval of Changes by 900601 to Allow Time to Plan Refueling Outage Activities Re Inservice Exam Program Requested | Holtzscher D Illinois Power Company | Office of Information Resources Management |
NRC Generic Letter 1990-04 | 25 April 1990 | NRC Generic Letter 1990-004: Request for Information on Status of Licensee Implementation of Generic Safety Issues Resolved with Imposition of Requirements or Corrective Actions | Partlow J Office of Nuclear Reactor Regulation | |
ML20043G822 | 7 June 1990 | Provides Update to Util Response to Item 1 of Generic Ltr 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping. | Jamila Perry Illinois Power Company | Office of Information Resources Management |
NRC Generic Letter 1990-05 | 15 June 1990 | NRC Generic Letter 1990-005: Guidance for Performing Temporary Non-Code Repair of ASME Code Class 1, 2, and 3 Piping | Partlow J Office of Nuclear Reactor Regulation | |
ML20044B248 | 11 July 1990 | Proposed Tech Specs 4.0.5,3/4.4.3.1, RCS Leakage Detection Sys, 3/4.4.3.2, Operational Leakage, 3/4.8.3.1, Onsite Power Distribution Sys-Operating & 3/4.8.1.1, AC Sources - Operating. | Illinois Power Company | |
ML20059H067 | 24 August 1990 | SER Accepting Licensee Response to Generic Ltr 88-01, NRC Position on IGSCC in BWR Austentic Stainless Steel Piping, W/Exception of Licensee Position on Frequency of Leakage Monitoring | Office of Nuclear Reactor Regulation | |
ML20059H064 | 24 August 1990 | Advises That 880729 & 890921 Responses to Generic Ltr 88-01, IGSCC in BWR Austenitic Stainless Steel Piping, Acceptable W/Some Exceptions.Review of Exceptions Requested | John Hickman Office of Nuclear Reactor Regulation | Spangenberg F Illinois Power Company |
JSP-255-91, Suppls 880729 & 890921 Responses to Generic Ltr 88-01, IGSCC in BWR Austenitic Stainless Steel Piping to Resolve Open Items Re Classification of 50 Welds as Category a & Monitoring Leakage,Per Tech Spec Changes | 12 April 1991 | Suppls 880729 & 890921 Responses to Generic Ltr 88-01, IGSCC in BWR Austenitic Stainless Steel Piping to Resolve Open Items Re Classification of 50 Welds as Category a & Monitoring Leakage,Per Tech Spec Changes | Jamila Perry Illinois Power Company | Office of Information Resources Management |
U-601820, Proposed Tech Specs Re Operational Leakage & Reactor Coolant Leakage Detection Sys,In Response to Generic Ltr 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping | 7 May 1991 | Proposed Tech Specs Re Operational Leakage & Reactor Coolant Leakage Detection Sys,In Response to Generic Ltr 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping | Illinois Power Company | |
JSP-316-91, Suppls 900711 Application for Amend to License NPF-62,re Operational Leakage & Reactor Coolant Leakage Detection Sys, in Part,In Response to Generic Ltr 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping | 7 May 1991 | Suppls 900711 Application for Amend to License NPF-62,re Operational Leakage & Reactor Coolant Leakage Detection Sys, in Part,In Response to Generic Ltr 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping | Jamila Perry Illinois Power Company | Office of Information Resources Management |
ML20024H320 | 8 May 1991 | Inservice Insp Summary Rept. | John Miller Elkins P Stephen Bell Illinois Power Company | |
IR 05000461/1993020 | 23 December 1993 | Insp Rept 50-461/93-20 on 931006-1202.No Violations Noted. Major Areas Inspected:Review of Program,Procedures, Observation of Work Activities,Data Review & Evaluation & Review of Erosion/Corrosion Program | Jeffrey Jacobson NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) Schapker J | |
JSP-079-94, Application for Amend to License NPF-62,revising TS 3/4.4.3.1, RCS Leakage-Leakage Detection Sys, in Response to Inoperability of Drywell Floor Drain Sump Flow Rate Monitoring Instrumentation | 25 February 1994 | Application for Amend to License NPF-62,revising TS 3/4.4.3.1, RCS Leakage-Leakage Detection Sys, in Response to Inoperability of Drywell Floor Drain Sump Flow Rate Monitoring Instrumentation | Jamila Perry Illinois Power Company | Office of Information Resources Management |
U-602303, Application for Amend to License NPF-62,changing TS 3/4.4.3.1, Reactor Coolant Sys Leakage-Leakage Detection Sys | 20 June 1994 | Application for Amend to License NPF-62,changing TS 3/4.4.3.1, Reactor Coolant Sys Leakage-Leakage Detection Sys | Jackie Cook Illinois Power Company | Office of Information Resources Management |
U-602592, Requests NRC Evaluation of Util Revised Response to GL 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping, in Advance of Refueling outage-6 | 4 July 1996 | Requests NRC Evaluation of Util Revised Response to GL 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping, in Advance of Refueling outage-6 | Connell W Illinois Power Company | Office of Information Resources Management |
ML20137A102 | 10 July 1996 | Rev 5 to App IV Second 10-Yr Interval Inservice Exam Plan | WEC Energy Group | |
ML043380183 | 9 December 2004 | Commitment Audit | Pickett D NRC/NRR/DLPM/LPD3 | AmerGen Crane C |
RS-09-072, Relief Requests Associated with the Third Inservice Inspection Interval | 30 December 2009 | Relief Requests Associated with the Third Inservice Inspection Interval | Exelon Hansen J | Office of Nuclear Reactor Regulation Document Control Desk |
RS-10-008, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3) | 15 February 2010 | Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3) | Exelon Hansen J | Office of Nuclear Reactor Regulation Document Control Desk |
U-603958, Post-Outage 90-Day Inservice Inspection Summary Report | 6 May 2010 | Post-Outage 90-Day Inservice Inspection Summary Report | Exelon Kemper D | Office of Nuclear Reactor Regulation Document Control Desk |
RS-10-093, Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B | 21 May 2010 | Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B | Exelon Hansen J | Office of Nuclear Reactor Regulation Document Control Desk |
ML11269A018 | 12 October 2010 | ISI Program Plan Third Ten-Year Inspection Interval | ALION Science & Technology Corp Coleman S | Exelon Office of Nuclear Reactor Regulation |
U-604060, Post-Outage 90-Day Inservice Inspection (ISI) Summary Report | 21 March 2012 | Post-Outage 90-Day Inservice Inspection (ISI) Summary Report | Exelon Kemper D | Office of Nuclear Reactor Regulation Document Control Desk |
RS-13-009, Operational Requirements Manual (Orm) 2013 | 10 January 2013 | Operational Requirements Manual (Orm) 2013 | Exelon | Office of Nuclear Reactor Regulation |
RS-14-006, Updated Safety Analysis Report, Revision 16, CPS Operational Requirements Manual | 9 January 2014 | Updated Safety Analysis Report, Revision 16, CPS Operational Requirements Manual | Exelon | Office of Nuclear Reactor Regulation |
ML20105A277 | 31 March 2020 | 1 to Updated Safety Analysis Report, CPS Operational Requirements | Exelon | Office of Nuclear Reactor Regulation |
RS-21-063, Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements | 30 June 2021 | Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements | Exelon Simpson P | Office of Nuclear Reactor Regulation Document Control Desk |
U-604687, Post-Outage 90-Day Inservice Inspection (Isi) Summary Report | 21 January 2022 | Post-Outage 90-Day Inservice Inspection (Isi) Summary Report | Exelon Chalmers T | Office of Nuclear Reactor Regulation Document Control Desk |
ML22111A224 | 31 March 2022 | 2 to Updated Safety Analysis Report, Clinton Power Station Operational Requirements Manual (Orm) | Constellation | Office of Nuclear Reactor Regulation |