Semantic search

Jump to navigation Jump to search
 Issue dateSiteTitle
ML24032A1111 February 2024North AnnaOwner'S Activity Report for North Anna, Unit 2, Refueling Outage N2R29 - First Period of the Fifth ISI Interval
ML23311A2049 October 2023North AnnaAnnual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.d
ML23206A01626 September 2023Companion Proposed Rule: List of Approved Spent Fuel Storage Casks: Tn Americas, LLC, Standardized NUHOMS
ML23065A26618 May 2023Management Directive 12.8, NRC Defensive Counterintelligence Program
ML21132A17118 May 2023Management Directive 8.2, NRC Incident Response Program
ML23121A05917 May 2023Nomination of Tara Inverso to Serve as the Primary Member on the SLTPS-PAC
ML23082A16210 February 2023Triso-XComment (821) of Sue and John Morris on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Trisox Special Nuclear Material License
ML23053A2117 February 2023North AnnaOwner'S Activity Report
ML23031A32212 January 2023Comanche PeakComment (417) of Sue and John Morris on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Vistra Operations Company LLC; Comanche Peak Nuclear Power Plant, Units 1 and 2
ML22303A0199 October 2022North AnnaAnnual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.d
ML22255A01028 June 2022North AnnaOwner'S Activity Report
ML22153A32521 June 2022sessionabstract-th22
IR 015000035/202000214 June 202215000035
015000035
Notice of Violation and Proposed Imposition of Civil Penalty - $8,000 and Exercise of Enforcement Discretion, NRC Inspection Report 150-00035/2020-002 and Investigation Report 4-2021-005
ML22153A47114 June 202215000035Notice of Violation and Proposed Imposition of Civil Penalty - $8,000 and Exercise of Enforcement Discretion, NRC Inspection Report 150-00035/2020-002 and Investigation Report 4-2021-005
IA-21-069, Notice of Violation, NRC Investigation Report 4-2021-00514 June 202215000035Notice of Violation, NRC Investigation Report 4-2021-005
ML22143A98919 May 2022Palo VerdePV-2022-05-Post Exam Comments
IR 05000206/202140224 March 2022San OnofreNotice of Violation, NRC Inspection Report 05000206/2021402, 05000361/2021402, 05000362/2021402, and 07200041/2021401; and Investigation Report 4-2021-004- Public- Cover Letter
IR 015000046/202100118 March 202215000046
015000046
Northwest Inspection, Inc., Notice of Violation, NRC Inspection Report 15000046/2021001
ML22124A05010 March 2022RIC 2022 34th Regulatory Information Conference (RIC) Technical Session - TH22 Emergency Response During Covid-19: Lessons from Hurricane Ida -transcript
ML22140A36610 March 2022morriss-hv-th22-r2
ML22145A3738 March 2022morriss-th22-bio
ML22145A2818 March 2022Morriss-w15-Bio
IR 05000416/20210062 March 2022Grand GulfAnnual Assessment Letter for Grand Gulf Nuclear Station (Report 05000416/2021006)
ML22034A9962 February 2022San OnofreS. Morris Response to C. Langley-Questions About Moving Snf at San Onfre
ML21349B33715 December 2021Grand GulfNOV_EA-20-125 21-096 21-110_GG Combined Case
IA-20-054, Notice of Violation, NRC Investigation Report 4-2019-02115 December 2021Notice of Violation, NRC Investigation Report 4-2019-021
IA-21-049, Notice of Violation - NRC Investigation Report 4-2020-0166 December 2021Notice of Violation - NRC Investigation Report 4-2020-016
IR 015000042/202100126 November 202115000042
015000042
Notice of Violation and NRC Inspection Report 150-00042/2021-001
IR 05000416/202104018 November 2021Grand GulfNRC Supplemental Inspection Report 05000416/2021040 and Assessment Follow-Up Letter
IA-21-043, Notice of Violation, NRC Investigation Report 4-2020-02718 October 2021Grand GulfNotice of Violation, NRC Investigation Report 4-2020-027
IA-21-034, Notice of Violation, NRC Investigation Report 4-2020-00814 October 2021River BendNotice of Violation, NRC Investigation Report 4-2020-008
IR 05000458/202109130 September 2021River BendNotice of Violation and Proposed Imposition of $150,000 Civil Penalty, NRC Inspection Report 05000458/2021091 and Investigation Reports 4-2020-008, 4-2020-009, and 4-2020-019
IA-21-035, Notice of Violation, NRC Investigation Report 4-2020-01930 September 2021River BendNotice of Violation, NRC Investigation Report 4-2020-019
IR 05000416/20210051 September 2021Grand GulfMid-Cycle Inspection Plan Transmittal Letter for Grand Gulf Nuclear Station (Report 05000416/2021005)
ML21229A13917 August 2021Resident Inspector Telework Guidance
IR 05000498/202109024 May 2021South TexasNotice of Violation, NRC Inspection Report 05000498/2021090 and 05000499/2021090
IR 05000382/202109018 May 2021WaterfordNotice of Violation; NRC Inspection Report 05000382/2021090 and NRC Investigation Report 4-2017-033
IA-21-006, NOV IA-21-006 Waterford Hernandez18 May 2021WaterfordNOV_IA-21-006_Waterford_Hernandez
ML21127A28114 May 2021WaterfordNotice of Violation - NRC Investigation Report 4-2020-018
ML21091A2981 April 2021Email from Scott Morris to Paul Blanch April 1, 2021
IR 015000046/202000125 March 202115000046
015000046
Notice of Violation, NRC Inspection Report 15000046/2020001
ML21075A35716 March 2021Grand GulfPublic Webinar with Entergy Operations, Inc., to Discuss the Nrc'S 2020 Annual Assessment of Grand Gulf Nuclear Station
IR 05000528/20210904 March 2021Palo VerdeNotice of Violation; NRC Inspection Report 05000528/2021090, 05000529/2021090, and 05000530/2021090
ML21055A0083 March 2021Grand Gulf2020 Annual Assessment Letter
IR 05000498/202009123 February 2021South TexasEA-19-054, South Texas Project Electric Generating Station, Units 1 and 2, Notice of Violation, NRC Inspection Report 05000498/2020091; 05000499/2020091 and NRC Investigation Report 4-2017-034
IA-20-033, Notice of Violation, NRC Investigation Report 4-2017-03423 February 2021South TexasIA-20-033, Notice of Violation, NRC Investigation Report 4-2017-034
ML21028A73028 January 2021South TexasRegulatory Commission Enforcement ADR Agreement to Mediate
IA-20-050, Notice of Violation, NRC Investigation Report 4-2019-01211 January 2021Notice of Violation, NRC Investigation Report 4-2019-012
ML20323A03517 November 2020Palo VerdeConfirmatory Order Modifying License - Palo Verde Nuclear Generating Station
ML20253A3609 September 2020PilgrimWithdrawal of Pilgrim Nuclear Power Station from the Requirements of Confirmatory Order EA-17-132 and EA-17-153