L-23-051, Plan, Nineteenth Inservice Inspection Summary Report | 22 June 2023 | Plan, Nineteenth Inservice Inspection Summary Report | |
L-21-282, Proposed Inservice Inspection Alternative IR-063 | 5 January 2022 | Proposed Inservice Inspection Alternative IR-063 | Time of Discovery Weld Overlay Subsequent License Renewal Power Uprate |
L-21-017, Eighteenth Inservice Inspection Summary Report | 29 June 2021 | Eighteenth Inservice Inspection Summary Report | |
L-21-028, 10 CFR 50.55a Request Number SR-2, Revision 0, Snubber Testing Extension | 15 January 2021 | 10 CFR 50.55a Request Number SR-2, Revision 0, Snubber Testing Extension | Pandemic COVID-19 |
L-19-143, Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements | 17 April 2020 | Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements | Weld Overlay VT-2 Liquid penetrant Pressure Boundary Leakage Dissimilar Metal Weld |
L-19-257, Submittal of Perry Nuclear Power Plant Inservice Testing Programs | 13 February 2020 | Submittal of Perry Nuclear Power Plant Inservice Testing Programs | Safe Shutdown High Radiation Area Stroke time Post Accident Monitoring Nondestructive Examination Squib Surveillance Frequency Control Program Scram Discharge Volume Cold shutdown justification Power Operated Valves Scaffolding Grace period |
L-19-119, Seventeenth Inservice Inspection Summary Report | 26 June 2019 | Seventeenth Inservice Inspection Summary Report | Weld Overlay |
L-18-104, 10 CFR 50.55a Requests in Support of the Fourth 10-Year In-Service Testing Interval | 21 June 2018 | 10 CFR 50.55a Requests in Support of the Fourth 10-Year In-Service Testing Interval | Stroke time Grace period |
L-17-038, Submittal of Report of Facility Changes, Tests, and Experiments | 23 October 2017 | Submittal of Report of Facility Changes, Tests, and Experiments | |
L-17-072, Sixteenth Inservice Inspection Summary Report | 29 June 2017 | Sixteenth Inservice Inspection Summary Report | Nondestructive Examination VT-2 |
L-15-165, Fifteenth Inservice Inspection Summary Report | 22 July 2015 | Fifteenth Inservice Inspection Summary Report | |
L-14-105, Notification of Impracticality for the Third 10-Year Inservice Inspection Interval | 7 March 2014 | Notification of Impracticality for the Third 10-Year Inservice Inspection Interval | Scaffolding |
ML14043A108 | 12 February 2014 | Notification of Impracticality for the Third 10-Year Lnservice Inspection Interval | Scaffolding |
L-13-190, Fourteenth Inservice Inspection Summary Report | 9 August 2013 | Fourteenth Inservice Inspection Summary Report | |
L-11-260, Thirteenth Inservice Inspection Summary Report | 1 September 2011 | Thirteenth Inservice Inspection Summary Report | Non-Destructive Examination Hydrostatic Nondestructive Examination Squib VT-2 EVT-1 Liquid penetrant |
L-11-083, Submittal of Inservice Examination Plan | 28 March 2011 | Submittal of Inservice Examination Plan | Non-Destructive Examination Weld Overlay Hydrostatic Coatings Nondestructive Examination VT-2 Incorporated by reference Moisture barrier Earthquake EVT-1 Liquid penetrant Through-Wall Leak Fire Protection Program Dissimilar Metal Weld DM weld Scaffolding Grace period |
L-11-082, Submittal of Inservice Testing Programs | 25 March 2011 | Submittal of Inservice Testing Programs | Safe Shutdown High Radiation Area Stroke time Nondestructive Examination Squib Scram Discharge Volume Cold shutdown justification Power Operated Valves Scaffolding |
L-10-246, 10 CFR 50.55a Requests in Support of the Third 10-Year In-Service Inspection Interval | 24 January 2011 | 10 CFR 50.55a Requests in Support of the Third 10-Year In-Service Inspection Interval | VT-2 EVT-1 Through-Wall Leak Fire Protection Program |
L-09-197, Twelfth Inservice Inspection Summary Report | 5 August 2009 | Twelfth Inservice Inspection Summary Report | |
L-08-350, 10 CFR 50.55a Request Number PR-3, Inservice Testing Program | 18 February 2009 | 10 CFR 50.55a Request Number PR-3, Inservice Testing Program | |
L-08-270, Response to Request for Additional Information Regarding Relief Request IR-054, Revision 0 | 17 September 2008 | Response to Request for Additional Information Regarding Relief Request IR-054, Revision 0 | |
L-08-066, Inservice Inspection Program Relief Requests IR-043, Revision 1, IR-055, IR-056, and IR-057 | 20 February 2008 | Inservice Inspection Program Relief Requests IR-043, Revision 1, IR-055, IR-056, and IR-057 | High Radiation Area Nondestructive Examination VT-2 EVT-1 Dissimilar Metal Weld Scaffolding |
ML072250365 | 7 August 2007 | Submittal of Eleventh Inservice Inspection Summary Report | Hydrostatic Nondestructive Examination Squib VT-2 Liquid penetrant Dissimilar Metal Weld Scaffolding |
ML052230327 | 2 August 2005 | Owners Report for Inservice Inspections as Required by the Provisions of the ASME Code Rules | Non-Destructive Examination Hydrostatic Coatings Nondestructive Examination VT-2 Locked High Radiation Area |
ML032731423 | 28 August 2003 | Inservice Inspection Summary Report | Packing leak Non-Destructive Examination Hydrostatic Nondestructive Examination Squib VT-2 EVT-1 Liquid penetrant |