Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-02
ML20324A623
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 11/19/2020
From: Mccartney E
NextEra Energy Seabrook
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
SBK-L-20143
Download: ML20324A623 (2)


Text

NEXTera' November 19, 2020 EN~ SBK-L-20143 10 CFR 50.12 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington DC 20555-0001 RE: Seabrook Station Docket No. 50-443 Renewed Facility Operating License No. NPF-86 Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-02 References :

1. NextEra Energy Seabrook, LLC, Updated Final Response to NRC Generic Letter 2004-02 ,

January 31, 2018 (ADAMS Accession No. ML18031B248)

2. NextEra Energy Seabrook, LLC, Exemption Request to Support Updated Final Response to NRC Generic Letter 2004-02 , August 30 , 2018 (ADAMS Accession No. ML18243A043)

In Reference 1, NextEra Energy Seabrook, LLC (NextEra) submitted on behalf of Seabrook Station (Seabrook) an updated final response to NRC Generic Letter 2004-02 , "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors". In Reference 2, NextEra requested on behalf of Seabrook a limited exemption from the single failure criterion of 10 CFR 50, Appendix K, Section (l)(D)(1) in support of Reference 1.

Subsequent to the exemption request submittal, NextEra conducted additional testing and analyses relating to containment sump performance at Seabrook which renders this exemption from the single-failure criterion unnecessary. Therefore, NextEra hereby withdraws the exemption request of Reference 2. A supplement to Reference 1 reflecting the additional testing and analyses is being prepared for submittal in Spring 2021.

Should you have any questions regarding this submission, please contact Mr. Ken Browne, Safety Assurance and Learning Site Director, at 603-773-7932 .

Sincerely,

  1. 'YYI~

McCartney Site Director (VP) - Seabrook Nuclear Power Station NextEra Energy cc: USNRC Region I Administrator USN RC Project Manager USNRC Senior Resident Inspector Director Homeland Security and Emergency Management New Hampshire Department of Safety Division of Homeland Security and Emergency Management Bureau of Emergency Management 33 Hazen Drive Concord, NH 03305

Seabrook Station SBK-L-20143 Docket Nos. 50-443 Page 2 of 2 Katharine Cederberg, Lead Nuclear Planner The Commonwealth of Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399