Other: ML14049A197, ML15181A269, ML15278A200, SBK-L-12212, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049), SBK-L-13038, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), SBK-L-13039, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), SBK-L-13157, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, SBK-L-13158, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, SBK-L-14041, Second Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), SBK-L-14042, Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), SBK-L-14153, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), SBK-L-14154, Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No EA- 12-05 1), SBK-L-15025, NextEra Energy Seabrook, Llc'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-1, SBK-L-15026, NextEra Energy Seabrook, Llc'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), SBK-L-15137, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events..., SBK-L-15138, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), SBK-L-16011, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
|
MONTHYEARSBK-L-12212, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2012-10-26026 October 2012 Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) Project stage: Other SBK-L-13038, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-02-26026 February 2013 Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other SBK-L-13039, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-02-26026 February 2013 Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other SBK-L-13158, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other SBK-L-13157, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML13267A3882013-12-0404 December 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI ML14049A1972014-02-14014 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Seabrook Station, TAC No.: MF0836 Project stage: Other ML14030A5522014-02-25025 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Acceptance Review SBK-L-14041, Second Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-02-27027 February 2014 Second Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other SBK-L-14042, Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-27027 February 2014 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other SBK-L-14153, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-26026 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other SBK-L-14154, Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No EA- 12-05 1)2014-08-26026 August 2014 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No EA- 12-05 1) Project stage: Other SBK-L-15026, NextEra Energy Seabrook, Llc'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 NextEra Energy Seabrook, Llc'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other SBK-L-15025, NextEra Energy Seabrook, Llc'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12015-02-27027 February 2015 NextEra Energy Seabrook, Llc'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-0 Project stage: Other ML15181A2692015-07-0606 July 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-51 Project stage: Other SBK-L-15152, NextEra Energy Seabrook Llc'S Request for Schedule Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-07-23023 July 2015 NextEra Energy Seabrook Llc'S Request for Schedule Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request SBK-L-15137, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events...2015-08-26026 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events... Project stage: Other SBK-L-15138, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-08-27027 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML15244A0452015-10-0404 October 2015 Relaxation of the Scheduler Requirements of Order EA-12-049, Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events Project stage: Approval ML15278A2002015-10-28028 October 2015 Report for the Onsite Audit Regarding Implementation of Mitgating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 (TAC Nos. MF0836 and MF0837) Project stage: Other SBK-L-16011, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-02-11011 February 2016 Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other 2014-08-26
[Table View] |
|
---|
Category:Letter type:SBK
MONTHYEARSBK-L-23053, Radiological Emergency Plan (Ssrep), Revision 802023-06-22022 June 2023 Radiological Emergency Plan (Ssrep), Revision 80 SBK-L-23031, 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 2022 Annual Radioactive Effluent Release Report SBK-L-23044, 2022 Annual Radiological Environmental Operating Report2023-04-28028 April 2023 2022 Annual Radiological Environmental Operating Report SBK-L-23033, 2022 Annual Environmental Operating Report2023-04-11011 April 2023 2022 Annual Environmental Operating Report SBK-L-22093, 75 Day and 150 Day Submittal Letters2022-12-0101 December 2022 75 Day and 150 Day Submittal Letters SBK-L-22113, Radiological Emergency Plan (Ssrep), Revision 792022-11-16016 November 2022 Radiological Emergency Plan (Ssrep), Revision 79 SBK-L-22114, Independent Spent Fuel Storage Installation (Isfsi), Cask Registration2022-11-0909 November 2022 Independent Spent Fuel Storage Installation (Isfsi), Cask Registration SBK-L-22112, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2022-11-0303 November 2022 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration SBK-L-22094, Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2)2022-10-26026 October 2022 Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) SBK-L-22105, Supplement to 2021 Annual Radioactive Effluent Release Report2022-10-24024 October 2022 Supplement to 2021 Annual Radioactive Effluent Release Report SBK-L-22103, 5 to the Physical Security Plan, Training and Qualification Plan and Safeguards Contingency Plan2022-10-12012 October 2022 5 to the Physical Security Plan, Training and Qualification Plan and Safeguards Contingency Plan SBK-L-22102, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2022-10-0606 October 2022 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration SBK-L-22080, Submittal of 10 CFR 72.48 Report of Changes, Tests and Experiments for August 2020 to July 20222022-08-12012 August 2022 Submittal of 10 CFR 72.48 Report of Changes, Tests and Experiments for August 2020 to July 2022 SBK-L-22054, SBK-L-22054 - License Amendment Request 22-01, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-06-0909 June 2022 SBK-L-22054 - License Amendment Request 22-01, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections SBK-L-22044, 2021 Annual Radioactive Effluent Release Report2022-04-29029 April 2022 2021 Annual Radioactive Effluent Release Report SBK-L-22036, Steam Generator Tube Inspection Report2022-04-25025 April 2022 Steam Generator Tube Inspection Report SBK-L-22040, Radiological Emergency Plan (Ssrep), Revision 7822022-04-20020 April 2022 Radiological Emergency Plan (Ssrep), Revision 782 SBK-L-22024, Response to Request for Additional Information (Raj) Regarding License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2022-03-0707 March 2022 Response to Request for Additional Information (Raj) Regarding License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-22003, Inservice Inspection Examination Report2022-01-24024 January 2022 Inservice Inspection Examination Report SBK-L-21126, Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan2022-01-0404 January 2022 Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan SBK-L-21135, Submittal of Changes to the Seabrook Station Technical Specification Bases2021-12-29029 December 2021 Submittal of Changes to the Seabrook Station Technical Specification Bases SBK-L-21108, Core Operating Limits Report for Cycle 222021-11-0404 November 2021 Core Operating Limits Report for Cycle 22 SBK-L-21106, Transmittal of WCAP-18607-NP, Analysis of Capsule X from the NextEra Energy Seabrook Unit 1 Reactor Vessel Radiation Surveillance Program2021-09-30030 September 2021 Transmittal of WCAP-18607-NP, Analysis of Capsule X from the NextEra Energy Seabrook Unit 1 Reactor Vessel Radiation Surveillance Program SBK-L-21105, Withdrawal of Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink One-Time Allowed Outage Time (AOT) Extension2021-09-27027 September 2021 Withdrawal of Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink One-Time Allowed Outage Time (AOT) Extension SBK-L-21103, Request for Exercise of Enforcement Discretion2021-09-25025 September 2021 Request for Exercise of Enforcement Discretion SBK-L-21104, Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink Onetime Allowed Outage Time (AOT) Extension2021-09-25025 September 2021 Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink Onetime Allowed Outage Time (AOT) Extension SBK-L-21098, Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2021-09-22022 September 2021 Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-21083, NextEra Energy Seabrook, LLC - Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage2021-08-18018 August 2021 NextEra Energy Seabrook, LLC - Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage SBK-L-21067, License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2021-07-21021 July 2021 License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-21049, Revision to Updated Final Response to NRC Generic Letter 2004-022021-06-24024 June 2021 Revision to Updated Final Response to NRC Generic Letter 2004-02 SBK-L-21056, Response to Request for Additional Information Regarding Seabrook Steam Generator Tube Inspection Report Review References:2021-05-20020 May 2021 Response to Request for Additional Information Regarding Seabrook Steam Generator Tube Inspection Report Review References: SBK-L-21045, Submittal of 2020 Annual Radioactive Effluent Release Report2021-04-30030 April 2021 Submittal of 2020 Annual Radioactive Effluent Release Report SBK-L-21044, 2020 Annual Radiological Environmental Operating Report2021-04-30030 April 2021 2020 Annual Radiological Environmental Operating Report SBK-L-21042, Response to RIS 2021-01 Preparation and Scheduling of Operator Licensing Examinations2021-04-22022 April 2021 Response to RIS 2021-01 Preparation and Scheduling of Operator Licensing Examinations SBK-L-21033, Response to Request for Additional Information (RAI) Regarding License Amendment Request (LAR) 20-02, Resolve Non-Conservative Heat Flux Hot Channel Factor (Fo(Z)) Requirements2021-03-24024 March 2021 Response to Request for Additional Information (RAI) Regarding License Amendment Request (LAR) 20-02, Resolve Non-Conservative Heat Flux Hot Channel Factor (Fo(Z)) Requirements SBK-L-21023, Radiological Emergency Plan (Ssrep), Revision 772021-03-0404 March 2021 Radiological Emergency Plan (Ssrep), Revision 77 SBK-L-20154, Submittal of Changes to the Seabrook Station Technical Specification Bases2020-12-22022 December 2020 Submittal of Changes to the Seabrook Station Technical Specification Bases SBK-L-20149, Response to Request for Additional Information in Respect to One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-12-0808 December 2020 Response to Request for Additional Information in Respect to One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic SBK-L-20146, One-Time Exemption Request for the Biennial Emergency Preparedness Exercise Requirements of 10 CFR 50, Appendix E. IV.F.2.b and IV.F.2.c2020-12-0303 December 2020 One-Time Exemption Request for the Biennial Emergency Preparedness Exercise Requirements of 10 CFR 50, Appendix E. IV.F.2.b and IV.F.2.c SBK-L-20144, Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-23023 November 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic SBK-L-20143, Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-022020-11-19019 November 2020 Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-02 SBK-L-20132, Fourth Interval Inservice Testing (IST) Program2020-10-21021 October 2020 Fourth Interval Inservice Testing (IST) Program SBK-L-20127, Generator Tube Inspection Report2020-10-20020 October 2020 Generator Tube Inspection Report SBK-L-20117, Response to Request for Additional Information Regarding Technical Specification 3/4.8.1 for a One-Time Extension of Allowed Outage Time License Amendment Request2020-09-23023 September 2020 Response to Request for Additional Information Regarding Technical Specification 3/4.8.1 for a One-Time Extension of Allowed Outage Time License Amendment Request SBK-L-20103, Inservice Inspection Examination Report2020-07-27027 July 2020 Inservice Inspection Examination Report SBK-L-20092, Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-411 and TSTF-4182020-07-13013 July 2020 Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-411 and TSTF-418 SBK-L-20068, License Amendment Request 20-01, One-Time Change to the Seabrook Technical Specifications A.C. Sources - Operating2020-07-13013 July 2020 License Amendment Request 20-01, One-Time Change to the Seabrook Technical Specifications A.C. Sources - Operating SBK-L-20085, Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic2020-06-16016 June 2020 Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic SBK-L-20077, Core Operating Limits Report for Cycle 212020-06-0101 June 2020 Core Operating Limits Report for Cycle 21 SBK-L-20057, Response to Request for Additional Information Regarding Degraded Voltage Time Delay Setpoint License Amendment Request2020-05-20020 May 2020 Response to Request for Additional Information Regarding Degraded Voltage Time Delay Setpoint License Amendment Request 2023-06-22
[Table view] |
Text
NEXTerao ENERGY j SSEABROOK July 23, 2015 SBK-L-15152 Docket No. 50-443 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Seabrook Station NextEra Energy Seabrook LLC's Request for Schedule Relaxation from NRC Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events"
References:
- 1. NRC Order Number EA- 12-049, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," March 12, 2012 (ML12054A735)
- 2. NextEra Energy Seabrook LLC's letter to the NRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA 049)," February 26, 2013 (ML13063A438)
- 3. NextEra Energy Seabrook LLC's letter to the NRC, "Nextera Energy Seabrook, LLC's Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)", February 27, 2015 (ML15068A021)
This letter transmits a request for relaxation of the schedule requirements contained in Nuclear Regulatory Commission ("NRC" or "Commission") Order EA-12-049. On March 12, 2012, the NRC issued an Order (Reference 1) to NextEra Energy Seabrook, LLC (hereafter known as "Seabrook"). Reference 1 was immediately effective and directed Seabrook to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event.Section IV of NRC Order EA-12-049 (Reference 1) provides that the Director, Office of Nuclear Reactor Regulation may relax the requirements of this Order. Alýjwiý NextEra Energy Seabrook, LLC, P.O. Box 300, Lafayette Road, Seabrook, NH 03874
U.S. Nuclear Regulatory Commission SBK-L- 15 152/Page 2 In accordance with Section IV of NRC Order EA-12-049, NextEra is requesting that the Director, Office of Nuclear Reactor Regulation relax the requirement for completion of full implementation for Seabrook as prescribed in Section IV.A.2 of NRC Order EA-12-049, as described in the enclosure to this letter.
Seabrook considers that, upon approval by the NRC, the alternative full implementation dates regarding NRC Order EA- 12-049 proposed in the attachment will constitute a condition of the NRC Order EA-12-049 for Seabrook. Therefore, there are no new regulatory commitments contained in this letter.
If you have any questions regarding this report, please contact Mr. Michael Ossing, Licensing Manager, at (603) 773-7512.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on July 23 ,2015.
Sincerely, NextEra Energy Seabrook, LLC Dean Curtland Site Vice President Enclosure
U.S. Nuclear Regulatory Commission SBK-L- 15152/Page 3 cc: D. Dorman, NRC Region I Administrator J.G. Lamb, NRC Project Manager, Project Directorate 1-2 P. Cataldo, NRC Senior Resident Inspector Director, Office of Nuclear Reactor Regulation Ms. Jessica A. Kratchmann, NRR/JLD/PMB, NRC Mr. Eric E. Bowman, NRR/DPR/PGCB Director Homeland Security and Emergency Management New Hampshire Department of Safety Division of Homeland Security and Emergency Management Bureau of Emergency Management 33 Hazen Drive Concord, NH 03305 Mr. John Giarrusso, Jr., Nuclear Preparedness Manager The Commonwealth of Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399
Enclosure to SBK-L- 15152 Request for Schedule Relaxation from NRC Order EA-12-049, "Order Modifying Licenses with Regard to Reauirements for Mitigation Strategies for Bevond-Design-Basis External Events"
REQUEST FOR SCHEDULE RELAXATION OF NRC ORDER EA-12-049 REQUIREMENT IV.A.2 FOR NEXTERA ENERGY SEABROOK, LLC Relaxation Request:
Pursuant to the procedure specified in Section IV of Nuclear Regulatory Commission (NRC)
Order EA-12-049, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (Reference 1), NextEra Energy Seabrook, LLC (hereafter known as "Seabrook") hereby submits a request for schedule relaxation from the Order requirements for completion of full implementation, from November 2015 to May 30, 2016.
Order Requirement from Which Relaxation is Requested:
NRC Order EA- 12-049,Section IV.A.2 requires completion of full implementation of the Order requirements no later than two (2) refueling cycles after submittal of the Overall Integrated Plan (OIP), as required by Condition C.1 .a, or December 31, 2016, whichever comes first. In accordance with the requirements of the Order, Seabrook submitted the Seabrook Mitigation Strategies Overall Integrated Plan (Reference 2) on February 26, 2013. The Seabrook Mitigation Strategies Overall Integrated Plan milestone schedule identified the planned completion date for full implementation of NRC Order EA-12-049 as November 2015.
Justification for Relaxation Request:
Seabrook's original strategy employed the Supplemental Electrical Power System (SEPS), a permanently installed set of two diesel generators and supporting equipment, and the Service Water Cooling Tower, a redundant ultimate heat sink (refer to the original OIP in Reference 2).
Following loss of all AC power and normal access to the normal ultimate heat sink, the SEPS would provide AC power to an emergency bus, and the Cooling Tower would then provide cooling to critical loads. This strategy will continue to be employed in every situation where the SEPS and Cooling Tower are available. However, the SEPS and Cooling Tower are not fully protected from the entire spectrum of high wind events, including wind driven missiles. Due to the potential vulnerability of the SEPS and Cooling Tower to this small subset of possible Beyond Design Basis External Events (BDBEEs), a second set of strategies was developed to ensure that all possible BDBEEs can be addressed. These strategies add a complete set of fully protected portable equipment capable of complying with NEI 12-06, independent of SEPS. This plan offers significantly more diversity than simply adding protection to the SEPS and the Cooling Tower. The new set of strategies requires the development and implementation of additional modifications, procedures, and training that were not originally planned when the strategies relied solely on the SEPS and the Cooling Tower. The new strategies were transmitted to the NRC on February 27, 2015 as part of NextEra Energy Seabrook LLC's fourth six-month status report.
Page 1 of 4
The original schedule for implementation of Fukushima strategies allowed 33 months from the time the OIP was submitted to the planned completion in November 2015. November 2015 is the planned end of the second refueling outage after transmittal of the original OIP. From the time of transmittal of the revised OIP in February 2015, the November 2015 due date allows only 9 months to develop and implement the new plan. This implementation time frame is extremely short given the work required to:
- Develop and implement modifications
- Specify, procure and test new portable equipment
" Develop, review and approve new procedures
" Train on the new equipment and procedures Many efforts are being performed as parallel activities (worked at risk) to reduce the overall implementation duration. Seabrook has used knowledge of other plant's programs, procedures, and experiences to further expedite this effort. By the end of the upcoming refueling outage in November 2015, completed modification efforts are expected to include:
" All outage required FLEX modifications including RCP seals.
- U2 Circulating Water Piping Cistern completion and fill.
- ESF Bus 5 and 6 connections for the NSRC generators.
- SG and RCS makeup connections.
" Refueling strategy pumps installation in the Diesel Generator fuel tank rooms.
- Seismic hardening of the SEPS.
FLEX portable equipment is expected to be received on site, tested, and incorporated into the Seabrook PM Program. This equipment includes:
- 405 kW diesel generator and associated cables
- Flex Low Pressure Pump and associated hose 0 Flex High Pressure Pump and associated hose
- Flex Debris Removal and Towing Tractors
- Flex sump pump (to provide water from the U2 Circulating Water Piping Cistern) 0 Refueling tanker trailer Per our current schedule, by the end of the November refueling outage all procedures and program documents will be completed, reviewed, validated, and ready for issuance. All planned training will be complete. Site staffing will be consistent with the site staffing study. The National SAFER Response Centers will be in place and ready to support Seabrook mitigating strategies.
The compressed time frame is challenging project completion. Current items at risk are:
a) Completion of the modifications to the Service Water Pumphouse to allow its use as the fully protected storage location for the majority of the portable site FLEX equipment.
b) Completing validation and verification of strategies with respect to equipment stored in the Service Water Pumphouse.
While not expected, emergent issues may challenge other specific project initiatives.
Page 2 of 4
Due to these challenges it is not expected that Seabrook will achieve full implementation of the mitigation strategies in accordance with NRC Order EA- 12-049, by the Order requirement date of no later than two (2) refueling cycles after submittal of the overall integrated plan as required by Condition C. 1a, or December 31, 2016, whichever comes first. Accordingly, Seabrook requests that the NRC Order EA-12-049,Section IV.A.2, full implementation requirement date for Seabrook be relaxed to May 30, 2016. Due to the integrated nature of the Seabrook mitigation strategies, partial functional scope compliance is not feasible. Fukushima procedures will be available but not issued until field implementation is complete.
The schedule relaxation for Seabrook results in extending the Seabrook site implementation date seven months from November 2015 to May 30, 2016, which continues to meet the December 31, 2016 backstop date of NRC Order EA-12-049.
There is little risk to safety for this delay for the following reasons:
a) The extension is short, and still within the limiting date of December 31, 2016.
b) Existing procedures direct operation of the SEPS and Cooling Tower, and personnel are already trained in their operation. This equipment can address the vast majority of BDBEE events.
c) Until completion of the Service Water Pumphouse modifications, major portable site FLEX equipment will be stored more than 1200 feet from the SEPS equipment to achieve a measure of protection by spatial separation.
d) SAFER support will be available to provide equipment if required.
e) Final implementation will occur prior to the next hurricane season, reducing the risk of a high wind event.
f) Additionally, the following efforts are planned to be completed prior to the original implementation date:
- a. SEPS seismic hardening to ensure its availability following a seismic event.
- b. U2 Circulating Water Piping Cistern completion and filling, providing a protected alternate feed source for the steam generators.
- c. Major site FLEX equipment receipt and testing, and training of personnel on the use of this equipment.
It should be noted that when this project is complete, Seabrook safety will be enhanced by the diversity of its Fukushima strategies as compared to strategies relying on two sets of redundant equipment.
Conclusion:
As described above, compliance with the NRC Order EA-12-049 schedule requirement for full completion of implementation of mitigation strategies is not expected to be achievable due to the inability to complete all required modifications in the compressed time frame that resulted from the recent significant change in strategy to improve overall safety. Therefore, in accordance with the provisions of Section IV of the Order, NextEra requests relaxation of the requirement described in Section IV.A.2 by extension of the completion date for full implementation to May 30, 2016.
Page 3 of 4
References:
- 1. NRC Order Number EA- 12-049, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," March 12, 2012 (ML12054A735)
- 2. NextEra Energy Seabrook LLC's letter to the NRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"
February 26, 2013 (ML13063A438)
- 3. NextEra Energy Seabrook LLC's letter to the NRC, "Nextera Energy Seabrook, LLC's Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)", February 27, 2015 (ML15068A021)