Response to Request for Additional Information - Exemption from 10CFR20.1703 and 10CFR20 Appendix a Use of Delta Protection French Designed Respiratory Protection EquipmentML043420081 |
Person / Time |
---|
Site: |
Dresden, Peach Bottom, Oyster Creek, Byron, Three Mile Island, Braidwood, Limerick, Clinton, Quad Cities, LaSalle, 07201027 ![Constellation icon.png](/w/images/b/be/Constellation_icon.png) |
---|
Issue date: |
12/07/2004 |
---|
From: |
Gallagher M AmerGen Energy Co, Exelon Generation Co |
---|
To: |
Document Control Desk, Office of Nuclear Reactor Regulation |
---|
References |
---|
2130-04-20298, 5928-04-20254, RS-04-177 |
Download: ML043420081 (8) |
|
Similar Documents at Dresden, Peach Bottom, Oyster Creek, Byron, Three Mile Island, Braidwood, Limerick, Clinton, Quad Cities, LaSalle, 07201027 |
---|
Category:Letter type:RS
MONTHYEARRS-24-004, Proposed Alternative to the Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators2024-01-11011 January 2024 Proposed Alternative to the Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators RS-24-001, Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2024-01-0303 January 2024 Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-128, Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-15015 December 2023 Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-121, Sixth Ten-Year Interval Inservice Testing Program2023-11-30030 November 2023 Sixth Ten-Year Interval Inservice Testing Program RS-23-104, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-120, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information RS-23-119, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information RS-23-118, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information RS-23-117, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information RS-23-107, Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-11-0808 November 2023 Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-114, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2023-11-0101 November 2023 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds RS-23-113, Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 262023-10-20020 October 2023 Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 26 RS-23-102, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-100, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-103, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections RS-23-093, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel.2023-09-29029 September 2023 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel. RS-23-094, Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 752023-09-29029 September 2023 Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 75 RS-23-091, Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals2023-09-26026 September 2023 Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals RS-23-090, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2023-09-0707 September 2023 Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station RS-23-089, Sixth Ten-Year Interval Inservice Testing Program2023-09-0505 September 2023 Sixth Ten-Year Interval Inservice Testing Program RS-23-071, Application to Adopt TSTF-564, Safety Limit MCPR2023-08-30030 August 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-086, Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-08-28028 August 2023 Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-081, Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2023-08-21021 August 2023 Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor RS-23-085, Supplemental Information Related to Request for Partial Site Release2023-08-0303 August 2023 Supplemental Information Related to Request for Partial Site Release RS-23-084, Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis2023-07-24024 July 2023 Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-078, Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times2023-06-16016 June 2023 Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-074, Supplement to Application for License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2023-06-0909 June 2023 Supplement to Application for License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-23-060, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2023-06-0808 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors RS-23-059, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0808 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b RS-23-073, Request for Partial Site Release2023-06-0707 June 2023 Request for Partial Site Release RS-23-075, Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process2023-06-0707 June 2023 Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. RS-23-070, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-05-16016 May 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel RS-22-067, 10 CFR 50.46 Annual Report2023-05-0404 May 2023 10 CFR 50.46 Annual Report RS-23-068, Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell2023-04-28028 April 2023 Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell RS-23-058, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges2023-04-24024 April 2023 Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges RS-23-056, Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 102023-04-20020 April 2023 Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 10 RS-23-057, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-04-17017 April 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel RS-23-055, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2023-04-10010 April 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-23-052, License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2023-03-24024 March 2023 License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations 2024-01-03
[Table view] |
Text
iM 8 www.exeloncorp.com An Exelon Company AmeTCen Energy Company, LLC r
4300 Winfield Road Exelon Generation Warrenville, IL 60555 4300 Winfield Road Warrenville, IL 60555 10CFR20.2301 RS-04-177 5928-04-20254 2130-04-20298 December 7,2004 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457 Byron Station, Units 1 and 2 Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-454 and STN 50-455 Clinton Power Station, Unit 1 Facility Operating License No. NPF-62 NRC Docket No. 50-461 Dresden Nuclear Station, Units 1, 2 and 3 Facility Operating License Nos. DPR-2, DPR-19 and DPR-25 NRC Docket Nos. 50-10, 50-237, 50-249 and 72-37 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-11 and NPF-18 NRC Docket Nos. 50-373 and 50-374 Limerick Generating Station, Units 1 and 2 Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353 Oyster Creek Generating Station Facility Operating License No. DPR-16 NRC Docket Nos. 50-219 and 72-15 Peach Bottom Atomic Power Station, Units 1, 2 and 3
'Facility Operating License Nos. DPR-12, DPR-44 and DPR-56 NRC Docket Nos. 50-171, 50-277, 50-278 and 72-1027
US. Nuclear Regulatory Commission December 7,2004 Page 2 of 3 Quad Cities Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254. 50-265 Three Mile Island Nuclear Station, Unit 1 Facility Operating License No. DPR-50 NRC Docket No. 50-289
Subject:
Response to Request for Additional Information - Exemption from 10CFR20.1703 and 10CFR20 Appendix A Use of Delta Protection French Designed Respiratory Protection Equipment
Reference:
(1) Letter from M. P. Gallagher (Exelon/AmerGen) to USNRC, Request for Exemption from 10CFR20.1703 and 10CFR20 Appendix A Use of Delta Protection French Designed Respiratory Equipment, dated October 15, 2004 This letter provides additional information, as discussed on November 23, 2004, regarding the Exelon Generation Company, LLC (Exelon) and AmerGen Energy Company, LLC (AmerGen) request for exemption to allow use of the Delta Protection French-Designed suits as respiratory protection equipment. The Exelon/AmerGen request for exemption from the requirements of 10CFR20.1703 and 10CFR20 Appendix A was previously provided in Reference 1. Enclosed is a detailed response to the NRC request for additional information.
Regulatory commitments as a result of this submittal are identified in Enclosure 2. If any additional information is needed, please contact Mr. David J. Distel at (610) 765-5517.
Very truly yours, Michael P. Gallagher Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC and AmerGen Energy Company, LLC
Enclosures:
(1) Response to Request for Additional Information (2) Regulatory Commitments
U.S. Nuclear Regulatory Commission December 7,2004 Page 3 of 3 cc: Regional Administrator - NRC Region I Regional Administrator - NRC Region I l l NRC Project Manager, NRR - Braidwood Station NRC Project Manager, NRR - Byron Station NRC Project Manager, NRR - Clinton Power Station NRC Project Manager, NRR - Dresden Nuclear Power Station NRC Project Manager, NRR - LaSalle County Station NRC Project Manager, NRR - Limerick Generating Station NRC Project Manager, NRR - Oyster Creek Generating Station NRC Project Manager, NRR - Peach Bottom Atomic Power Station NRC Project Manager, NRR - TMI Unit 1 NRC Project Manager, NRR - Quad Cities Nuclear Power Station NRC Senior Resident Inspector - Braidwood Station NRC Senior Resident Inspector - Byron Station NRC Senior Resident Inspector - Clinton Power Station NRC Senior Resident Inspector - Dresden Nuclear Power Station NRC Senior Resident Inspector - LaSalle County Station NRC Senior Resident Inspector - Limerick Generating Station NRC Senior Resident Inspector - Oyster Creek Generating Station NRC Senior Resident Inspector - Peach Bottom Atomic Power Station NRC Senior Resident Inspector - TMI Unit 1 NRC Senior Resident Inspector - Quad Cities Nuclear Power Station Illinois Emergency Management Agency - Division of Nuclear Safety Director, Bureau of Radiation Protection - Pennsylvania Department of Environmental Resources Director, Bureau of Nuclear Engineering, New Jersey Department of Environmental Protection Chairman, Board of County Commissioners of Dauphin County, PA Chairman, Board of Supervisors of Londonderry Township, PA Mayor of Lacey Township, Forked River, NJ R. I. McLean, State of Maryland R. R. Janati, Commonwealth of Pennsylvania K. Jabbour, NRC Project Manager, NRR - (ExelodAmerGen Fleet)
ENCLOSURE 1 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION
Enclosure 1 Response to RAI Page 1 of 2
- 1. NRC Question Based on a review of the attachments provided in the licensees submittal, the manufacturer states (and the European Certification Authority assumes) that both models of the suits are authorized for single-use only. Please confirm that the suit will be discarded after one use.
Response
Exelon/AmerGen procedures will be revised to include guidance to ensure appropriate suit disposal after each use.
- 2. NRC Question While the licensee has established a useful communication with the vendor for suit improvements and lessons learned from other users, it is vital that the vendor establish and alert each product user (licensee) to any significant problems or deficiencies with the suit, similar to the warning/alert system required by NIOSH in the United States.
Verify that Exelon and AmerGen have committed to timely reporting of any defects experienced with these suits to the manufacturer and other U.S. users.
Response
The vendor has committed to report product issues on a quarterly basis. Upon discovery of manufacturer defects or usage problems identified by Exelon/AmerGen, the problem will be entered into the Exelon/AmerGen corrective action program. The Exelon/AmerGen corrective action program will enter identified manufacturer defects or significant usage problems into an Operating Experience Report issued to the nuclear power industry via the INPO Nuclear Network. Additionally, procedural guidance will be established to ensure that Exelon/AmerGen identified defects and usage problems are reported to the suit manufacturer.
- 3. NRC Question While the licensees committed to use the manufacturers information in developing implementing procedures (and training lesson plans) for using the suits, please identify any of the manufacturers instructions for donning and removal, instructions for use and emergency features technical information/directions provided, that will not be required by procedures. For each instruction identified, explain the rationale for not including it in the programs procedures/training (and any other compensating actions).
Response
Exelon/AmerGen intends to adhere to all of the manufacturers instructions for donning and removal, instructions for use, and emergency features technical information/directions provided, with one exception. Exelon/AmerGen will not Response to RAI Page 2 of 2 incorporate the instructions for donning and removal, Attachment 2.5.5, Caution Step 2, which states, The buddy system must be in effect with the use of this suit fed with a sufficient breathable air source with either both persons in it or the second person nearby in view with a particulate respirator ready. The inherent safety features of this suit (mouth and wrist tear-away strips), combined with the use of headsets for communication and remote video monitoring, make the use of a stand-by rescue person or buddy system unnecessary. Additionally, it is noted that Exelon/AmerGen standard practice is to have individuals standing by to assist workers in removing the suits.
- 4. NRC Question The submittal requests Exelon/AmerGen fleet approval for 10 CFR Part 50 and Part 72 licenses. Briefly describe how the respiratory protection suits will be used for Part 72 licenses.
ResDonse Use of these suits at the ExelonlAmerGen sites that have 10 CFR Part 72 licenses will primarily include usage, if needed, for activities around the spent fuel pool involving spent fuel cask evolutions in support of Independent Spent Fuel Storage Installation activities.
ENCLOSURE 2 REGULATORY COMMITMENTS
Enclosure 2 Page 1 of 1 List of Requlatory Commitments COMMITMENTS COMMITFED DATE Procedural guidance will ensure appropriate February 1, 2005, upon NRC approval.
suit disposal after each use.
Procedural guidance will be established to February 1,2005, upon NRC approval.
ensure Exelon/AmerGen identified defects and usage problems are reported to the suit manufacturer.
All of the manufacturers instructions for February 1,2005, upon NRC approval.
donning and removal, instructions for use, and emergency features technical information/directions provided will be adhered to, with the exception of instructions for donning and removal, Attachment 2.5.5, Caution Step 2.