MONTHYEARRNP-RA/21-0035, Duke Energy Progress, Inc - Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-18018 February 2021 Duke Energy Progress, Inc - Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report RNP-RA/20-0234, Independent Spent Fuel Storage Installation, Registration of Use of Spent Fuel Casks2020-07-23023 July 2020 Independent Spent Fuel Storage Installation, Registration of Use of Spent Fuel Casks RNP-RA/20-0199, Registration of Use of Spent Fuel Casks2020-06-25025 June 2020 Registration of Use of Spent Fuel Casks RNP-RA/18-0063, Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal2018-11-29029 November 2018 Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal RNP-RA/18-0060, Transmittal of Core Operating Limits Report2018-10-17017 October 2018 Transmittal of Core Operating Limits Report RNP-RA/18-0050, Response to Supplemental Request for Additional Information Regarding License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Change2018-08-0101 August 2018 Response to Supplemental Request for Additional Information Regarding License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Change RNP-RA/18-0044, Supplement to License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transform2018-07-11011 July 2018 Supplement to License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transformers RNP-RA/18-0039, Transmittal of Emergency Procedure Revisions and 10 CFR 50.54(q) Summary of Analysis2018-06-27027 June 2018 Transmittal of Emergency Procedure Revisions and 10 CFR 50.54(q) Summary of Analysis RNP-RA/18-0041, Independent Spent Fuel Storage Installation - Register as User for Cask2018-06-13013 June 2018 Independent Spent Fuel Storage Installation - Register as User for Cask RNP-RA/18-0036, Response to Request for Additional Information (RAI) Regarding Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use ...2018-05-16016 May 2018 Response to Request for Additional Information (RAI) Regarding Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use ... RNP-RA/18-0029, Submittal of 2017 Annual Radiological Environmental Operating Report2018-05-0808 May 2018 Submittal of 2017 Annual Radiological Environmental Operating Report RNP-RA/18-0031, (Hbrsep), Unit 2 - 2017 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Revision 352018-04-23023 April 2018 (Hbrsep), Unit 2 - 2017 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Revision 35 RNP-RA/18-0015, Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequently Requirements to a Licensee Controlled Program2018-04-16016 April 2018 Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequently Requirements to a Licensee Controlled Program RNP-RA/18-0024, Report of Changes Pursuant to 10 CFR 50.59(d)(2)2018-04-0202 April 2018 Report of Changes Pursuant to 10 CFR 50.59(d)(2) RNP-RA/18-0020, Notification of Change in Licensed Operator Status2018-02-20020 February 2018 Notification of Change in Licensed Operator Status RNP-RA/18-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2018-01-23023 January 2018 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report RNP-RA/17-0085, Request for Additional Information Regarding Application to Revise Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2018-01-0808 January 2018 Request for Additional Information Regarding Application to Revise Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0086, Transmittal of Emergency Procedure Revision and 10 CFR 50.54(q) Summary of Analyses2017-12-14014 December 2017 Transmittal of Emergency Procedure Revision and 10 CFR 50.54(q) Summary of Analyses RNP-RA/17-0081, Submittal of Change in Licensed Operators Medical Status2017-12-11011 December 2017 Submittal of Change in Licensed Operators Medical Status RNP-RA/17-0079, Operator License Renewal Application2017-12-0707 December 2017 Operator License Renewal Application RNP-RA/17-0071, Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License Spent Fuel Casks2017-10-19019 October 2017 Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License Spent Fuel Casks RNP-RA/17-0068, Response to NRC Request for Additional Information Related to License Amendment Request Regarding Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2017-09-28028 September 2017 Response to NRC Request for Additional Information Related to License Amendment Request Regarding Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0037, License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specifications 3.8.1, AC Sources-Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transformers2017-09-27027 September 2017 License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specifications 3.8.1, AC Sources-Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transformers RNP-RA/17-0043, Relief Request (RR)-12 for Relief from Volumetric/Surface Examination Frequency Requirements of ASME Code Case N-729-42017-09-22022 September 2017 Relief Request (RR)-12 for Relief from Volumetric/Surface Examination Frequency Requirements of ASME Code Case N-729-4 RNP-RA/17-0065, Refueling Outage 30 Steam Generator Tube Inspection Report2017-09-18018 September 2017 Refueling Outage 30 Steam Generator Tube Inspection Report RNP-RA/17-0060, Notification of Change in Licensed Operator Status2017-08-10010 August 2017 Notification of Change in Licensed Operator Status RNP-RA/17-0058, Notification of Change in Licensed Operator Status2017-08-0303 August 2017 Notification of Change in Licensed Operator Status RNP-RA/17-0055, Transmittal of Core Operating Limits Report for Cycle 312017-07-26026 July 2017 Transmittal of Core Operating Limits Report for Cycle 31 RNP-RA/17-0042, Submittal of the PWROG-14048-P, Revision 1, to Satisfy the Regulatory Commitment Related to the Pressurized Water Reactor Internals Program Plan for Aging Management of Reactor Internals2017-06-29029 June 2017 Submittal of the PWROG-14048-P, Revision 1, to Satisfy the Regulatory Commitment Related to the Pressurized Water Reactor Internals Program Plan for Aging Management of Reactor Internals RNP-RA/17-0051, Submittal of Nine Day Inservice Inspection Summary Report2017-06-29029 June 2017 Submittal of Nine Day Inservice Inspection Summary Report RNP-RA/17-0041, Transmittal of Technical Specifications Bases Revisions2017-05-23023 May 2017 Transmittal of Technical Specifications Bases Revisions RNP-RA/17-0038, (Hbrsep), Unit No. 2 - 2016 Annual Radiological Environmental Operating Report2017-05-0909 May 2017 (Hbrsep), Unit No. 2 - 2016 Annual Radiological Environmental Operating Report RNP-RA/17-0034, Modification of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544)2017-05-0202 May 2017 Modification of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544) RNP-RA/17-0036, (Hbrsep), Unit No. 2 - 2016 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Current Revision 342017-04-25025 April 2017 (Hbrsep), Unit No. 2 - 2016 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual, Current Revision 34 RNP-RA/17-0031, Provides Additional Information Regarding License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler 522, Revision 02017-04-20020 April 2017 Provides Additional Information Regarding License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler 522, Revision 0 RNP-RA/17-0033, Flood Hazard Mitigating Strategies Assessment (MSA) Report Submittal2017-04-12012 April 2017 Flood Hazard Mitigating Strategies Assessment (MSA) Report Submittal RNP-RA/17-0014, Resubmittal of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2017-04-0303 April 2017 Resubmittal of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0028, Submittal of Engineering Calculation in Support of a Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2017-04-0303 April 2017 Submittal of Engineering Calculation in Support of a Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/17-0021, Transmittal of Core Operating Limits Report2017-03-13013 March 2017 Transmittal of Core Operating Limits Report RNP-RA/17-0019, Supplemental Submittal to Correct Marked Up Technical Specifications (TS) Pages Transmitted with Application for Technical Specification Task Force (TSTF)-339, Relocate TS Parameters to the COLR Consistent with WCAP-14483, Revision 22017-03-0808 March 2017 Supplemental Submittal to Correct Marked Up Technical Specifications (TS) Pages Transmitted with Application for Technical Specification Task Force (TSTF)-339, Relocate TS Parameters to the COLR Consistent with WCAP-14483, Revision 2 RNP-RA/17-0015, Independent Spent Fuel Storage Installations - Letter Regarding Report of Changes Pursuant to 10 CFR 72.482017-02-22022 February 2017 Independent Spent Fuel Storage Installations - Letter Regarding Report of Changes Pursuant to 10 CFR 72.48 RNP-RA/17-0016, Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report2017-02-22022 February 2017 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report RNP-RA/17-0015, H.B. Robinson Steam Electric Plant & ISFSIs - Report of Changes Pursuant to 10 CFR 72.482017-02-22022 February 2017 H.B. Robinson Steam Electric Plant & ISFSIs - Report of Changes Pursuant to 10 CFR 72.48 RNP-RA/16-0100, Response to Apparent Violation in NRC Inspection Report 05000261/2016404, EA-16-2272017-01-24024 January 2017 Response to Apparent Violation in NRC Inspection Report 05000261/2016404, EA-16-227 RNP-RA/16-0097, Transmittal Letter for Response to Inspection Report Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestones 1-7, Inspection Report 05000261/20154052016-12-15015 December 2016 Transmittal Letter for Response to Inspection Report Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestones 1-7, Inspection Report 05000261/2015405 RNP-RA/16-0089, Request for Withdrawal of License Amendment Request for Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles2016-11-10010 November 2016 Request for Withdrawal of License Amendment Request for Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles RNP-RA/16-0090, Notification of Rescheduled Date for 2017 Emergency Preparedness Graded Exercise2016-11-10010 November 2016 Notification of Rescheduled Date for 2017 Emergency Preparedness Graded Exercise RNP-RA/16-0087, Technical Specifications Section 5.6.6 Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors2016-10-31031 October 2016 Technical Specifications Section 5.6.6 Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors RNP-RA/16-0078, Technical Specifications Section 5.6.6, Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors2016-10-0505 October 2016 Technical Specifications Section 5.6.6, Post Accident Monitoring Instrumentation Report for Inoperable High Range Containment Area Radiation Monitors RNP-RA/16-0079, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Light Water Reactor Electric Generating Plants.2016-10-0505 October 2016 Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Light Water Reactor Electric Generating Plants. 2021-02-18
[Table view] |
Text
S Duke Sharon A. Wheeler H. B. Robinson Steam Electric Plant Unit 2 Manager - Support Services Duke Energy 3581 West Entrance Road Hartsville, SC 29550 Serial: RNP-RA/13-0017 10 CFR 50.90 MAR 0 6 2013 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261/RENEWED LICENSE NO. DPR-23 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION FOR REVIEW REGARDING STEAM GENERATOR LICENSE AMENDMENT REQUEST TO REVISE TECHNCIAL SPECIFICATIONS FOR STEAM GENERATOR PERMANENT ALTERNATE REPAIR CRITERIA By letter to the U. S. Nuclear Regulatory Commission (NRC) dated August 29, 2012, (Agencywide Documents Access and Management System Accession No. ML12251A363),
Carolina Power and Light Company, now doing business as Progress Energy, submitted a license amendment request (LAR) which combined two proposed changes that affect the same Technical Specification (TS) sections. The first part proposes to implement revisions consistent with TS Task Force-5 10 (TSTF-5 10), Revision 2, "Revision to Steam Generator Inspection Frequencies and Tube Sample Selection." The second part proposes to exclude portions of the steam generator tube below the top of the steam generator tubesheet from periodic inspections by implementing the permanent alternate repair criteria "H*."
By letter dated February 4, 2013, (ADAMS Accession No. ML13017A288) the NRC staff requested additional information needed to continue its review of the proposed license amendment.
Progress Energy's response to the request for additional information is provided in the enclosure to this letter.
This letter contains the following new Regulatory Commitments:
Submit a revised license amendment request regarding Steam Generator program inspection frequencies and tube sample selection, and application of permanent alternate repair criteria (H*), by April 10, 2013.
If you have any questions concerning this matter, please contact Mr. Richard Hightower, Supervisor - Licensing/Regulatory Programs at (843) 857-1329.
Aoo / .
United States Nuclear Regulatory Commission Serial: RNP-RA/13-0017 Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct. Executed On:
MAR 0 6 2013 Sincerely, Sha l eeler Manager - Support Services - Nuclear SAW/jk
Enclosure:
Response to Request for Additional Information Regarding H. B. Robinson Steam Electric Plant, Unit 2 The Steam Generator License Amendment Request to Revise Technical Specification for Permanent Alternate Repair Criteria c: Ms. S. E. Jenkins, Manager, Infectious and Radioactive Waste Management Section (SC)
Mr. V. M. McCree, NRC, Region II Ms. A. T. Billoch-Colon, NRC Project Manager, NRR NRC Resident Inspector, HBRSEP Unit No. 2 Mr. A. Wilson, Attorney General (SC)
United States Nuclear Regulatory Commission Enclosure to Serial: RNP-RA/13-0017 Page 1 of 2 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT 2 THE STEAM GENERATOR LICENSE AMENDMENT REQUEST TO REVISE TECHNCIAL SPECIFICATION FOR PERMANENT ALTERNATE REPAIR CRITERIA NRC REQUEST FOR ADDITIONAL INFORMATION (RAI)
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated August 29, 2012 (Agencywide Documents Access and Management System Accession No. ML12251A363),
Carolina Power & Light Company (the licensee), doing business as Progress Energy Carolinas, submitted a license amendment request (LAR) for H. B. Robinson Steam Electric Plant, Unit 2 (HBRSEP). The proposed LAR combines two changes that affect the same technical specification (TS) sections. The first part proposes to implement revisions consistent with Technical Specification Task Force-5 10, Revision 2, "Revision to Steam Generator Program Inspection Frequencies and tube Sample Selection." The second part proposes to permanently revise TS 5.5.9 "Steam Generator Program" to exclude portions of the steam generator tube below the top of the steam generator tubesheet from periodic inspections by implementing the permanent alternate repair criteria "H*." to the letter dated August 29, 2012, is a Westinghouse letter (LTR-SGMP-12-30 dated May 7, 2012) addressing the applicability of H* and the recommended leakage factor for HBRSEP, given the fact that HBRSEP has implemented a Measurement Uncertainty Recapture Power Uprate.
On pages 2 and 3 of Attachment 6, two tables from the references within Attachment 6 are reproduced. Upon review of the table on page 2, and comparison to Tables 5-1 and 9-5 of WCAP-17091-P (which is Reference 3 of Attachment 6), it isnot clear if the hot leg temperature provided in these three tables represents a low Tavg, a high Tavg, or a nominal Tavg condition for HBRSEP. As it appears that hot leg temperature has a significant effect on secondary pressure (e.g., see the large secondary pressure change between high Tavg to low Tavg at Turkey Point Units 3 and 4 in Table 9-5).
The NRC staff requests the following additional information related to your submittal:
- 1. Determine the low Tavg and high Tavg hot leg temperatures for HBRSEP. Then determine if the differential pressure across the tubesheet for HBRSEP continues to be bounded by the H* analysis for Turkey Point Units 3 and 4, when the low Tavg hot leg temperature is used in the HBRSEP H* analysis.
- 2. Provide the results of the above requested analysis.
United States Nuclear Regulatory Commission Enclosure to Serial: RNP-RA/13-0017 Page 2 of 2 PROGRESS ENERGY RESPONSE Engineering Change (EC) 90553, "Input for NRC Request for Additional Information Regarding Alternate Repair Criteria" was performed and yielded results as shown below:
RCS SG Tubesheet (psia) RCS Conditions Conditions Tavg Tcold Thot Psteam RCS-SG 2250 (OF) (OF) (OF) (psia) psi Low Tavg 571.9 543.1 600.7 773.6 1476.4 High Tavg 579.9 551.5 608.3 833.9 1416.1 As stated in the NRC Request for Additional Information, the critical parameter for the structural analysis is the normal operating parameters (NOP) condition low Tavg secondary pressure because this pressure dictates the largest tube end-cap (pull-out) loads on the tubes.
The following is a comparison of the H. B. Robinson low Tavg data with the Turkey Point data, provided on page 3 to attachment 6 of RNP-RA/12-0057, License Amendment Request for Revision to Steam generator Program Inspection frequencies and Tube Selection and Application of Permanent Alternate Repair Criteria (H*).
Parameter and Units Turkey Point Robinson Power - NSSS MWth 2652 2239 Primary Pressure psia 2250 2250 Secondary Pressure psia 701 773.6 SG Hot Leg Temperature OF 604.5 600.7 SG Primary-to-secondary Pressure Psid 1549 1476.4 Differential (psid) Across Tubesheet Turkey Point Units 3 and 4 exhibits a lower secondary pressure for the low Tavg under NOP condition (701 psia); therefore, it bounds the secondary pressure under the same condition for HBRSEP Unit 2 (773.6 psia). Based upon this, the applicable H* inspection criterion for HBRSEP is 18.11 inches as described in the August 29, 2012 License Amendment Request.
During the development of this response it was determined that the appropriate leakage factor for HBRSEP Unit 2 should be 1.87 rather than 1.82 as previously reported. As a result, it will be necessary to revise our August 29, 2012, License Amendment Request. We expect to provide the revised request by April 10, 2013.