RC-04-0109, Request for Additional Information for Security Plan Sections 1-19
Letter Sequence Request | |
---|---|
TAC:MC2976, (Open) | |
Administration | |
MONTHYEARML0413300242004-05-12012 May 2004
[Table View]Supplemental Response to the April 29, 2003, Orders Modifying Licenses for Revised Design Basis Threat Project stage: Other ML0417704482004-06-22022 June 2004 RAI, Security Plan Sections 1-9 Project stage: RAI RC-04-0109, Request for Additional Information for Security Plan Sections 1-192004-07-0101 July 2004 Request for Additional Information for Security Plan Sections 1-19 Project stage: Request ML0420500032004-07-0909 July 2004 Request for Additional Information Training and Qualification Plan Project stage: RAI ML0421103072004-07-26026 July 2004 Request for Additional Information Training and Qualification Plan Project stage: Request RC-04-0127, Response to Request for Additional Information, Physical Security Plan and Safeguards Contingency Plan2004-08-11011 August 2004 Response to Request for Additional Information, Physical Security Plan and Safeguards Contingency Plan Project stage: Response to RAI ML0423105152004-08-13013 August 2004 Response to Request for Additional Information, Physical Security Plan and Safeguards Contingency Plan Project stage: Response to RAI ML0423900472004-08-23023 August 2004 Response to Request for Additional Information for Security Plan Sections 1-19 Project stage: Response to RAI ML0424606572004-08-31031 August 2004 Response to Request for Additional Information for Security Plan Sections 1-19 Project stage: Response to RAI ML0431200242004-10-28028 October 2004 Administrative Change to Facility Operating License in Conjunction with the Commission Order EA-03-086 Regarding Revised Design Basis Threat (DBT) and Revisions to Physical Security Plan, Training and Qualifications Plan, and Safe... Project stage: Other 2004-07-26 |
ML041880224 | |
Person / Time | |
---|---|
Site: | Summer |
Issue date: | 07/01/2004 |
From: | Byrne S South Carolina Electric & Gas Co |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
RC-04-0109, TAC MC2976 | |
Download: ML041880224 (1) | |
Similar Documents at Summer | |
---|---|
Category:Letter type:RC
MONTHYEARRC-22-0004, (Vcsns), Unit 1 - 2021 Annual Letter of Certification and Testing Results of the Public Alerting System2022-01-14014 January 2022
[Table view](Vcsns), Unit 1 - 2021 Annual Letter of Certification and Testing Results of the Public Alerting System RC-18-0157, (Vcsns), Units 1, 2 and 3 Independent Spent Fuel Storage Installation - Order Approving Indirect Transfer of Control of Operating License and Combined Licenses2018-12-28028 December 2018 (Vcsns), Units 1, 2 and 3 Independent Spent Fuel Storage Installation - Order Approving Indirect Transfer of Control of Operating License and Combined Licenses RC-18-0149, ISFSI - Order Approving Indirect Transfer of Control of Operating License and Combined Licenses2018-12-21021 December 2018 ISFSI - Order Approving Indirect Transfer of Control of Operating License and Combined Licenses RC-18-0136, (Vcsns), Unit 1 - Request to Remove the Expired One-Time Extension to Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation and to Remove the Index from Technical Specifications (LAR-18-04683)2018-12-12012 December 2018 (Vcsns), Unit 1 - Request to Remove the Expired One-Time Extension to Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation and to Remove the Index from Technical Specifications (LAR-18-04683) RC-18-0144, (Vcsns), Unit 1 - Core Operating Limits Report (COLR) for Cycle 252018-11-20020 November 2018 (Vcsns), Unit 1 - Core Operating Limits Report (COLR) for Cycle 25 RC-18-0126, (Vcsns), Unit 1 - Notification of an Intended Change a Commitment Date for Open Phase Condition (OPC) Made in RC-17-01692018-11-0909 November 2018 (Vcsns), Unit 1 - Notification of an Intended Change a Commitment Date for Open Phase Condition (OPC) Made in RC-17-0169 RC-18-0070, (Vcsns), Unit 1 - Relief Request RR-4-14, Use of a Performance Based Testing Frequency for Pressure Isolation Valves as an Alternative to the Requirements of the American Society of Mechanical Engineers Code for ...2018-10-0808 October 2018 (Vcsns), Unit 1 - Relief Request RR-4-14, Use of a Performance Based Testing Frequency for Pressure Isolation Valves as an Alternative to the Requirements of the American Society of Mechanical Engineers Code for ... RC-18-0067, (Vcsns), Unit 1 - License Amendment Request - LAR-16-00644 - Revise Reactor Coolant System Operational Leakage Technical Specification Surveillance Requirement 4.4.6.2.22018-10-0808 October 2018 (Vcsns), Unit 1 - License Amendment Request - LAR-16-00644 - Revise Reactor Coolant System Operational Leakage Technical Specification Surveillance Requirement 4.4.6.2.2 RC-18-0123, NRC Request for Information Baseline Radiation Safety Inspection2018-10-0404 October 2018 NRC Request for Information Baseline Radiation Safety Inspection RC-18-0117, (Vcsns), Unit 1 - Fukushima Near-Term Task Force Recommendation 3.1: Seismic Probabilistic Risk Assessment2018-09-28028 September 2018 (Vcsns), Unit 1 - Fukushima Near-Term Task Force Recommendation 3.1: Seismic Probabilistic Risk Assessment RC-18-0112, (Vcsns), Unit 1 - Request for License Amendment to Virgil C. Summer Nuclear Station Technical Specification 3.8.2, D.C. Sources - Operating, Surveillance Requirements 4.8.2.1.B.2 and 4.8.2.1.C.32018-09-27027 September 2018 (Vcsns), Unit 1 - Request for License Amendment to Virgil C. Summer Nuclear Station Technical Specification 3.8.2, D.C. Sources - Operating, Surveillance Requirements 4.8.2.1.B.2 and 4.8.2.1.C.3 RC-18-0119, (Vcsns), Unit 1 - Supplement to License Amendment Request LAR-18-03422, Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation2018-09-19019 September 2018 (Vcsns), Unit 1 - Supplement to License Amendment Request LAR-18-03422, Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation RC-18-0118, (Vcsns), Unit 1 - Relief Request RR-4-18, Request for a Temporary Non-Code Repair of a Service Water System Flange2018-09-14014 September 2018 (Vcsns), Unit 1 - Relief Request RR-4-18, Request for a Temporary Non-Code Repair of a Service Water System Flange RC-18-0116, (Vcsns), Unit 1 - Request for a One-Time Extension to the Surveillance Frequency 4.4.4.6 of the Core Exit Temperature Instrumentation - Response to Request for Additional Information2018-09-11011 September 2018 (Vcsns), Unit 1 - Request for a One-Time Extension to the Surveillance Frequency 4.4.4.6 of the Core Exit Temperature Instrumentation - Response to Request for Additional Information RC-18-0113, (Vcsns), Unit 1 - Supplement to License Amendment Request LAR-18-03422 Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation2018-08-31031 August 2018 (Vcsns), Unit 1 - Supplement to License Amendment Request LAR-18-03422 Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation RC-18-0091, License Amendment Request - LAR-16-01490 National Fire Protection Association Standard 805 Program Revisions2018-08-29029 August 2018 License Amendment Request - LAR-16-01490 National Fire Protection Association Standard 805 Program Revisions RC-18-0111, License Amendment Request LAR-18-03422 Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation2018-08-24024 August 2018 License Amendment Request LAR-18-03422 Request for a One-Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation RC-18-0100, (Vcsns), Unit 1 - Technical Specification Change Request for the Revision of the Surveillance Frequency of the Turbine Trip Functional Unit: Response to Request for Additional Information2018-08-22022 August 2018 (Vcsns), Unit 1 - Technical Specification Change Request for the Revision of the Surveillance Frequency of the Turbine Trip Functional Unit: Response to Request for Additional Information RC-18-0105, (Vcsns), Unit 1 - Relief Request RR-4-17, Request to Utilize Code Case N-513-3 'Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1' for a Service Water ..2018-08-14014 August 2018 (Vcsns), Unit 1 - Relief Request RR-4-17, Request to Utilize Code Case N-513-3 'Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1' for a Service Water .. RC-18-0102, Withdrawal of Request to Revise Technical Specifications to Correct an Administrative Error2018-08-10010 August 2018 Withdrawal of Request to Revise Technical Specifications to Correct an Administrative Error RC-18-0098, (Vcsns), Units 1, 2 and 3 - Modification of Requested Latest Completion Date in Application for Order Approving Indirect Transfer of Control of Operating License and Combined Licenses2018-07-30030 July 2018 (Vcsns), Units 1, 2 and 3 - Modification of Requested Latest Completion Date in Application for Order Approving Indirect Transfer of Control of Operating License and Combined Licenses RC-18-0085, (Vcsns), Unit 1 - Notification of an Intended Change to a Commitment Made in RC-17-01262018-07-23023 July 2018 (Vcsns), Unit 1 - Notification of an Intended Change to a Commitment Made in RC-17-0126 RC-18-0090, (Vcsns), Unit 1 - Relief Request RR-4-16, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Response to Request...2018-07-12012 July 2018 (Vcsns), Unit 1 - Relief Request RR-4-16, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Response to Request... RC-18-0089, (Vcsns), Unit 1 - Relief Request RR-4-16, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping2018-07-11011 July 2018 (Vcsns), Unit 1 - Relief Request RR-4-16, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping RC-18-0084, Virgil C Summer Nuclear Station (Vcsns), Unit 1 - Relief Request RR-4-15, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Laws in Moderate Energy Class 2 or 3 Piping Response to Requ2018-07-0303 July 2018 Virgil C Summer Nuclear Station (Vcsns), Unit 1 - Relief Request RR-4-15, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Laws in Moderate Energy Class 2 or 3 Piping Response to Reques RC-18-0082, Relief Request RR-4-15, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping2018-07-0303 July 2018 Relief Request RR-4-15, Request for Alternative to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping RC-18-0079, Vigil C. Summer Nuclear Station (Vcsns), Unit 1 - Request to Revise Technical Specifications to Correct an Administrative Error2018-06-29029 June 2018 Vigil C. Summer Nuclear Station (Vcsns), Unit 1 - Request to Revise Technical Specifications to Correct an Administrative Error RC-18-0074, Change of the Commitment Date of DRIB/105A&B Door Submittal2018-06-18018 June 2018 Change of the Commitment Date of DRIB/105A&B Door Submittal RC-18-0060, (VCSNS) - Request to Revise Technical Specifications to Correct Administrative Error2018-05-30030 May 2018 (VCSNS) - Request to Revise Technical Specifications to Correct Administrative Error RC-18-0064, (Vcsns), Unit 1 - Annual Commitment Change Summary Report2018-05-18018 May 2018 (Vcsns), Unit 1 - Annual Commitment Change Summary Report RC-18-0063, Submittal of 10 CFR 72.48 Biennial Report for the Independent Spent Fuel Storage Installation2018-05-0202 May 2018 Submittal of 10 CFR 72.48 Biennial Report for the Independent Spent Fuel Storage Installation RC-18-0056, (Vcsns), Unit 1 - Licensee Event Reports (2016-001-02, 2016-002-01, 2016-003-02) - Revision to Correct Typographical Errors2018-04-25025 April 2018 (Vcsns), Unit 1 - Licensee Event Reports (2016-001-02, 2016-002-01, 2016-003-02) - Revision to Correct Typographical Errors RC-18-0059, Annual Radioactive Effluent Release Report2018-04-25025 April 2018 Annual Radioactive Effluent Release Report RC-18-0046, License Amendment Request LAR-14-01541 Integrated Leak Rate Test Peak Calculated Containment Internal Pressure Change Request for Additional Information2018-04-19019 April 2018 License Amendment Request LAR-14-01541 Integrated Leak Rate Test Peak Calculated Containment Internal Pressure Change Request for Additional Information RC-18-0036, (Vcsns), Unit 1 - Relief Request RR-4-13, Use of a Risk-Informed Process as an Alternative for the Selection of Class 1 and Class 2 Piping Welds - Response to Request for Additional Information2018-04-0202 April 2018 (Vcsns), Unit 1 - Relief Request RR-4-13, Use of a Risk-Informed Process as an Alternative for the Selection of Class 1 and Class 2 Piping Welds - Response to Request for Additional Information RC-18-0041, Report of Status of Decommissioning Funding2018-03-28028 March 2018 Report of Status of Decommissioning Funding RC-17-0175, Correction to Amendment No. 170 Request to Revise Technical Specifications to Correct Administrative Error2018-01-31031 January 2018 Correction to Amendment No. 170 Request to Revise Technical Specifications to Correct Administrative Error RC-18-0006, Independent Spent Fuel Storage Installation Re Application for Order Approving Indirect Transfer of Control of Operating License and Combined Licenses2018-01-25025 January 2018 Independent Spent Fuel Storage Installation Re Application for Order Approving Indirect Transfer of Control of Operating License and Combined Licenses RC-17-0169, Notification of an Intended Change of a Commitment Date for Open Phase Condition Made in RC-14-00192017-12-11011 December 2017 Notification of an Intended Change of a Commitment Date for Open Phase Condition Made in RC-14-0019 RC-17-0182, (VCSNS) - Anchor Darling Double Disc Gate Valve Information and Status2017-12-11011 December 2017 (VCSNS) - Anchor Darling Double Disc Gate Valve Information and Status RC-17-0172, Notification of Personnel Changes2017-11-30030 November 2017 Notification of Personnel Changes RC-17-0161, Submittal of Change of the Commitment Date of DRIB/105A&B Door2017-11-28028 November 2017 Submittal of Change of the Commitment Date of DRIB/105A&B Door RC-17-0135, Annual Commitment Change Summary Report2017-11-0303 November 2017 Annual Commitment Change Summary Report RC-17-0123, Relief Request RR-4-13, Use of a Risk-Informed Process as an Alternative for the Selection of Class 1 and Class 2 Piping Welds2017-10-30030 October 2017 Relief Request RR-4-13, Use of a Risk-Informed Process as an Alternative for the Selection of Class 1 and Class 2 Piping Welds RC-17-0140, Transmittal of 10 CFR 50.59 Biennial Report2017-10-23023 October 2017 Transmittal of 10 CFR 50.59 Biennial Report RC-17-0107, (Vcsns), Unit 1 - Integrated Leak Rate Test Peak Calculated Containment Internal Pressure Change2017-10-0606 October 2017 (Vcsns), Unit 1 - Integrated Leak Rate Test Peak Calculated Containment Internal Pressure Change RC-17-0134, Response to Request for Supplemental Information, License Amendment Request - LAR-15-01424; Implementation of WCAP-15376-P-A, Revision 12017-09-27027 September 2017 Response to Request for Supplemental Information, License Amendment Request - LAR-15-01424; Implementation of WCAP-15376-P-A, Revision 1 RC-17-0126, Reply to a Notice of Violation, Per Inspection Report 05000395/20170022017-09-0606 September 2017 Reply to a Notice of Violation, Per Inspection Report 05000395/2017002 RC-17-0112, Special Report (Spr) 2017-007 Regarding Waste Gas Holdup System Explosive Gas Monitoring System Being Inoperable for Greater than Thirty Days2017-09-0101 September 2017 Special Report (Spr) 2017-007 Regarding Waste Gas Holdup System Explosive Gas Monitoring System Being Inoperable for Greater than Thirty Days RC-17-0069, (Vcsns), Unit 1 - Quality Assurance Approval Certificate No. 0479, Transmittal of the Quality Assurance Program Description2017-08-30030 August 2017 (Vcsns), Unit 1 - Quality Assurance Approval Certificate No. 0479, Transmittal of the Quality Assurance Program Description 2022-01-14 |
Text
Stephen A. Byrne Senior Vice President, Nuclear Operations 803.345.4622 A SCANA COMPANY July 1, 2004 Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555
Dear Sir/Madam:
Subject:
VIRGIL C. SUMMER NUCLEAR STATION DOCKET NO. 50-395 OPERATING LICENSE NO. NPF-12 REQUEST FOR ADDITIONAL INFORMATION FOR SECURITY PLAN SECTIONS 1-19 (TAC NO. MC2976)
Reference:
Margaret H. Chernoff (NRC) to Stephen A. Byrne letter dated June 16, 2004 Margaret H. Chernoff (NRC) to Stephen A. Byrne letter dated June 22, 2004 South Carolina Electric & Gas Company (SCE&G) hereby requests an extension to provide the additional information for Security Plan Sections 1-9 and 10-19. The requests for additional information (RAls) were received in letters from the Office of Nuclear Reactor Regulation dated June 16, 2004 and June 22, 2004 (TAC No. MC2976). As discussed in a telephone conference with NRR on June 27, 2004, SCE&G will provide the response to address which initiatives will be directly adopted and which ones requirq additional dialogue by July 14, 2004.
Should you have any questions, please call Mr. Mark P. Findlay at (803) 345-4186.
Very truly yours, Stephen A. Byrne SBR/SAB/sr c: Mr. N. 0. Lorick Ms. K. R. Cotton Mr. N. S. Carns Mr. D. Walters, NEI Mr. R. J. White Ms. K. M. Sutton Mr. T. G. Eppink NSRC Ms. M. H. Chernoff RTS (C-03-1497)
Mr. W. D. Travers File (815.07)
NRC Resident Inspector DMS (RC-04-0109) 60b'3 SCE&G I Virgil C.Summer Nudear Station . P.0. Box 88
- Jenkinsville, South Carolina 29065