Category:Press Release
MONTHYEARML22255A0862022-09-0909 September 2022 News Release-22-037: NRC to Hold Decommissioning Plan Public Meeting for Palisades Nuclear Power Plant in Michigan ML22112A0212022-04-19019 April 2022 News Release-III-22-005: NRC to Conduct Open House to Discuss 2021 Performance of Palisades Nuclear Plant Press Release-21-053, NRC Approves License Transfer for Palisades and Big Rock Point Nuclear Power Plants2021-12-13013 December 2021 Press Release-21-053: NRC Approves License Transfer for Palisades and Big Rock Point Nuclear Power Plants Press Release-III-21-015, NRC to Hold Virtual Meeting to Discuss Palisades Nuclear Power Plant 2020 Performance2021-06-24024 June 2021 Press Release-III-21-015: NRC to Hold Virtual Meeting to Discuss Palisades Nuclear Power Plant 2020 Performance ML21209A4962021-02-0303 February 2021 News Release-21-006: NRC to Seek Comment on Environmental Review Topics for Point Beach Subsequent License Renewal Press Release-III-20-004, NRC Names New Resident Inspector at Palisades Nuclear Power Plant2020-05-29029 May 2020 Press Release-III-20-004: NRC Names New Resident Inspector at Palisades Nuclear Power Plant Press Release-19-039, NRC Announces Public Meetings Dates and Venues for Community Advisory Boards Near Decommissioning Nuclear Power Plants2019-08-21021 August 2019 Press Release-19-039: NRC Announces Public Meetings Dates and Venues for Community Advisory Boards Near Decommissioning Nuclear Power Plants Press Release-III-19-009, NRC to Hold Open House to Discuss 2018 Performance of Palisades Nuclear Plant2019-04-30030 April 2019 Press Release-III-19-009: NRC to Hold Open House to Discuss 2018 Performance of Palisades Nuclear Plant Press Release-III-18-026, NRC Names New Senior Resident Inspector at Palisades Nuclear Power Station2018-07-27027 July 2018 Press Release-III-18-026: NRC Names New Senior Resident Inspector at Palisades Nuclear Power Station Press Release-III-18-010, NRC to Conduct Open House to Discuss 2017 Performance of Palisades Nuclear Power Plant2018-04-0202 April 2018 Press Release-III-18-010: NRC to Conduct Open House to Discuss 2017 Performance of Palisades Nuclear Power Plant Press Release-IV-18-002, NRC Issues Confirmatory Order to Entergy2018-03-14014 March 2018 Press Release-IV-18-002: NRC Issues Confirmatory Order to Entergy Press Release-III-17-022, NRC to Conduct Open House to Discuss 2016 Performance of Palisades Nuclear Plant2017-07-17017 July 2017 Press Release-III-17-022: NRC to Conduct Open House to Discuss 2016 Performance of Palisades Nuclear Plant Press Release-III-16-015, NRC Schedules a Town Hall Meeting June 23 to Discuss Palisades Nuclear Plant2016-06-14014 June 2016 Press Release-III-16-015: NRC Schedules a Town Hall Meeting June 23 to Discuss Palisades Nuclear Plant Press Release-III-16-010, NRC Issues Confirmatory Order to Entergy Regarding Palisades Nuclear Plant2016-05-16016 May 2016 Press Release-III-16-010: NRC Issues Confirmatory Order to Entergy Regarding Palisades Nuclear Plant Press Release-15-068, NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors2015-10-27027 October 2015 Press Release-15-068: NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors Press Release-III-15-023, NRC Names New Resident Inspector at Palisades Nuclear Plant2015-10-0505 October 2015 Press Release-III-15-023: NRC Names New Resident Inspector at Palisades Nuclear Plant Press Release-15-054, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2015-09-0303 September 2015 Press Release-15-054: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-III-15-008, NRC Schedules Public Meeting Apr. 9 to Discuss Performance of Palisades Nuclear Power Station2015-04-0303 April 2015 Press Release-III-15-008: NRC Schedules Public Meeting Apr. 9 to Discuss Performance of Palisades Nuclear Power Station Press Release-III-15-003, NRC Has Increased Oversight of Palisades Nuclear Power Plant2015-02-27027 February 2015 Press Release-III-15-003: NRC Has Increased Oversight of Palisades Nuclear Power Plant Press Release-III-15-001, NRC Schedules Regulatory Conference to Discuss Apparent Violation at Palisades Nuclear Plant2015-01-0707 January 2015 Press Release-III-15-001: NRC Schedules Regulatory Conference to Discuss Apparent Violation at Palisades Nuclear Plant Press Release-III-14-031, NRC Issues Confirmatory Order to Entergy Regarding Palisades Nuclear Plant2014-07-24024 July 2014 Press Release-III-14-031: NRC Issues Confirmatory Order to Entergy Regarding Palisades Nuclear Plant ML14204A2102014-07-22022 July 2014 Press Release-III-14-031: NRC Issues Confirmatory Order to Entergy Regarding Palisades Nuclear Plant Press Release-III-14-023, NRC Schedules Public Meeting June 26 to Discuss Performance of Palisades Nuclear Power Station2014-06-23023 June 2014 Press Release-III-14-023: NRC Schedules Public Meeting June 26 to Discuss Performance of Palisades Nuclear Power Station Press Release-III-14-008, NRC Names New Senior Resident Inspector at Palisades Nuclear Station2014-03-20020 March 2014 Press Release-III-14-008: NRC Names New Senior Resident Inspector at Palisades Nuclear Station Press Release-III-13-035, NRC Names Cynthia D. Pederson as Region III Administrator2013-08-13013 August 2013 Press Release-III-13-035: NRC Names Cynthia D. Pederson as Region III Administrator Press Release-III-13-027, NRC Regional Office Webinar to Discuss Agency Steps on Palisades Water Tank2013-07-0909 July 2013 Press Release-III-13-027: NRC Regional Office Webinar to Discuss Agency Steps on Palisades Water Tank Press Release-III-13-007, NRC Schedules Public Meeting April 2, 2013, to Discuss Performance of Palisades Nuclear Power Station2013-03-25025 March 2013 Press Release-III-13-007: NRC Schedules Public Meeting April 2, 2013, to Discuss Performance of Palisades Nuclear Power Station Press Release-III-13-006, NRC to Discuss Pressurized Thermal Shock Basics for Palisades; Webinar to Be Held March 192013-03-0707 March 2013 Press Release-III-13-006: NRC to Discuss Pressurized Thermal Shock Basics for Palisades; Webinar to Be Held March 19 Press Release-III-13-001, NRC to Discuss Recent Through-Wall Leaks at Palisades; Webinar to Be Held January 122013-01-0808 January 2013 Press Release-III-13-001: NRC to Discuss Recent Through-Wall Leaks at Palisades; Webinar to Be Held January 12 Press Release-III-12-042, NRC Schedules Public Meeting for December 11 to Discuss Palisades Corrective Actions and NRC Oversight2012-12-0404 December 2012 Press Release-III-12-042: NRC Schedules Public Meeting for December 11 to Discuss Palisades Corrective Actions and NRC Oversight Press Release-III-12-041, NRC Says Palisades Performance Has Improved But Still Needs Heightened Oversight2012-11-0909 November 2012 Press Release-III-12-041: NRC Says Palisades Performance Has Improved But Still Needs Heightened Oversight Press Release-III-12-038, NRC to Discuss Preliminary Special Inspection Results; Webinar to Be Held October 12012-09-26026 September 2012 Press Release-III-12-038: NRC to Discuss Preliminary Special Inspection Results; Webinar to Be Held October 1 Press Release-III-12-036, NRC to Hold Public Meeting to Discuss Palisades Safety Culture Assessment Results2012-09-0707 September 2012 Press Release-III-12-036: NRC to Hold Public Meeting to Discuss Palisades Safety Culture Assessment Results Press Release-III-12-035, NRC Begins Special Inspection at Palisades Nuclear Plant2012-08-15015 August 2012 Press Release-III-12-035: NRC Begins Special Inspection at Palisades Nuclear Plant Press Release-III-12-030, NRC Issues Confirmatory Action Letter to Palisades Nuclear Power Plant2012-07-17017 July 2012 Press Release-III-12-030: NRC Issues Confirmatory Action Letter to Palisades Nuclear Power Plant Press Release-III-12-015, NRC Names New Resident Inspector at Palisades Nuclear Power Plant2012-04-25025 April 2012 Press Release-III-12-015: NRC Names New Resident Inspector at Palisades Nuclear Power Plant Press Release-III-12-009, NRC Schedules Open House and Public Meeting for March 21 to Discuss Palisades Nuclear Power Plant Performance in 20112012-03-15015 March 2012 Press Release-III-12-009: NRC Schedules Open House and Public Meeting for March 21 to Discuss Palisades Nuclear Power Plant Performance in 2011 Press Release-III-12-006, NRC Cites Palisades for Three Violations; Public Meeting Scheduled2012-02-14014 February 2012 Press Release-III-12-006: NRC Cites Palisades for Three Violations; Public Meeting Scheduled Press Release-III-12-003, NRC Issues Confirmatory Orders to Palisades Plant Owner Entergy and Plant Operator2012-01-26026 January 2012 Press Release-III-12-003: NRC Issues Confirmatory Orders to Palisades Plant Owner Entergy and Plant Operator Press Release-III-12-002, NRC to Hold Two Regulatory Conferences on January 11 to Discuss Preliminary White and Preliminary Yellow Findings at Palisades Nuclear Plant2012-01-0505 January 2012 Press Release-III-12-002: NRC to Hold Two Regulatory Conferences on January 11 to Discuss Preliminary White and Preliminary Yellow Findings at Palisades Nuclear Plant ML1200502902012-01-0505 January 2012 Press Release-III-12-002: NRC to Hold Two Regulatory Conferences on January 11 to Discuss Preliminary White and Preliminary Yellow Findings at Palisades Nuclear Plant Press Release-III-11-034, NRC Begins Special Inspection at Palisades Nuclear Plant2011-09-29029 September 2011 Press Release-III-11-034: NRC Begins Special Inspection at Palisades Nuclear Plant Press Release-IV-11-038, NRC Issues Confirmatory Order to Entergy with Actions to Improve Quality Control and Employee Concerns Programs2011-08-25025 August 2011 Press Release-IV-11-038: NRC Issues Confirmatory Order to Entergy with Actions to Improve Quality Control and Employee Concerns Programs Press Release-III-11-029, NRC Begins Special Inspection at Palisades Nuclear Power Plant2011-08-15015 August 2011 Press Release-III-11-029: NRC Begins Special Inspection at Palisades Nuclear Power Plant Press Release-III-11-011, NRC Schedules Public Meeting for May 5 to Discuss Palisades Nuclear Power Plant Performance and NRC Oversight2011-04-21021 April 2011 Press Release-III-11-011: NRC Schedules Public Meeting for May 5 to Discuss Palisades Nuclear Power Plant Performance and NRC Oversight Press Release-10-154, National Academy of Sciences Seeks Nominations for Experts to Conduct NRC-Sponsored Cancer Risk Study2010-09-0303 September 2010 Press Release-10-154: National Academy of Sciences Seeks Nominations for Experts to Conduct NRC-Sponsored Cancer Risk Study Press Release-III-10-014, NRC to Discuss 2009 Performance Assessment Palisades Nuclear Power Plant May 112010-05-0404 May 2010 Press Release-III-10-014: NRC to Discuss 2009 Performance Assessment Palisades Nuclear Power Plant May 11 Press Release-III-10-007, NRC to Hold Public Meeting with Entergy Nuclear Operations Inc2010-03-26026 March 2010 Press Release-III-10-007: NRC to Hold Public Meeting with Entergy Nuclear Operations Inc Press Release-III-09-032, NRC Staff Issues Confirmatory Order to Entergy2009-11-17017 November 2009 Press Release-III-09-032: NRC Staff Issues Confirmatory Order to Entergy Press Release-III-09-017, NRC to Discuss 2008 Performance Assessment for Palisades Nuclear Power Plant May 262009-05-18018 May 2009 Press Release-III-09-017: NRC to Discuss 2008 Performance Assessment for Palisades Nuclear Power Plant May 26 2022-09-09
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Region III 2443 Warrenville Road Lisle IL 60532 Site: www.nrc.gov Blog: http://public-blog.nrc-gateway.gov No. III-12-009 March 15, 2012
Contact:
Viktoria Mitlyng (630) 829-9662 E-Mail: OPA3.RegionIII@nrc.gov Prema Chandrathil (630) 829-9663 NRC SCHEDULES OPEN HOUSE AND PUBLIC MEETING FOR MARCH 21 TO DISCUSS PALISADES NUCLEAR POWER PLANT PERFORMANCE IN 2011 Nuclear Regulatory Commission officials have scheduled a public meeting for Wednesday, March 21, to discuss with local residents the agencys assessment of safety performance at the Palisades nuclear power plant and the NRC oversight activities.
The plant is located in Covert, Mich., approximately 50 miles west of Kalamazoo, and is operated by Entergy Nuclear Operations.
The open house is informal and will be held from 5:30 p.m. to 6 p.m. EDT. The public meeting will be held 6 p.m. to 8:30 p.m. and consist of a formal exchange between the NRC and Entergy representatives about the plants 2011 performance followed by the opportunity for members of the public to ask questions and make comments to the NRC staff. The meeting will be held at the Beach Haven Event Center, 10420 M-140, in South Haven.
The NRC continually reviews the performance of the Palisades plant and the nations other commercial nuclear power facilities, said NRC Acting Region III Administrator Cynthia Pederson. This meeting allows us to discuss our annual assessment of safety performance with members of the local community. The goal of this open house is to explain how the NRC works to protect people and the environment and answer questions from residents about nuclear regulation.
A letter sent from the NRC Region III office to plant officials addressed the performance of the plant during 2011 and will serve as the basis for the discussion. It is available on the NRC Web site at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/pali_2011q4.pdf .
While overall, the NRC believes the plant operated safely last year, the NRC identified several issues which have prompted the NRC to significantly increase its oversight of the plant.
The NRC uses color-coded inspection findings and performance indicators to assess nuclear plant performance. The colors start with green and then increase to white, yellow or red, commensurate with the safety significance of the issues involved.
The NRC letter states that two white findings of low to moderate safety significance and one yellow finding of substantial significance to safety were identified during 2011. As a result, the NRC moved the plant into the Degraded Cornerstone Column of the Action Matrix, or the third performance column, during the last quarter of last year from the Licensee Response Column, or the first performance column.
The yellow finding is related to an electrical fault caused by personnel at the site which resulted in a reactor trip, the loss of half of the control room indicators, and actuation of safety systems that were not warranted by actual plant conditions. One white finding is related a the coupling failure in a service water pump which was a repeat of a previous equipment failure that occurred in 2009 because plant failed to prevent recurrence of the cracking condition and failed to completely consider the properties of the steel used in a past modification of the couplings.
The other white issue is associated with an auxiliary feedwater pump trip caused in part by incorrect greasing of a piece of the pump mechanism.
The NRC will perform supplemental inspections to make sure the plant understands the causes of the findings and has taken effective short- and long-term corrective actions to prevent their recurrence.
The letter also notes that the NRC identified three cross-cutting issues in the area of human performance associated with conservative assumptions; documentation and procedures; and oversight. Human performance concerns constitute a Cross-cutting issue and affect multiple areas of plant operation. These issues tend to involve behaviors, such as the plant staffs ability to effectively develop and follow procedures. These behaviors do not constitute violations of NRC requirements. However, they can be major contributing factors to safety-significant findings. The cross-cutting issue will remain open until the number of findings with cross-cutting aspects decreases and the plant demonstrates effective corrective actions that result in sustained improvement in human performance. The NRC expects Entergy to discuss the companys plans to address human performance issues during this public meeting.
In additional to supplemental inspections to address the findings, Palisades will continue to receive inspections performed by two NRC Resident Inspectors assigned to the plant and by inspection specialists from the Region III Office in Lisle, Ill., and the agencys headquarters in Rockville, Md. Among the areas of plant operations being inspected are license renewal, dry cask spent fuel storage, emergency preparedness and radiation protection.
The most current performance information for Palisades is available on the NRC website at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/PALI/pali_chart.html News releases are available through a free listserv subscription at the following Web address:
http://www.nrc.gov/public-involve/listserver.html. The NRC homepage at www.nrc.gov also offers a SUBSCRIBE link. E-mail notifications are sent to subscribers when news releases are posted to NRC's Web site.