PNO-II-97-034, on 970613,extended Shutdown to Meet CAL 2-97-03 Commitments to Shutdown Unit 1 No Later than 970614 & to Implement Actions Re HPI Sys.Nrc Resident Inspector Will Followup on Unit 1 Shutdown & Recovery Activities

From kanterella
(Redirected from PNO-II-97-034)
Jump to navigation Jump to search
PNO-II-97-034:on 970613,extended Shutdown to Meet CAL 2-97-03 Commitments to Shutdown Unit 1 No Later than 970614 & to Implement Actions Re HPI Sys.Nrc Resident Inspector Will Followup on Unit 1 Shutdown & Recovery Activities
ML20140G431
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 06/13/1997
From: Carroll R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
References
CAL-2-97-03, CAL-2-97-3, FACA, PNO-II-97-034, PNO-II-97-34, NUDOCS 9706160232
Download: ML20140G431 (1)


--

_ ~._

i i

l

~

  • June 13, 1997 1

REELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE PNO-II-97-034 l

i l

This preliminary notification constitutes EARLY notice of events of POSSIBLE i

safety or public. interest significance. The information is as initially l received without verification or evaluation, and is basically all that is known by Region II staff in Atlanta, Georgia on this date.

Facility Licensee Emercency Classification Duke Power Co.

Notification of Unusual Event Oconee 1 Alert I

< Seneca, South Carolina Site Area Emergency l Dockets: 50-269 General Emergency X Not Applicable l

Subject:

EXTENDED SHUTDOWN TO MEET CONFIRMATORY ACTION LETTER Oconee Unit 1 is scheduled to be shutdown by early evening on June 13, 1997, to conduct non-destructive test examinations of high pressure injection (HPI) lines / nozzles and implement letdown storage tank j

l level / pressure modifications similar to those recently performed in the l other two Oconee Units as a result of the Unit 2 HPI line/ nozzle weld crack (PNO-II-97-26) and Unit 3 HPI system degradation (PNO-II-97-023).

l As. encompassed in the May 22, 1997, update to associated Confirmatory j

i Action Letter 2-97-003, the licensee committed to shutdown Unit i no

later than June 14 and implement compensatory actions in the interim with l

respect to the above issues, as well as HPI pump minimum recirculation L flow orifice degradation.

Accordingly, during this estimated two week outage, HPI pump minimum recirculation flow orifice blocks will also be replaced.

The NRC resident inspectors will followup on the Unit 1 shutdown and associated recovery activities.

,.The state of South Carolina has been notified.

The licensee is prepared j to respond to any media inquiries, but no press release is planned.

l This information is current as of 11:00 a.m.,

on June 13, 1997.

Contact:

R.

CARROLL (404)S62-4511 9706160232 970613 PDR I&E

,4)3(s PNO-II-97-034 PDR D

1G0057 i