PLA-6150, Clarification of Implementation Dates for Proposed Amendment Nos. 279, and 248, Arts/Mellla Implementation

From kanterella
Jump to navigation Jump to search

Clarification of Implementation Dates for Proposed Amendment Nos. 279, and 248, Arts/Mellla Implementation
ML070170458
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 01/09/2007
From: Mckinney B
Susquehanna
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
PLA-6150
Download: ML070170458 (2)


Text

ift' l Sý*

Britt T. McKInney PPL Susquehanna, LLC 0 Sr. Vice President & Chief Nuclear Officer 769 Salem Boulevard ppmu **

Berwick, PA 18603 Tel. 570.542.3149 Fax 570.542.1504 btmckinney@pplweb.com U.S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station OP 1-17 Washington, DC 20555 SUSQUEHANNA STEAM ELECTRIC STATION CLARIFICATION OF IMPLEMENTATION DATES FOR PROPOSED AMENDMENT NO. 279 TO LICENSE NPF-14 AND PROPOSED AMENDMENT NO. 248 TO LICENSE NPF-22:

ARTS/MELLLA IMPLEMENTATION Docket Nos. 50-387 PLA-6150 and 50-388

Reference:

PLA Letter PLA-5931, Britt T McKinney (PPL)to USNRC "SusquehannaSteam Electric Station ProposedLicense Amendment Numbers 279for Unit 1 OperatingLicense No.

NPF-14 and 248 for Unit 2 OperatingLicense No. NPF-22."ARTS/MELLLA Implementation, "dated November 18, 2005.

The purpose of this letter is to amend PPL's proposed implementation schedule for the ARTS/MELLLA amendment. In the above reference, PPL stated in the cover letter "After NRC approval, PPL plans to implement ARTS/MELLLA on Unit 1. PPL plans to implement PRNMS and ARTS/MELLLA on Unit 2 during the Spring 2007 Outage."

When the above implementation schedules were proposed, PPL was planning to install ARTS/MELLLA while Unit 1 was online. Based on more recent evaluation, PPL has decided to install ARTS/MELLLA in Unit 1 during a scheduled outage but not later than the Unit 1 Spring 2008 Outage. Therefore, PPL requests that the implementation date for the Unit 1 ARTS/MELLLA amendment be prior to the startup following the Unit 1 Spring 2008 Outage.

Unit 2's implementation date for these changes remains prior to startup following the Unit 2 Spring 2007 Outage.

-A-001

Document Control Desk PLA-6150 If you have any questions, please contact Mr. Michael H. Crowthers at (610) 774-7766.

T. cKinneyy cc: NRC Region I Mr. R. V. Guzman, NRC Project Manager Mr. R. Janati, DEP/BRP Mr. C. Welch, NRC Sr. Resident Inspector