MONTHYEARNOC-AE-230040, Supplement to Proposed Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (Relief Request RR-ENG-4-06)2023-12-14014 December 2023 Supplement to Proposed Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (Relief Request RR-ENG-4-06) NOC-AE-230039, Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/20230032023-12-12012 December 2023 Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/2023003 NOC-AE-230039, Submittal of Update Foreign Ownership, Control or Influence (FOCI)2023-07-11011 July 2023 Submittal of Update Foreign Ownership, Control or Influence (FOCI) NOC-AE-220039, Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program Revision 252023-02-0606 February 2023 Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program Revision 25 NOC-AE-220038, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2022-06-23023 June 2022 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask NOC-AE-210038, Submittal of Operations Quality Assurance Plan Changes QA-089, QA-091, and Revision 252022-01-0404 January 2022 Submittal of Operations Quality Assurance Plan Changes QA-089, QA-091, and Revision 25 NOC-AE-21003858, 10 CFR 50.46 Thirty-Day Report of Significant ECCS Model Changes2021-12-0606 December 2021 10 CFR 50.46 Thirty-Day Report of Significant ECCS Model Changes NOC-AE-21003853, Revised Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material2021-12-0303 December 2021 Revised Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material NOC-AE-21003848, Unit 1 Cycle 24 Core Operating Limits Report2021-11-18018 November 2021 Unit 1 Cycle 24 Core Operating Limits Report NOC-AE-21003846, Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material2021-11-0404 November 2021 Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material NOC-AE-21003842, 10 CFR 50.59 Summary Report2021-09-23023 September 2021 10 CFR 50.59 Summary Report NOC-AE-21003841, Request for Relief from ASME Section Xl Code Requirements for Weld Examinations (Relief Request RR-ENG-3-25)2021-09-23023 September 2021 Request for Relief from ASME Section Xl Code Requirements for Weld Examinations (Relief Request RR-ENG-3-25) NOC-AE-21003832, Supplement to License Amendment Request to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2021-09-0909 September 2021 Supplement to License Amendment Request to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections NOC-AE-21003812, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2021-08-10010 August 2021 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections NOC-AE-21003825, Update of Foreign Ownership, Control, or Influence Information (FOCI)2021-08-0505 August 2021 Update of Foreign Ownership, Control, or Influence Information (FOCI) NOC-AE-21003824, Update Foreign Ownership, Control, or Influence (FOCI)2021-07-29029 July 2021 Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-21003823, Update Foreign Ownership Control or Influence (FOCI)2021-07-28028 July 2021 Update Foreign Ownership Control or Influence (FOCI) NOC-AE-21003820, Nuclear Insurance Protection2021-07-20020 July 2021 Nuclear Insurance Protection NOC-AE-21003819, Inservice Inspection Summary Report - 2RE212021-07-15015 July 2021 Inservice Inspection Summary Report - 2RE21 NOC-AE-21003816, Commitment Change Summary Report2021-06-30030 June 2021 Commitment Change Summary Report NOC-AE-21003814, Technical Specification Bases Control Program2021-06-24024 June 2021 Technical Specification Bases Control Program NOC-AE-21003810, Update Foreign Ownership, Control, or Influence (FOCI)- CPS Energy2021-06-17017 June 2021 Update Foreign Ownership, Control, or Influence (FOCI)- CPS Energy NOC-AE-21003811, Update Foreign Ownership, Control, or Influence (FOCI)- Nrg Energy2021-06-17017 June 2021 Update Foreign Ownership, Control, or Influence (FOCI)- Nrg Energy NOC-AE-21003806, Inservice Inspection Program Plan and Inservice Testing Program Snubber Inservice Test Plan for the Fourth Ten-Year Interval2021-05-20020 May 2021 Inservice Inspection Program Plan and Inservice Testing Program Snubber Inservice Test Plan for the Fourth Ten-Year Interval NOC-AE-21003801, Annual Dose Report for 20202021-04-26026 April 2021 Annual Dose Report for 2020 NOC-AE-21003802, 2020 South Texas Project Electric Generating Station Annual Environmental Operating Report2021-04-26026 April 2021 2020 South Texas Project Electric Generating Station Annual Environmental Operating Report NOC-AE-21003804, Operator Licensing Examination Schedule2021-04-21021 April 2021 Operator Licensing Examination Schedule NOC-AE-21003800, Radioactive Effluent Release Report2021-04-19019 April 2021 Radioactive Effluent Release Report NOC-AE-21003799, Changes to South Texas Project Electric Generating Station (STPEGS) Emergency Plan2021-04-15015 April 2021 Changes to South Texas Project Electric Generating Station (STPEGS) Emergency Plan NOC-AE-21003795, Cycle 22 Core Operating Limits Report2021-04-15015 April 2021 Cycle 22 Core Operating Limits Report NOC-AE-21003796, Update Foreign Ownership, Control, or Influence (FOCI)2021-04-15015 April 2021 Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-21003791, Financial Assurance for Decommissioning - 2021 Update2021-03-31031 March 2021 Financial Assurance for Decommissioning - 2021 Update NOC-AE-21003790, Response to Apparent Violations in NRC Inspection Report 05000498/2020401 and 05000499/2020401: (EA-20-122) (Letter)2021-03-31031 March 2021 Response to Apparent Violations in NRC Inspection Report 05000498/2020401 and 05000499/2020401: (EA-20-122) (Letter) NOC-AE-210037, STP Fire Hazards Analysis Report, Amendment 26 (Redacted)2021-03-30030 March 2021 STP Fire Hazards Analysis Report, Amendment 26 (Redacted) NOC-AE-21003792, STP Fire Hazards Analysis Report, Amendment 26 (Redacted)2021-03-30030 March 2021 STP Fire Hazards Analysis Report, Amendment 26 (Redacted) NOC-AE-200037, License Amendment Request to Revise Technical Specification 3.6.3 to Append a Note and Remove the Index from Technical Specifications2021-03-11011 March 2021 License Amendment Request to Revise Technical Specification 3.6.3 to Append a Note and Remove the Index from Technical Specifications NOC-AE-21003784, Response to Request for Additional Information Regarding 1RE22 Inspection Summary Report for Steam Generator Tubing2021-03-0808 March 2021 Response to Request for Additional Information Regarding 1RE22 Inspection Summary Report for Steam Generator Tubing NOC-AE-21003786, Annual Fitness for Duty Performance Report for 20202021-03-0101 March 2021 Annual Fitness for Duty Performance Report for 2020 NOC-AE-21003785, Evidence of Financial Protection2021-02-23023 February 2021 Evidence of Financial Protection NOC-AE-21003781, Notice Regarding Withdrawal of Funds from Nuclear Decommissioning Trust Subaccounts2021-01-27027 January 2021 Notice Regarding Withdrawal of Funds from Nuclear Decommissioning Trust Subaccounts NOC-AE-21003780, Submittal of Update Foreign Ownership, Control, or Influence (FOCI)2021-01-0707 January 2021 Submittal of Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-20003778, Changes to South Texas Project Electric Generating Station Emergency Plan2020-12-17017 December 2020 Changes to South Texas Project Electric Generating Station Emergency Plan NOC-AE-20003777, STPNOC Concerns Regarding the Proposed Change to the Evaluated Force-on-Force Inspection Guidance During the COVID-19 Public Health Emergency2020-12-10010 December 2020 STPNOC Concerns Regarding the Proposed Change to the Evaluated Force-on-Force Inspection Guidance During the COVID-19 Public Health Emergency NOC-AE-20003766, Supplement to Change Implementation Date for License Amendment Request to Revise the STPEGS Emergency Plan2020-12-0202 December 2020 Supplement to Change Implementation Date for License Amendment Request to Revise the STPEGS Emergency Plan NOC-AE-20003767, Request for a One-Time Exemption from 10 CFR 73, Appendix 8, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-16016 November 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix 8, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic NOC-AE-20003765, Inservice Testing Program Description for the Fourth Ten-Year Interval2020-10-28028 October 2020 Inservice Testing Program Description for the Fourth Ten-Year Interval NOC-AE-20003764, 1 RE22 Inspection Summary Report for Steam Generator Tubing2020-10-0707 October 2020 1 RE22 Inspection Summary Report for Steam Generator Tubing NOC-AE-20003762, Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-374, Revision 0, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil Using the Consolidated Line Item Improvemen2020-09-22022 September 2020 Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-374, Revision 0, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil Using the Consolidated Line Item Improvemen NOC-AE-20003761, Supplement to Exemption Request from 10 CFR 50 Appendix E Due to COVID-19 Pandemic2020-09-10010 September 2020 Supplement to Exemption Request from 10 CFR 50 Appendix E Due to COVID-19 Pandemic NOC-AE-20003760, Update Foreign Ownership. Control. or Influence(FOCI)- Transmittal2020-09-0808 September 2020 Update Foreign Ownership. Control. or Influence(FOCI)- Transmittal 2023-07-11
[Table view] |
Text
Nuclear Operating Company dEetrlc GeneratingStation PC. Box 28 South Texas Project Wadsworth, Texas 77483 .V June 5, 2002 NOC-AE-02001334 File No.: G25 STI: 31451791 U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 South Texas Project Units 1 and 2 Docket Nos. STN 50-498, STN 50-499 Technical Specification Bases Changes Revised South Texas Project Technical Specification Bases pages are attached for your information and for updating of the NRC copy of the Technical Specification's. The attached pages incorporate information regarding the recently approved amendment for 1.4 percent power uprate.
If there are any questions regarding these changes, please contact me at (361) 972-7136.
Scott M. Head Manager, Licensing mkj
Attachment:
Revised Technical Specification Bases Pages B 2-1 and B 3/4 7-1 O:\QUALITYANDULICENSING\TSB\AMENDMENThO2\NOC-AE- 02001334
NOC-AE-02001334 Page 2 of 2 cc:
(paper copy) (electronic copy)
Ellis W. Merschoff A. H. Gutterman, Esquire Regional Administrator, Region IV Morgan, Lewis & Bockius LLP U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 M. T. Hardt/W. C. Gunst Arlington, Texas 76011-8064 City Public Service U. S. Nuclear Regulatory Commission Mohan C. Thadani Attention: Document Control Desk U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike R. L. Balcom Rockville, MD 20852 Reliant Energy, Inc.
Richard A. Ratliff A. Ramirez Bureau of Radiation Control City of Austin Texas Department of Health 1100 West 49th Street C. A. Johnson Austin, TX 78756-3189 AEP - Central Power and Light Company Cornelius F. O'Keefe Jon C. Wood U. S. Nuclear Regulatory Commission Matthews & Branscomb P. 0. Box 289, Mail Code: MN116 Wadsworth, TX 77483 C. M. Canady City of Austin Electric Utility Department 721 Barton Springs Road Austin, TX 78704
ATTACHMENT REVISED BASES PAGES
"SAFETYLIMITS BASES 2.1.1 REACTOR CORE The restrictions of this Safety Limit prevent overheating of the fuel and possible cladding perforation which would result in the release of fission products to the reactor coolant. Overheating of the fuel cladding is prevented by restricting fuel operation to within the nucleate boiling regime where the heat transfer coefficient is large and the cladding surface temperature is slightly above the coolant saturation temperature.
Operation above the upper boundary of the nucleate boiling regime could result in excessive cladding temperatures because of the onset of departure from nucleate boiling (DNB) and the resultant sharp reduction in heat transfer coefficient. DNB is not a directly measurable parameter during operation and therefore THERMAL POWER and reactor coolant temperature and pressure have been related to DNB through the WRB-1 correlation and the WRB-2M correlation. The WRB-1 DNB and WRB-2M correlations have been developed to predict the DNB flux and the location of DNB for axially uniform and nonuniform heat flux distributions. The local DNB heat flux ratio (DNBR) is defined as the ratio of the heat flux that would cause DNB at a particular core location to the local heat flux and is indicative of the margin to DNB.
The DNB design basis is as follows: uncertainties in the WRB-1 and WRB-2M correlations, plant operating parameters, nuclear and thermal parameters, fuel fabrication parameters, and computer codes are considered statistically such that there is at least a 95 percent probability with a 95 percent confidence level that DNBR will not occur on the most limiting fuel rod during Condition I and II events. This establishes a design DNBR value which must be met in plant safety analyses using values of input parameters without uncertainties. In addition, margin has been maintained in the design by meeting safety analysis DNBR limits in performing safety analyses.
The reactor core Safety Limits are established to preclude violation of the following fuel design criteria:
- a. There must be at least a 95% probability at a 95% confidence level (the 95/95 DNB criterion) that the hot fuel rod in the core does not experience DNB; and
- b. There must be at least a 95% probability at a 95% confidence level that the hot fuel pellet in the core does not experience centerline fuel melting.
The reactor core Safety Limits are used to define the various Reactor Protection System (RPS) functions such that the above criteria are satisfied during steady state operation, normal operational transients, and anticipated operational occurrences (AOOs). To ensure that the RPS precludes the violation of the above criteria, additional criteria are applied to the Overtemperature and Overpower AT reactor trip functions. That is, it must be demonstrated that the average enthalpy in the hot leg is less than or equal to the saturation enthalpy and that the core exit quality is within the limits defined by the DNBR correlation. Appropriate functioning of the RPS ensures that, for variations in the Thermal Power, RCS Pressure, RCS average temperature, RCS flow rate, and Al, the reactor core Safety Limits will be satisfied during steady state operation, normal operational transients, and AOOs.
SOUTH TEXAS - UNITS 1 & 2 B 2-1 Unit 1 - Amendment No.
Unit 2 - Amendment No.
01-1862
3/4.7 PLANT SYSTEMS BASES 3/4.7.1 TURBINE CYCLE 3/4.7.1.1 SAFETY VALVES The OPERABILITY of the main steam line Code safety valves ensures that the Secondary System pressure will be limited to within 110% (1413.5 psig) of its design pressure of 1285 psig during the most severe anticipated system operational transient. The maximum relieving capacity is associated with a Turbine trip from 100% RATED THERMAL POWER coincident with an assumed loss of condenser heat sink (i.e., no steam bypass to the condenser).
Five MSSVS, each with an orifice size of 16 in 2, are located on each main steam header, outside containment, upstream of the main steam isolation valves. The specified valve lift settings and relieving capacities are in accordance with the requirements of Section III of the ASME Boiler and Pressure Code, 1971 Edition. The total relieving capacity for all valves on all of the steam lines is 20.65 x 106 lbs/h which is 122% of the total secondary steam flow of 16.94 X 106 lbs/h for the Model E steam generators or 120% of the total secondary steam flow of 17.20 X 106 lbs/hr for the Model A94 steam generators at 100% RATED THERMAL POWER. A minimum of two OPERABLE safety valves per steam generator ensures that sufficient relieving capacity is available for the allowable THERMAL POWER restriction in Table 3.7-1.
STARTUP and/or POWER OPERATION is allowable with safety valves inoperable within the limitations of the ACTION requirements on the basis of the reduction in Secondary Coolant System steam flow and THERMAL POWER required by the reduced Reactor trip settings of the Power Range Neutron Flux channels. The Reactor Trip Setpoint reductions are derived on the following bases:
HiCk= ( 100 -S) WshfrN g )
Q K Where:
Hi 0 = Safety analysis power range high neutron flux setpoint, percent Q = Nominal NSSS power rating of the plant (including reactor coolant pump heat), MWt K = Conversion Factor, 947.82 (BTU/sec)/MWt W, = Minimum total steam flow rate capability of the operable MSSVs on any one steam generator at the highest MSSV opening pressure, including tolerance and accumulation, as appropriate, in Ibm/sec. For example, if the maximum number of inoperable MSSVs on any one steam generator is one, then w. should be a summation of the capacity of the operable MSSVs at the highest operable MSSV operating pressure, excluding the highest capacity MSSV. If the maximum number of inoperable MSSVs per steam generator is three, then ws should be a summation of the capacity of the operable MSSVs at the highest operable MSSV operating pressure, excluding the three highest capacity MSSVs.
hfg = Heat of vaporization for steam at the highest MSSV operating pressure including allowances for tolerance, drift, and accumulation, as appropriate, Btu/Ibm N = Number of loops in the plant.
The calculated values are lowered an additional 9% full power to account for instrument and channel uncertainties.
SOUTH TEXAS - UNITS 1 & 2 B 3/4 7-1 Unit 1 - Amendment No. 01-1862 Unit 2 - Amendment No. 01-1862