NL-15-015, Response to NRC Regulatory Issue Summary 2014-13: Planned Licensing Action Submittals

From kanterella
Jump to navigation Jump to search
Response to NRC Regulatory Issue Summary 2014-13: Planned Licensing Action Submittals
ML15036A028
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 01/30/2015
From: Coyle L
Entergy Corp, Entergy Nuclear Northeast
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-15-015, RIS-14-013
Download: ML15036A028 (5)


Text

Entercqv Nuclear Northeast Indian Point Energy Center Entergy 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Tel (914) 254-6700 Lawrence Coyle Site Vice President NL-15-015 January 30, 2015 U.S. Nuclear Regulatory Commission Document Control Desk 11545 Rockville Pike, TWFN-2 F1 Rockville, MD 20852-2738

SUBJECT:

Response to NRC RIS 2014-13: Planned Licensing Action Submittals Indian Point Nuclear Generating Unit Nos. 2 and 3 Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and -64

REFERENCE:

NRC Regulatory Issue Summary 2014-13 Planned Licensing Action Submittals for All Power Reactor Licensees, dated December 17, 2014 (ML14329A165)

Dear Sir or Madam:

The NRC has issued Regulatory Issue Summary (RIS) 2014-13 requesting licensees to voluntarily provide information regarding the licensing actions that they plan to submit to the NRC for review over the next 3 calendar. years, and power uprate applications that they plan to submit to the NRC for review over the next 5 calendar years.

In accordance with the RIS, if the licensee chooses to provide a voluntary response, the NRC would like to obtain the information within 45 days of the date of the RIS. This letter and its attachment provides Entergy Nuclear Operations, Inc.'s voluntary response to the subject RIS.

Entergy is not planning to submit any power uprate license amendment requests at IP2 and IP3 within the next 5 calendar years. The information provided in this letter may be made public.

There are no new commitments being made in this submittal. If you have any questions or require additional information, please contact Mr. Robert W. Walpole, Regulatory Assurance Manager at (914) 254-6710.

Sincerely,

Attachment:

Table of Estimated Licensing Actions for Indian Point Unit Nos. 2 and 3 AooI

NL-15-015 Docket Nos. 50-247 and 50-286 Page 2 of 2 cc: Mr. Daniel H. Dorman, Regional Administrator, NRC Region I Mr. Douglas Pickett, NRC, Sr. Project Manager, Division of Reactor Licensing Ms. Bridget Frymire, New York State Dept. of Public Service Mr. John B. Rhodes, President and CEO NYSERDA NRC Resident Inspector's Office

ATTACHMENT TO NL-15-015 TABLE OF ESTIMATED LICENSING ACTIONS FOR INDIAN POINT UNIT NOS. 2 AND 3 DOCKET NOS. 50-247 AND 50-286 ENTERGY NUCLEAR OPERATIONS, INC.

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 DOCKET NOS. 50-247 AND 50-286

NL-15-015 Attachment Page 1 of 2 TABLE OF ESTIMATED LICENSING ACTIONS INDIAN POINT UNITS 2 AND 3 DOCKET NOS. 50-247 AND 50-286 LICENSING LICENSING ACTION LICENSING PROJECTED OUTAGE COMMENTS (AS ACTION ACTION SUBMITTAL DATE RELATED? NEEDED)

NUMBER DESCRIPTION IF SO, DATE NEEDED 1 IP3 License Amendment TSTF-51 addition of January, 2016 No Request (LAR) "recently" to action (10 CFR 50.90) statements on irradiated fuel.

2 IP3 License Amendment Add EDG FO margin to September, 2015 No Request (LAR) current TS (10 CFR 50.90) requirements.

3 IP2 and 3 - License TSTF 412 -Actions for June, 2016 No Amendment loss of a single steam Request (LAR) supply to TD AFW (10 CFR 50.90 pump.

4 IP2 and 3 - License TSTF 471 remove June, 2015 No Amendment suspension of core Request (LAR) alterations from actions.

(10 CFR 50.90 5 IP-2 License Amendment Revise Technical November, 2015 Yes, needed by Request (LAR) Specifications for Spent December, 2016 (10 CFR 50.90) Fuel Pit Storage to allow credit for inserted neutron absorber panels.

NL-15-015 Attachment Page 2 of 2 6 IP-3 License Amendment Revise Technical February, 2015 Yes, needed by Request (LAR) Specifications for September, 2015 (10 CFR 50.90) Reactor Coolant System Pressure and Temperature Limits and Low Temperature Overpressure Protection System Requirements 7 IP-3 License Amendment Revise Technical January, 2016 Yes, needed by Request (LAR) Specification Appendix January, 2017 (10 CFR 50.90) C - Inter-Unit Fuel Transfer initial average enrichment LCO for intact fuel assemblies.