Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents (Order Number EA-12-050)
ML12305A375
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 10/29/2012
From: Richard Anderson
NextEra Energy Duane Arnold
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NG-12-0427, EA-12-050
Download: ML12305A375 (2)


Text

NEXTera M ENERGV~ """-'

~ DUANE ARNOLD October 29, 2012 NG-12-0427 10 CFR 2.202 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Duane Arnold Energy Center Docket No. 50-331 Renewed Op. License No. DPR-49 NextEra Energy Duane Arnold, LLC's Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents (Order Number EA-12-050)

References:

1. NRC Order Number EA-12-050, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents (ML12054A694)
2. NRC Interim Staff Guidance JLD-ISG-2012-02, Compliance with Order EA-12-050, Reliable Hardened Containment Vents, Revision 0, dated August29,2012 (ML12229A475)

On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission")

issued an order (Reference 1) to NextEra Energy Duane Arnold, LLC (hereafter, NextEra Energy Duane Arnold). Reference 1 was immediately effective and directs NextEra Energy Duane Arnold to have a reliable hardened vent (RHV) to remove decay heat and maintain control of containment pressure within acceptable limits following events that result in the loss of active containment heat removal capability or prolonged station blackout (S80). Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final interim staff guidance (Reference 2) is dated August 29, 2012 The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2. This report confirms NextEra Energy Duane Arnold has received Reference 2 and is in the process of evaluating the guidance for the purpose of having a reliable hardened vent (RHV) to remove decay heat and maintain control of containment pressure within acceptable limits following events that result in the loss of active containment heat removal capability or prolonged station blackout (S80) as described in Attachment 2 of Reference 1.

NextEra Energy Duane Arnold, LLC, 3277 DAEC Road, Palo, IA 52324

Document Control Desk NG-12-0427 Page 2 of 2 Reference 2, Section 4.0 contains the specific reporting requirements for the initial status report. The following information provides the status pursuant to Section 4.0 of Reference 2.

Major activities completed during this reporting period:

  • Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.

Planned activities for the next six months:

  • Development and submittal of the overall integrated plan.

Technical difficulties encountered that could affect the ability to provide the licensee's February 28,2013, submittal:

  • None at this time.

Project milestones schedule through completion of installation and testing:

  • A project milestones schedule will be provided with the overall integrated plan.
  • Implementation of the order will be completed for the Duane Arnold Energy Center prior to startup from Refueling Outage (RFO) 25 (Fall 2016).

This letter makes no new commitments or changes to any existing commitments.

If you have any questions or require additional information, please contact Ken Putnam at 319-851-7238.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on October 29,2012

'7~cfA "-_

Ri~d L. Anderson ~

Vice President, Duane Arnold Energy Center NextEra Energy Duane Arnold, LLC