Ltr. 12/17/2009 Duane Arnold Re Confirmation of Initial Operator License Examinations
ML093550289
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 12/17/2009
From: Hironori Peterson
Division Reactor Projects III
To: Costanzo C R
NextEra Energy Duane Arnold
References
NG-08-0877
Download: ML093550289 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 December 17, 2009 Mr. Christopher R. Costanzo Vice President

NextEra Energy Duane Arnold, LLC

3277 DAEC Road

Palo, IA 52324-9785

SUBJECT:

DUANE ARNOLD ENERGY CENTER CONFIRMATION OF INITIAL OPERATOR LICENSE EXAMINATIONS

Dear Mr. Costanzo:

In a letter dated November 20, 2008 (NG-08-0877), your staff requested we schedule an initial

license operator examination during the week of June 20, 2011, or on the alternate week of

June 26, 2011. We have tentatively scheduled the requested examination to start during the

alternate requested week of June 26, 2011. Your staff also requested we schedule an initial

license operator examination during the week of April 8, 2013. We have tentatively scheduled the requested examination to start during the specified week of April 8, 2013. On-site validation

of these examinations is tentatively scheduled to occur approximately three weeks before the

examination week. In the unlikely event that we are unable to support an examination during the scheduled weeks, we will inform you immediately upon discovery of such conditions and

make arrangements to administer the examination at a mutually acceptable date.

We understand that your staff will develop the examinations unless we determine the need for

the NRC to develop an examination. The letter we received indicated that more than nine

applicants were being considered for the examinations. The examinations have been

scheduled for two weeks to accommodate more than nine applicants. If the number of

applicants should decrease below ten applicants, please inform us as soon as possible, as this

will result in a schedule change. Please inform us at your earliest opportunity if you discover you need to change the scheduled date for the examination.

A supplementary letter will be sent to the tr aining department approximately 120 days prior to each of these initial examinations. The letters will inform the training department of the chief

examiner=s name, outline examination security expecta tions, list the materials required by the NRC to conduct the examination, reconfirm the examination dates, and reconfirm the number of

candidates you have in the training program.

If you have any questions concerning this

information, please contact Mr. Dell McNeil of my staff at 630-829-9737.

C. Costanzo

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be

available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PAR S) component of NRC's Agencywide Documents Access and Management System (ADAMS), a ccessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely, /RA/ Hironori Peterson, Chief

Operations Branch Division of Reactor Projects Docket No. 50-331

License No. DPR-49

cc: Distribution via ListServ

C. Costanzo

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be

available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PAR S) component of NRC's Agencywide Documents Access and Management System (ADAMS), a ccessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely, /RA/ Hironori Peterson, Chief

Operations Branch Division of Reactor Projects Docket No. 50-331

License No. DPR-49

cc: Distribution via ListServ

DISTRIBUTION

Susan Bagley

RidsNrrDorlLpl3-1 Resource

RidsNrrPMDuaneArnold Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Steven Orth

Jared Heck

Allan Barker

Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley

Tammy Tomczak

DOCUMENT NAME: G:\DRS\Work in Progress\DUA 121709 DRS OL Exam Confirmation.doc Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the box " C" = Copy w/o attach/encl " E" = Copy with attach/encl "" = No copy N O FFICE R III:DRS

R III:DRS

R III:DRS

N AME J Kweiser:co

D McNeil H Peterson

DATE 12/15/09 12/15/09 12/17/09

OFFICIAL RECORD COPY