Units 3 and 4 Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule, and the Unit 3 Completion Schedule for Inspections, Tests, and Analyses (ITA)
ML19330D119
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 11/22/2019
From: Yox M
Southern Nuclear Operating Co
To: Ho Nieh
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML19330D118 List:
References
ND-19-1374
Download: ML19330D119 (4)


Text

Southern NucIear Michael J. Yox 7825 River Road Regulatory Affairs Director Waynesboro, Georgia 30830 Vogtle 3 & 4 706 848 6459 tel November 22, 2019 ND-19-1374 10CFR 52.99(a)

Docket Nos.;52-025 52-026 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Mr. Ho Nieh Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant - Units 3 and 4 Combined License(COL) Operational Programs and Other License Conditions Implementation Schedule, and the Unit 3 Completion Schedule for Inspections, Tests, and Analyses (ITA)

Ladies and Gentlemen:

The U.S. Nuclear Regulatory Commission (NRC)issued Combined Licenses(COLs) NPF-91 and NPF-92 to Southern Nuclear Operating Company(SNC) pursuant to Title 10 of the Code of Federal Regulations(10 CFR)Section 52.97, "Issuance of combined licenses," on February 10, 2012.

Two license conditions require SNC to submit, no later than twelve months after issuance of the COL, the following:

  • A schedule for implementation of the operational programs listed in the Final Safety Analysis Report Table 13.4-201, including the associated estimated date for initial loading of fuel(COL section 2.D.(11))
  • A schedule for implementation of the license conditions listed in COL section 2.D.(12)(f)1-9 In accordance with the license conditions, the schedules shall be updated every six months until twelve months before scheduled fuel loading, and every month thereafter until each license condition has been fully implemented.

U. S. Nuclear Regulatory Commission ND-19-1374 Page 2 of 4 SNC is also required to submit, with similar frequency, its schedule for completing the Inspections, Tests, or Analyses (ITA)for the Nuclear Regulatory Commission approved Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) per 10 CFR 52.99(a). SNC intends to submit the Unit 3 updates to the ITAAC schedule every 30 days until the final notification is provided to the NRC under 10 CFR 52.99(c)(1). SNC will continue to provide the Unit 4 ITA completion schedules on the current 6 month periodicity until one year prior to the initial loading of fuel at which time the Unit 4 ITA schedule will be submitted monthly.

Enclosure 1 contains the Unit 3 and 4 COL Operational Programs and Other License Conditions Implementation Schedule. Enclosure 2 contains the Unit 3 Preoperational Test Procedure Completion Schedule. Enclosure 3 contains the Unit 3 Inspections, Tests, and Analyses Completion Schedule. The information provided in the enclosures is current as of October 26, 2019. As is typical with a construction project, the schedule information is dynamic in nature.

The schedule information provided in the enclosures is considered confidential commercial information and exempt from mandatory public disclosure pursuant to the provisions of 10 CFR 2.390(a)(4) and 10 CFR 9.17(a)(4). Following the approach described in SECY-06-0114, no additional withholding determination is needed as the schedule information was demonstrated to be confidential commercial information based on the schedule updates provided to the NRC on February 8, 2019, Agencywide Documents Access and Management System (ADAMS)

Accession Number ML19039A264, and on October 6, 2017, ADAMS Accession Number ML17279A661. Accordingly, the enclosures to this letter should be withheld from public disclosure.

This letter contains no regulatory commitments.

Should you have questions regarding the enclosed information, please contact Kelli Roberts at (706) 848-6991.

Respectfully submitted, SOUTHERN NUCLEAR OPERATING COMPANY Michael J. Yox;;^

Regulatory Affairs ^ifector Vogtle 3 & 4 MJY/KJD/sfr Enclosures; 1. COL Operational Programs and Other License Conditions Implementation Schedule {Withhold from Public Disclosure}

2. Preoperational Test Procedure Completion Schedule (Withhold from Public Disclosure}
3. Unit 3 ITAAC Closure schedule(Withhold from Public Disclosure}

U. S. Nuclear Regulatory Commission ND-19-1374 Page 3 of 4 cc:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III (w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier(w/o enclosures)

Mr. D. H. Jones(w/o enclosures)

Mr. G. Chick Mr. M. Page Mr. P. Martino Mr. M. J. Yox Mr. A. 8. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Mr. 8. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 Nuclear Requlatorv Commission Mr. W. Jones (w/o enclosures)

Mr. H. K. Nieh Mr. C. P. Patel Mr. G. J. Khouri Ms. 8. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. V. Hall Mr. G. Armstrong Ms. T. Lamb Mr. M. Webb Mr. T. Fredette Mr. C. Weber Mr. 8. Smith Mr. C. Santos State of Georgia Mr. R. Dunn (w/o enclosures 1, 2, and 3)

U. S. Nuclear Regulatory Commission ND-19-1374 Page 4 of 4 Qqlethorpe Power Corporation Mr. R. B. Brinkman (w/o enclosures 1,2 and 3)

Mr. E. Rasmussen (w/o enclosures 1, 2 and 3)

Municipal Electric Authority of Georgia Mr. J. E. Fuller (w/o enclosures 1,2 and 3)

Mr. S. M. Jackson (w/o enclosures 1,2 and 3)

Daiton Utilities Mr. T. Bundros(w/o enclosures 1,2 and 3)

Westinahouse Eiectric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. C. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. Z. S. Harper Mr. J. L. Coward Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc. (w/o enclosures 1,2 and 3)

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc. (w/o enclosures 1,2 and 3)

Mr. S. Roetger, Georgia Public Service Commission (w/o enclosures 1,2 and 3)

Ms. S. W. Kernlzan, Georgia Public Service Commission (w/o enclosures 1,2 and 3)

Mr. K. C. Greene, Troutman Sanders(w/o enclosures 1,2 and 3)

Mr. S. Blanton, Balch Bingham NDDocumentinBox@duke-energy.com, Duke (w/o enclosures 1,2 and 3)

Mr. S. Franzone, Florida Power & Light(w/o enclosures 1,2 and 3)