ND-19-0354, Unit 4, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.3.09.03.ii (Index Number 424)

From kanterella
(Redirected from ND-19-0354)
Jump to navigation Jump to search
Unit 4, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.3.09.03.ii (Index Number 424)
ML19105B144
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 04/11/2019
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-19-0354
Download: ML19105B144 (14)


Text

^Southern Nuclear Michael J. Yox Regulatory Affairs Director 7825 River Road Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel APR 1 1 2019 Docket Nos.: 52-025 52-026 ND-19-0354 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.3.09.03.ii [Index Number 4241 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of April 05, 2019, Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Uncompleted Inspections Tests Analyses and Acceptance Criteria (ITAAC) Item 2.3.09.03.ii

[Index Number 424] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing ITAAC 2.3.09.03.11 [Index Number 424]. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI-08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed.

All ITAAC will be fully completed and all Section 52.99(c)(3) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575

U.S. Nuclear Regulatory Commission ND-19-0354 Page 2 of 4 Respectfully submittecL Mfchael J. Yox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.3.09.03.11 [Index Number 424]

MJY/DLW/sfr

U.S. Nuclear Regulatory Commission ND-19-0354 Page 3 of 4 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. D. A. Best(w/o enclosures)

Mr. D. L. McKinney(w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones(w/o enclosures)

Mr. J. B. Klecha Mr. G. Chick Mr. M. J. Vox Mr. A. 8. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. W. A. Sparkman Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Ms. K. M. Stacy Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reaulatorv Commission Mr. W.Jones(w/o enclosures)

Mr. F. D. Brown Ms. J. M. Heisserer Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. I. Cozens Mr. J. Gaslevic Mr. V. Hall Qqiethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson

U.S. Nuclear Regulatory Commission ND-19-0354 Page 4 of 4 Dalton Utilities Mr. T. Bundros Westinahouse Electric Company. LLC Dr. L. Oriani(w/o enclosures)

Mr. D. C. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Ms. J. Monahan Mr. J. L. Coward Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kemizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-19-0354 Enclosure Page 1 of 10 Southern Nuclear Operating Company ND-19-0354 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.3.09.03.11 [Index Number 424]

U.S. Nuclear Regulatory Commission ND-19-0354 Enclosure Page 2of 10 ITAAC Statement Desion Commitment

3. The VLB provides the nonsafety-related function to control the containment hydrogen concentration for beyond design basis accidents.

4.a) Controls exist in the MCR to cause the components identified in Table 2.3.9-2 to perform the listed function.

5. Displays of the parameters identified in Table 2.3.9-1 can be retrieved in the MCR.

I nsoections/Tests/Analvses i) Inspection for the number of igniters will be performed.

ii) Operability testing will be performed on the igniters.

Testing will be performed on the igniters using the controls in the MCR.

Inspection will be performed for retrievability of the displays identified in Table 2.3.9-1 in the MCR.

Acceptance Criteria i) At least 66 hydrogen igniters are provided inside containment at the locations specified in Table 2.3.9-2.

ii) The surface temperature of the igniter meets or exceeds 1700°F.

Controls in the MCR operate to energize the igniters Displays identified in Table 2.3.9-1 can be retrieved in the MCR.

ITAAC Completion Description This ITAAC requires testing and inspections be performed to verify that the Containment Hydrogen Control System (VLB) provides the nonsafety-related function to control the containment hydrogen concentration for beyond design basis accidents by ensuring that the required number of hydrogen igniters are installed in the appropriate locations as specified by VEGP Combined License(COL)Appendix C Table 2.3.9-2(Attachment A)and that the surface temperature of the igniters meets or exceeds 1700°F. This ITAAC also verifies that controls exist in the Main Control Room (MCR)to cause the components identified in COL Appendix C Table 2.3.9-2 (Attachment A)to perform the listed function and that displays of the parameters identified in COL Appendix C Table 2.3.9-1 (Attachment B)can be retrieved in the MCR.

if At least 66 hvdrooen ioniters are provided inside containment at the locations specified in Table 2.3.9-2.

U.S. Nuclear Regulatory Commission ND-19-0354 Enclosure Page 3 of 10 An Inspection Is performed In accordance with Unit 3 and Unit 4 Inspection procedure SV3-VLS-ITR-XXXX and SV4-VLS-ITR-XXXX (References 1 and 2)to verify that at least 66 hydrogen Igniters are provided Inside containment at the locations specified In Attachment A.

The Inspection Is conducted by performing a walk down of the Installed hydrogen Igniters to verify the correct number of hydrogen Igniters are Installed and that they are all In the proper location. The results of the Inspection verify that for Unit 3 and Unit 4 there are at least 66 hydrogen Igniters provided Inside containment at the locations specified In Table 2.3.9-2.

II) The surface temperature of the Igniter meets or exceeds 1700°F.

Testing Is performed In accordance with Unit 3 and Unit 4 preoperatlonal test procedures 3-VLS-ITPP-501 and 4-VLS-ITPP-501 (References 3 and 4)to verify that the surface temperature of the Igniter meets or exceeds 1700°F.

Testing begins by Installing appropriate personnel protection barriers and closing the power supply breakers for the hydrogen Igniters and control cabinets. Each hydrogen Igniter group control Is placed to ON and the temperature of each Igniter Is taken and verified to meet acceptance criteria.

The results of the testing on Unit 3 and Unit 4 verifies the surface temperature of each Igniter meets or exceeds 1700°F.

Controls In the MGR operate to enerolze the lonlters Testing Is performed In accordance with Unit 3 and Unit 4 preoperatlonal test procedures 3-VLS-ITPP-501 and 4-VLS-ITPP-501 (References 3 and 4)to verify that controls In the MGR operate to energize the Igniters.

Testing Is performed at an operator work station In Unit 3 and Unit 4 MGR and places the hydrogen Igniters controls to GN. All of the Igniters listed In Attachment A are verified to energize by measuring the temperature which Is performed by Item II) above.

Dlsolavs Identified In Table 2.3.9-1 can be retrieved In the MGR.

An Inspection Is performed In accordance with the Unit 3 and Unit 4 component test package work orders SNC922139 and SNGXXXXXX (References 5 and 6)for VLS Indication verifications, and visually confirms that when each of the displays of parameters Identified In Attachment B Is summoned at an MGR workstation, the summoned plant parameter appears on a display monitor at that MGR workstation.

The completed test and Inspection results(References 1 through 6), confirm that at least 66 hydrogen Igniters are provided inside containment at the locations specified In Table 2.3.9-2, that the surface temperature of the Igniter meets or exceeds 1700°F, that controls In the MGR operate to energize the Igniters, and that the displays Identified In Table 2.3.9-1 can be retrieved In the MGR.

References 1 through 6 are available for NRG Inspection as part of Unit 3 and Unit 4ITAAG Gompletlon Packages(Reference 7 and 8).

U.S. Nuclear Regulatory Commission ND-19-0354 Enclosure Page 4 of 10 List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company(SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

References favailable for NRG inspection)

1. SV3-VLS-ITR-XXXX,"Hydrogen Igniter Location Verification"
2. SV4-VLS-ITR-XXXX,"Hydrogen Igniter Location Verification"
3. 3-VLS-ITPP-501,"Containment Hydrogen Control System Preoperational Test Procedure"
4. 4-VLS-ITPP-501,"Containment Hydrogen Control System Preoperational Test Procedure"
5. SNC922139,"Containment Hydrogen Control System Indication Verifications- ITAAC: SV3-2.3.09.03.ii Item 5"
6. SNCXXXXXX,"Containment Hydrogen Control System Indication Verifications- ITAAC:

SV4-2.3.09.03.ii Item 5"

7. 2.3.09.03.ii-U3-CP-Rev 0, ITAAC Completion Package
8. 2.3.09.03.ii-U4-CP-Rev 0, ITAAC Completion Package
9. NEI 08-01,"Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"

U.S. Nuclear Regulatory Commission ND-19-0354 Enclosure Page 5 of 10 Attachment A COL Appendix C Table 2.3.9-2 Equipment Tag Number Function Power Group Location Room No.

Name Number Hydrogen VLS-EH-01 Energize 1 Tunnel 11204 Igniter 01 connection loop compartments Hydrogen VLS-EH-02 Energize 2 Tunnel 11204 Igniter 02 connection loop compartments Hydrogen VLS-EH-03 Energize 1 Tunnel 11204 Igniter 03 connection loop compartments Hydrogen VLS-EH-04 Energize 2 Tunnel 11204 Igniter 04 connection loop compartments Hydrogen VLS-EH-OS Energize 1 Loop 11402 Igniter 05 compartment 02 Hydrogen VLS-EH-06 Energize 2 Loop 11502 Igniter 06 compartment 02 Hydrogen VLS-EH-07 Energize 2 Loop 11402 Igniter 07 compartment 02 Hydrogen VLS-EH-08 Energize 1 Loop 11502 Igniter 08 compartment 02 Hydrogen VLS-EH-09 Energize 1 In- 11305 Igniter 09 containment refueling water storage tank (IRWST) sparger side Hydrogen VLS-EH-10 Energize 2 IRWST sparger 11305 Igniter 10 side Hydrogen VLS-EH-11 Energize 2 Loop 11401 Igniter 11 compartment 01

U.S. Nuclear Regulatory Commission ND-19-0354 Enclosure Page 6 of 10 Attachment A(con't)

Equipment Tag Number Function Power Group Location Room No.

Name Number Hydrogen VLS-EH-12 Energize 1 Loop 11501 Igniter 12 compartment 01 Hydrogen VLS-EH-13 Energize 1 Loop 11401 Igniter 13 compartment 01 Hydrogen VLS-EH-14 Energize 2 Loop 11501 Igniter 14 compartment 01 Hydrogen VLS-EH-15 Energize 2 IRWST vacuum 11305 Igniter 15 breaker vents Hydrogen VLS-EH-16 Energize 1 IRWST vacuum 11305 Igniter 16 breaker vents Hydrogen VLS-EH-17 Energize 2 Northeast 11207 Igniter 17 valve room Hydrogen VLS-EH-18 Energize 1 Northeast 11207 Igniter 18 accumulator room Hydrogen VLS-EH-19 Energize 2 East valve 11208 Igniter 19 room Hydrogen VLS-EH-20 Energize 2 Southeast 11206 Igniter 20 accumulator room Hydrogen VLS-EH-21 Energize 1 Southeast 11206 Igniter 21 valve room Hydrogen VLS-EH-22 Energize 1 Lower 11400 Igniter 22 compartment area (core makeup tank

[CMT]and valve area)

Hydrogen VLS-EH-23 Energize 2 Lower 11400 Igniter 23 compartment area (CMT and valve area)

U.S. Nuclear Regulatory Commission ND-19-0354 Enclosure Page 7 of 10 Attachment A (con't)

Equipment Tag Number Function Power Group Location Room No.

Name Number Hydrogen VLS-EH-24 Energize 2 Lower 11400 igniter 24 compartment area (CMT and valve area)

Hydrogen VLS-EH-25 Energize 2 Lower 11400 Igniter 25 compartment area(CMT and valve area)

Hydrogen VLS-EH-26 Energize 2 Lower 11400 Igniter 26 compartment area (CMT and valve area)

Hydrogen VLS-EH-27 Energize 1 Lower 11300 Igniter 27 compartment area(CMT and valve area)

Hydrogen VLS-EH-28 Energize 1 Lower 11400 Igniter 28 compartment area (CMT and valve area)

Hydrogen VLS-EH-29 Energize 1 Lower 11400 Igniter 29 compartment area (CMT and valve area)

Hydrogen VLS-EH-30 Energize 2 Lower 11403 Igniter 30 compartment area(CMT and valve area)

Hydrogen VLS-EH-31 Energize 1 Lower 11400 Igniter 31 compartment area(CMT and valve area)

Hydrogen VLS-EH-32 Energize 1 Lower 11400 Igniter 32 compartment area (CMT and valve area)

U.S. Nuclear Regulatory Commission ND-19-0354 Enclosure Page 8 of 10 Attachment A(con't)

Equipment Tag Number Function Power Group Location Room No.

Name Number Hydrogen VLS-EH-33 Energize 2 North CVS 11209 Igniter 33 equipment room Hydrogen VLS-EH-34 Energize 1 North CVS 11209 Igniter 34 equipment room Hydrogen VLS-EH-35 Energize 1 IRWST hooded 11500 Igniter 35 vents Hydrogen VLS-EH-36 Energize 2 IRWST hooded 11500 Igniter 36 vents Hydrogen VLS-EH-37 Energize 1 IRWST hooded 11500 Igniter 37 vents Hydrogen VLS-EH-38 Energize 2 IRWST hooded 11500 Igniter 38 vents Hydrogen VLS-EH-39 Energize 1 Upper 11500 Igniter 39 compartment lower region Hydrogen VLS-EH-40 Energize 2 Upper 11500 Igniter 40 compartment lower region Hydrogen VLS-EH-41 Energize 2 Upper 11500 Igniter 41 compartment lower region Hydrogen VLS-EH-42 Energize 1 Upper 11500 Igniter 42 compartment lower region Hydrogen VLS-EH-43 Energize 1 Upper 11500 Igniter 43 compartment lower region Hydrogen VLS-EH-44 Energize 1 Upper 11500 Igniter 44 compartment lower region Hydrogen VLS-EH-45 Energize 2 Upper 11500 Igniter 45 compartment lower region Hydrogen VLS-EH-46 Energize 2 Upper 11500 Igniter 46 compartment lower region

U.S. Nuclear Regulatory Commission ND-19-0354 Enclosure Page 9 of 10 Attachment A(con't)

Equipment Tag Number Function Power Group Location Room No.

Name Number Hydrogen VLS-EH-47 Energize 1 Upper 11500 Igniter 47 compartment lower region Hydrogen VLS-EH-48 Energize 2 Upper 11500 Igniter 48 compartment lower region Hydrogen VLS-EH-49 Energize 1 Pressurizer 11503 Igniter 49 compartment Hydrogen VLS-EH-50 Energize 2 Pressurizer 11503 Igniter 50 compartment Hydrogen VLS-EH-51 Energize 1 Upper 11500 Igniter 51 compartment mid-region Hydrogen VLS-EH-52 Energize 2 Upper 11500 Igniter 52 compartment mid-region Hydrogen VLS-EH-53 Energize 2 Upper 11500 Igniter 53 compartment mid-region Hydrogen VLS-EH-54 Energize 1 Upper 11500 Igniter 54 compartment mid-region Hydrogen VLS-EH-55 Energize 1 Refueling 11504 Igniter 55 cavity Hydrogen VLS-EH-56 Energize 2 Refueling 11504 Igniter 56 cavity Hydrogen VLS-EH-57 Energize 2 Refueling 11504 Igniter 57 cavity Hydrogen VLS-EH-58 Energize 1 Refueling 11504 Igniter 58 cavity Hydrogen VLS-EH-59 Energize 2 Pressurizer 11503 Igniter 59 compartment Hydrogen VLS-EH-60 Energize 1 Pressurizer 11503 Igniter 60 compartment Hydrogen VLS-EH-61 Energize 1 Upper 11500 Igniter 61 compartment-upper region

U.S. Nuclear Regulatory Commission ND-19-0354 Enclosure Page 10 ol 10 Attachment A (con't)

Equipment Tag Number Function Power Group Location Room No.

Name Number Hydrogen VLS-EH-62 Energize 2 Upper 11500 Igniter 62 compartment-upper region Hydrogen VLS-EH-63 Energize 1 Upper 11500 Igniter 63 compartment-upper region Hydrogen VLS-EH-64 Energize 2 Upper 11500 Igniter 64 compartment-upper region Hydrogen VLS-EH-65 Energize 1 IRWST roof 11500 Igniter 65 vents Hydrogen VLS-EH-66 Energize 2 IRWST roof 11500 Igniter 66 vents Attachment B COL Appendix C Table 2.3.9-1 Equipment Tag No. Display Containment Hydrogen Monitor VLS-001 Yes Containment Hydrogen Monitor VLS-002 Yes Containment Hydrogen Monitor VLS-003 Yes