Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.6.02.02c (Index Number 595)
ML18127A006
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 05/04/2018
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-18-0640
Download: ML18127A006 (7)


Text

Michael J. Yox 7825 River Road jtk. Southern Nuclear Regulatory Affairs Director Vogtle 3 & 4 Waynesboro, GA 30830 706-848-6459 tel 410-474-8587 cell myox @southernco.com MAY 0 4 2018 Docket Nos.: 52-025 52-026 ND-18-0640 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Corrimjsslon Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.6.02.02c [Index Number 5951 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of May 1, 2018, Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.6.02.02c [Index Number 595]

has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.02.02c [Index Number 595]

MJY/PGL/amw

U.S. Nuclear Regulatory Commission ND-18-0640 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. M. D. Rauckhorst (w/o enclosures)

Mr. M. D. Meier Mr. D. H. Jones (w/o enclosures)

Mr. D. L. McKinney Mr. M. J. Yox Mr. D. L. Fulton Mr. J. B. Klecha Mr. G. Chick Mr. F. H. Willis Ms. A. L. Pugh Mr. A. 8. Parton Mr. W. A. Sparkman Mr. C. E. Morrow Ms. K. M. Stacy Mr. M. K. Washington Mr. J. P. Redd Ms. A. C. Chamberlain Mr. D. R. Culver Mr. T. G. Petrak Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reaulatorv Commission Mr. W. Jones (w/o enclosures)

Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. N. D. Karlovich Mr. A. J. Lerch Mr. C. J. Even Mr. F. D. Brown Mr. B. J. Kemker Ms. A. E. Rivera-Varona Ms. L. A. Kent Mr. P. B. Donnelly Ms. N. C. Coovert Qqiethorpe Power Corporation Mr. R. B. Brinkman

U.S. Nuclear Regulatory Commission ND-18-0640 Page 3 of 3 Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinahouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. C. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. D. Hawkins Ms. J. Monahan Mr. J. L. Coward Ms. N. E. Deangelis Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-18-0640 Enclosure Page 1 of 4 Southern Nuclear Operating Company ND-18-0640 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.02.02c [Index Number 595]

U.S. Nuclear Regulatory Commission ND-18-0640 Enclosure Page 2 of 4 ITAAC Statement Design Commitment 2.c) Each EDS load group 1, 2,3, and 4 inverter supplies the corresponding ac load.

Insoections/Tests/Analvses Testing of each as-built inverter will be performed by applying a simulated or real load, or a combination of simulated or real loads, equivalent to a resistive load greater than 55 kW.

Acceotance Criteria Each inverter provides a line-to-line output voltage of 208 +/- 2% Vat a frequency of 60 +/- 0.5%

Hz.

ITAAC Completion Description Testing is performed in accordance with Unit 3 and Unit 4 component test package work orders (References 1 and 2) to demonstrate that each Non-Class 1E direct current (dc) and Uninterruptible Power Supply System (EDS) load group 1, 2,3, and 4 inverter identified in the Combined License (COL) Appendix C, Table 2.6.2-2 (Attachment A) supplies its corresponding alternating current (ac) load.

A load test is performed on each EDS inverter by applying a simulated load greater than the inverter design capacity of 55 kilowatts (kW). Inverteroutput voltage, frequency, and power are continuously monitored during the test and after stabilization of load, recorded on data sheets included in the component test package work orders (References 1 and 2). Output voltage is verified to meet the specified acceptance criteria of 208 +/- 2% Volts (V) at a frequency of 60 +/-

0.5% Hertz (Hz) with the specified load applied. The recorded voltage and frequency values are identified in Attachment A for each EDS inverter.

The Unit 3 and Unit 4 component test results confirm that each inverter provides a line-to-line output voltage of 208 +/- 2% V at a frequency of 60 +/- 0.5% Hz.

The Unit 3 and Unit4 component test package work orders (References 1 and 2, respectively) are available for NRC inspection as part of the Unit 3 and Unit 4 ITAAC 2.6.02.02c Completion Packages (References 3 and 4, respectively).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

U.S. Nuclear Regulatory Commission ND-18-0640 Enclosure Page 3 of 4 References (available for NRG inspection)

1. SNC921194, Rev. 0, "EDS Inverter Frequency and Voltage Test - ITAAC: SV3-2.6.02.02c"
2. SNCXXXXXX, Rev x, "EDS Inverter Frequency and Voltage Test - ITAAC: SV4-2.6.02.02c"
3. 2.6.02.02c-U3-CP-Rev 0, ITAAC Completion Package
4. 2.6.02.02c-U4-CP-Rev 0, ITAAC Completion Package
5. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"

U.S. Nuclear Regulatory Commission ND-18-0640 Enclosure Page 4 of 4 Attachment A System: Non-Class 1E do and Uninterruptible Power Supply System Load Bank Voltage and Unit ^Component Name *Tag No.

Frequency XXXV 3 Load Group 1 Inverter EDS1-DU-1 YYYHz XXXV 3 Load Group 2 Inverter EDS2-DU-1 YYYHz XXXV 3 Load Group 3 Inverter EDS3-DU-1 YYYHz XXXV 3 Load Group 4 Inverter EDS4-DU-1 YYYHz XXXV 4 Load Group 1 Inverter EDS1-DU-1 YYYHz XXXV 4 Load Group 2 Inverter EDS2-DU-1 YYYHz XXXV 4 Load Group 3 Inverter EDS3-DU-1 YYYHz XXXV 4 Load Group 4 Inverter EDS4-DU-1 YYYHz Notes:

  • Excerpt from COL Appendix C, Table 2.6.2-2