ND-18-0612, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item E.3.9.08.01.02 (Index Number 871)

From kanterella
(Redirected from ND-18-0612)
Jump to navigation Jump to search
Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item E.3.9.08.01.02 (Index Number 871)
ML18131A238
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 05/11/2018
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ITAAC E.3.9.08.01.02, ND-18-0612
Download: ML18131A238 (6)


Text

Michael J. Yox 7825 River Road Southern Nuclear Regulatory Affairs Director Waynesboro, GA 30830 Vogtie 3 & 4 706-848-6459 tei 410-474-8587 ceii myox@southernco.com MAY I f 2018 Docket Nos.: 52-025 52-026 ND-18-0612 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtie Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item E.3.9.08.01.02 [Index Number 8711 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of April 24, 2018, Vogtie Electric Generating Plant (VEGP) Unit 3 and IJnit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item E.3.9.08.01.02 [Index Number 871] has not been completed greater than 225-days priorto initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Director Vogtie 3 &4

Enclosure:

Vogtie Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC E.3.9.08.01.02 [Index Number 871]

MJY/LBP/amw

U.S. Nuclear Regulatory Commission ND-18-0612 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. M. D. Rauckhorst (w/o enclosures)

Mr. M. D. Meier Mr. D. H. Jones (w/o enclosures)

Mr. D. L. McKinney Mr. M. J. Vox Mr. D. L. Fulton Mr. J. B. Klecha Mr. G. Chick Mr. F. H. Willis Ms. A. L. Pugh Mr. A. 8. Parton Mr. W. A. Sparkman Mr. C. E. Morrow Ms. K. M. Stacy Mr. M. K. Washington Mr. J. P. Redd Ms. A. C. Chamberlain Mr. D. R. Culver Mr. T. G. Petrak Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reaulatorv Commission Mr. W. Jones (w/o enclosures)

Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. N. D. Karlovlch Mr. A. J. Lerch Mr. C. J. Even Mr. F. D. Brown Mr. B. J. Kemker Ms. A. E. Rivera-Varona Ms. L. A. Kent Mr. P. B. Donnelly Ms. N. C. Coovert Oalethorpe Power Corporation Mr. R. B. Brinkman

U.S. Nuclear Regulatory Commission ND-18-0612 Page 3 of 3 Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinahouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. D. Hawkins Ms. J. Monahan Mr. J. L. Coward Ms. N. E. Deangelis Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-18-0612 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-18-0612 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC E.3.9.08.01.02 [Index Number 871]

U.S. Nuclear Regulatory Commission ND-18-0612 Enclosure Page 2 of 3 ITAAC Statement Proaram Commitment 8.1 The licensee conducts a partial participation exercise to evaluate portions of emergency response capabilities, which includes participation by each State and local agency within the plume exposure EPZ that have not been tested in a previous exercise. [N.I]

Inspections/Tests/Analvses 8.1 A partial participation exercise (test) will be conducted within the specified time periods of 10 CFR Part 50, Appendix E.

Acceptance Criteria 8.1.2 Onsite emergency response personnel are mobilized in sufficient number to fill the emergency positions identified in SNC Standard Emergency Plan, Section B, Emergency Response Organization, and Vogtle (Units 3 &4) Standard Emergency Plan Annex, Section 2, Organizationai Controi of Emergencies, and they successfully perform theirassigned responsibilities as outlined in Acceptance Criterion 8.1.1.D, Emergency Response Faciiities.

ITAAC Completion Description Multiple ITAAC are performed to ensurethat a partial participation exercise is conducted to evaluate portions of emergency response capabilities, which includes participation by each State and local agency within the plume exposure Emergency Planning Zone (EPZ) that have not been tested in a previous exercise. This ITAAC performs a partial participation exercise (test) within the specified time periods of 10 CFR Part 50, Appendix Eand confirms that onsite emergency response personnel are mobilized in sufficient number to fill the emergency positions identified in Southern Nuclear Operating Company Standard Emergency Plan, Section B, Emergency Response Organization, and Standard Emergency Plan Annex for Vogtle Electric Generating Plant Units 3 &4, Section 2, Organizational Control of Emergencies, and they successfully perform their assigned responsibilities as outlined in Acceptance Criterion 8.1.1 .D, Emergency Response Facilities.

An exercise scenario, simulating a radiological release to the environment, is developed and conducted using procedure NMP-EP-303 (Reference 1). Ascenario-specific onsite exercise objective is generated to evaluate that onsite emergency response personnel are mobilized in sufficient number to fill the emergency positions identified in Southern Nuclear Operating Company Standard Emergency Plan (Reference 2), Section B, Emergency Response Organization, Table 1 (Technical Support Center (TSC) 75 Minute Augmentation Emergency Response Organization ERO), Table 2 (Operations Support Center (OSC) 75 Minute Augmentation ERO), Table 3 (Emergency Operations Facility (EOF) 75 Minute Augmentation ERO) and Table 4 (Joint Information Center (JIC) Staff); and Standard Emergency Plan Annex for Vogtle Electric Generating Plant Units 3 and 4 (Reference 3), Section 2, Organizational Control of Emergencies, Table 2.2.A (Vogtle Electric Generating Plant On-Shift Staffing).

Confirmation that these emergency response personnel perform their assigned responsibilities as outlined in Acceptance Criterion 8.1.1 .D, Emergency Response Facilities, is documented in

U.S. Nuclear Regulatory Commission ND-18-0612 Enclosure Page 3 of 3 the Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 ITAAC E.3.9.08.01.01 Completion Packages (References 4 and 5).

The partial participation exercise performance (test) results are documented in Drill/Exercise Report XXX (Reference 6) per procedure NMP-EP-303. The Drill/Exercise Report documents and confirmsthat onsite emergency response personnel are mobilized in sufficient number to fill the emergency positions identified in Sf^C Standard Emergency Plan, Section B, Emergency Response Organization, and Vogtle (Units 3 &4) Standard Emergency Plan Annex, Section 2, Organizational Control of Emergencies.

References 1 through 6 are available for NRC inspection as part of the Unit 3 and Unit 4 ITAAC E.3.9.08.01.02 Completion Packages (References 7 and 8).

List nf ITAAC Findings In accordance with plantprocedures for ITAAC completion. Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

References ^available for NRC inspectionl

1. Procedure NMP-EP-303, Drill and Exercise Standards.
2. Southern NuclearOperating Company Standard Emergency Plan
3. Southern Nuclear Operating Company Standard Emergency Plan Annex for Vogtle Electric Generating Plant Units 3 and 4
4. E.3.9.08.01.01 -U3-CP-RevX, ITAAC Completion Package
5. E.3.9.08.01.01 -U4-CP-RevX, ITAAC Completion Package
6. Drill/Exercise Report XXX
7. E.3.9.08.01.02-U3-CP-RevX, ITAAC Completion Package
8. E.3.9.08.01.02-U4-CP-RevX, ITAAC Completion Package
9. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10CFR Part 52"