February 18, 2026 Ms. Gayle Elliott, Director Licensing and Regulatory Affairs Framatome Inc.
3315 Old Forest Road Lynchburg, VA 24501
SUBJECT:
THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVISED SCHEDULE FOR REVIEW OF FRAMATOMES, BAW-10247, REVISION 0, SUPPLEMENT 3P, REVISION 0, REALISTIC THERMAL-MECHANICAL FUEL ROD METHODOLOGY FOR BOILING WATER REACTORS SUPPLEMENT 3:
EXTENSION TO HIGHER EXPOSURE, TOPICAL REPORT (EPID L-2025-TOP-0013)
Dear Ms. Elliott:
By letter dated April 7, 2025 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML25094A181), Framatome Inc. submitted Topical Report (TR) BAW-10247, Revision 0, Supplement 3P, Revision 0, Realistic Thermal-Mechanical Fuel Rod Methodology for Boiling Water Reactors Supplement 3: Extension to Higher Exposures, for U.S. Nuclear Regulatory Commission (NRC) review and approval. The NRC staff accepted the TR for review on May 8, 2025 (ML25121A089) and provided an initial review schedule. The NRC staff is revising the current review schedule to account for the delay in the response to Request for Additional Information (RAI)-11050.
The revised dates for the completion of the draft and final Safety Evaluation (SE) will be August 5 and September 30, 2026, respectively based on a planned RAI response of May 8, 2026. These revised dates assume that the RAI response, resolution of technical issues, and proprietary review of the draft SE will be done in a timely manner. This revised schedule was discussed and agreed upon with Alan Meginnis of Framatome. The revised schedule is provided in the enclosure.
G. Elliott If you have any questions regarding the TR review, please contact me at 301-415-6695 or via email at Ngola.Otto@nrc.gov.
Sincerely,
/NA/
Ngola A. Otto, Project Manager Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 99902041
Enclosure:
Revised Review Schedule
Enclosure Revised Review Schedule Milestone Current Date Revised Date Initial Submittal April 4, 2025 Acceptance May 8, 2025 Conduct Audit September 9-11, 2025 Issue Requests for Additional Information (RAIs) to Framatome December 12, 2025 Framatome Response to RAIs February 13, 2026 May 8, 2026 Issue Draft Safety Evaluation (SE)
May 8, 2026 August 5, 2026 Draft SE Proprietary Review by Framatome May 22, 2026 September 2, 2026 Issue Final SE to Framatome June 12, 2026 September 30, 2026
-A (Approved Version) Issued by Framatome September 10, 2026 November 30, 2026 NRC Issued Verification October 9, 2026 December 18, 2026
- eConcurrence NRR-004 OFFICE NRR/DORL/LLPB/PM*
NRR/DORL/LLPB/LA*
NRR/DSS/SFNB/BC*
NRR/DORL/LLPB/BC*
NAME NOtto DHarrison SKrepel DMarcano DATE 02/3/2026 02/4/2026 02/11/2026 02/17/2026 OFFICE NRR/DORL/LLPB/PM*
NAME NOtto DATE 02/18/2026