MONTHYEARML24149A1412024-05-28028 May 2024 Notice of Pre-Application Meeting with Holtec International for the Model No. HI-STAR 330 Package Project stage: Meeting ML24199A0812024-06-30030 June 2024 Enclosure 2: HI-STAR 330 Pre-submittal Presentation to the U.S. Nuclear Regulatory Commission - Public Session Project stage: Other ML24199A0742024-07-19019 July 2024 Memo and Enclosure 1: Summary of June 20, 2024, Meeting with Holtec International Project stage: Meeting ML25071A3692025-03-10010 March 2025 International, HI-STAR 330 Transportation Package Initial Submittal Project stage: Request ML25178C6732025-08-0101 August 2025 Enclosure 1 - Request for Supplemental Information for HI-STAR 330 Transportation Cask, CoC No. 9397 (Redacted Public Version) Project stage: Other ML25176A1702025-08-0101 August 2025 Letter to Kimberly Manzione, Re Request for Supplemental Information for CoC No. 9397, Model Number HI-STAR 330 Project stage: Other ML25233A2332025-08-21021 August 2025 International - Schedule for Responses to Requests for Supplemental Information for Revision 0 of Certificate of Compliance No. 9397 for the HI-STAR 330 Package Project stage: Supplement ML25254A1712025-09-11011 September 2025 Enclosure 2 - Acceptance Review Audit Plan for HI-STAR 330 Project stage: Acceptance Review ML25253A4912025-09-11011 September 2025 Letter to K Manzione Re Additional Observations for CoC 9397 Project stage: Other ML25336A3002025-12-0202 December 2025 Enclosure 2: HI-STAR 330 Rsi Responses (Non-proprietary) Project stage: Other ML25336A3032025-12-0202 December 2025 Enclosure 5: Proposed CoC 71-9397 for the HI-STAR 330 Package Changed Pages (Non-proprietary) Project stage: Other ML25336A2982025-12-0202 December 2025 International - Responses to Requests for Supplemental Information for Revision 0 of Certificate of Compliance No.9397 for the HI-STAR 330 Package Project stage: Supplement ML25336A3022025-12-0202 December 2025 Enclosure 4: HI-2210970 - HI-STAR 330 Safety Analysis Report Revision 1 Changed Pages (Non-proprietary) Project stage: Other ML25336A3092025-12-0202 December 2025 Enclosure 11: Affidavit Pursuant to 10 CFR 2.390 to Withhold Information from Public Disclosure Project stage: Other ML25352A3192025-12-19019 December 2025 Acceptance Letter for HI-STAR 330, Docket Number 71-09397, CoC No. 9397 Project stage: Acceptance Review 2025-12-02
[Table View] |
Text
Holtec Technology Campus, One Holtec Blvd, Camden, NJ 08104 Telephone (856) 797-0900 Fax (856) 797-0909 Document ID 3155003 Page 1 of 2 August 21, 2025 Haimanot Yilma, Project Manager Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No.: 71-9397 (HI-STAR 330 Model)
EPID No.: L-2022-NEW-0002
Subject:
Schedule for Responses to Requests for Supplemental Information for Revision 0 of Certificate of Compliance No.9397 for the HI-STAR 330 Package
Reference:
[1] Application for Certificate of Compliance No. 9397 for the Model No. HI-STAR 330 Package-Request for Supplemental Information, letter from H. Yilma (NRC) to K. Manzione (Holtec) dated August 1, 2025. ADAMS Accession Number ML25176A170.
Dear Ms. Haimanot Yilma:
By letter dated August 1, 2025 [1], the NRC staff sent Requests for Supplemental Information (RSIs) to support review of the HI-STAR 330 Certificate of Compliance No. 9397 and requested that Holtec provide this information by August 31, 2025.
To ensure high-quality responses to the staffs questions and to allow sufficient time to complete additional analyses and drawing revisions needed to support the responses, Holtec plans to submit responses by October 31, 2025.
If you have any questions, please contact me at 856-797-0900 ext. 3469.