MONTHYEARML23335A1002023-11-30030 November 2023 Request for Exemption from 10 CFR 50.10(c) to Allow Excavation at the Clinch River Nuclear Site Prior to Construction Permit Issuance Project stage: Request ML24220A2872024-07-0707 July 2024 Species List: Tennessee Ecological Services Field Office Clinch River Exemption Request Review Project stage: Other ML24193A3012024-07-10010 July 2024 Clinch River Project - Response to Excavation Exemption Request Audit and Information Needs Project stage: Other ML24213A2682024-07-31031 July 2024 Us Sfr Owner, Llc–Kemmerer Unit 1 Environmental Report Audit Plan - CAC No. 001912; EPID No. L-2024-LNE-0002 Project stage: Other ML24228A1932024-08-28028 August 2024 Environmental Audit Report - Clinch River Nuclear Site Exemption Request Project stage: Other ML24281A2032024-10-0707 October 2024 Updated Species List: Tennessee Ecological Services Field Office Clinch River Exemption Request Review Project stage: Other ML24312A3212024-11-0707 November 2024 Final Environmental Assessment for the Clinch River Nuclear Site Exemption Request Project stage: Other ML25140A0632025-05-20020 May 2025 Submittal of the Preliminary Safety Analysis Report and Exemptions and Variances in Support of the Clinch River Nuclear Site Construction Permit Application Project stage: Other ML25164A0482025-06-0505 June 2025, 12 June 2025 Acceptance Letter, Part One of Tennessee Valley Authoritys CP Application (Clinch River Nuclear Site) Project stage: Request ML25133A1842025-06-0505 June 2025 Federal Register Notice, Notice of Availability, Tennessee Valley Authoritys CP Application (Clinch River Nuclear Site) Project stage: Other ML25156A0582025-06-12012 June 2025 Acceptance Letter, Part One of Tennessee Valley Authoritys CP Application (Clinch River Nuclear Site) Project stage: Acceptance Review ML25182A1512025-07-0909 July 2025 Letter to TVA, Acceptance, Docketing and Opportunity for Hearing, Tennessee Valley Authoritys CP Application Project stage: Other ML25189A3852025-07-10010 July 2025 Clinch River CP Environmental Audit Plan Project stage: Other ML25175A0322025-07-15015 July 2025 FRN Site Notice of Intent to Prepare a Supplement Project stage: Request ML25182A1222025-07-16016 July 2025 NRC Ltr to E. Patrick Mcintyre, Jr., Tn SHPO Re Initiation of NHPA Sec 106 Consult for the Clinch River Construction Permit Rev Project stage: Other ML25182A1232025-07-16016 July 2025 NRC Ltr to J. Loichinger, ACHP Re Notification of NHPA Sec 106 Consult for the Clinch River Construction Permit Review Project stage: Other ML25175A0642025-07-18018 July 2025 Tennessee Valley Authority - Notice of Intent to Prepare a Supplement to the Environmental Impact Statement in Relation to the Construction Permit Application for the Clinch River Nuclear Site Project stage: Other ML25205A0052025-07-25025 July 2025 Letter to TVA, Schedule and Resource Estimates for CP Application Review (Clinch River Nuclear Site, Unit 1) Project stage: Other ML25317A6432025-10-0202 October 2025 Notification of the Issuance of the Draft Supplemental Environmental Impact Statement for Tennessee Valley Authority at the Clinch River Nuclear Site Project stage: Draft Approval ML25290A1232025-10-17017 October 2025 Confirmatory Information Regarding the Environmental Report for the Long Mott Generating Station Constuction Permit Application Project stage: Other ML25261A2142025-11-0404 November 2025 Supplemental Environmental Impact Statement for a Construction Permit at the Clinch River Nuclear Site: Draft Report for Comment Project stage: Request ML25307A0052025-11-0606 November 2025 Formal Letter Lme Requesting RAIs Project stage: Other ML25289A3282025-11-0707 November 2025 Ltr to Wilson Yargee Alabama-Quassarte Tribal Town Re Crn CP DSEIS Project stage: Other ML25272A1552025-11-0707 November 2025 Ltr to J. Loichinger ACHP-CRN CP DSEIS Project stage: Other ML25289A3152025-11-0707 November 2025 Ltr to Deborah Dotson Delaware Nation Re Crn CP DSEIS Project stage: Other ML25272A1562025-11-0707 November 2025 Ltr to J.R. Johnson Absentee Shawnee Tribe-CRN CP DSEIS Project stage: Other ML25274A0932025-11-0707 November 2025 Clinch River Nuclear Site Construction Permit Draft SEIS Issuance Applicant Letter Project stage: Draft Approval ML25289A3122025-11-0707 November 2025 Ltr to Chuck Hoskin Jr. Cherokee Nation Re Crn CP DSEIS Project stage: Other ML25289A3132025-11-0707 November 2025 Ltr to David Hill Muscogee (Creek) Nation Re Crn CP DSEIS Project stage: Other ML25289A3162025-11-0707 November 2025 Ltr to Donnis Battise Alabama-Coushatta Tribe of Texas Re Crn CP DSEIS Project stage: Other ML25289A3202025-11-0707 November 2025 Ltr to Lewis J. Johnson Seminole Nation of Oklahoma Re Crn CP DSEIS Project stage: Other ML25289A3252025-11-0707 November 2025 Ltr to Ryan K. Morrow Thlopthlocco Tribal Town Re Crn CP DSEIS Project stage: Other ML25272A1542025-11-0707 November 2025 Ltr to E. Patrick Mcintyre Tn SHPO-CRN CP DSEIS Project stage: Other ML25289A3222025-11-0707 November 2025 Ltr to Marcellus W. Osceola Jr Seminole Tribe of Florida Re Crn CP DSEIS Project stage: Other ML25289A3212025-11-0707 November 2025 Ltr to Libby Rogers Jena Band of Choctaw Indians Re Crn CP DSEIS Project stage: Other ML25289A3142025-11-0707 November 2025 Ltr to David Sickey Coushatta Tribe of Louisiana Re Crn CP DSEIS Project stage: Other ML25289A3112025-11-0707 November 2025 Ltr to Ben Barnes Shawnee Tribe Re Crn CP DSEIS Project stage: Other ML25289A3172025-11-0707 November 2025 Ltr to Glenna J Wallace Eastern Shawnee Tribe of Oklahoma Re Crn CP DSEIS Project stage: Other ML25289A3232025-11-0707 November 2025 Ltr to Michell Hicks Eastern Band of Cherokee Indians Re Crn CP DSEIS Project stage: Other ML25289A3182025-11-0707 November 2025 Ltr to Jeff Wacoche United Keetoowah Band of Cherokee Indians Re Crn CP DSEIS Project stage: Other ML25289A3262025-11-0707 November 2025 Ltr to Stephaie Yahola Kialegee Tribal Town Re Crn CP DSEIS Project stage: Other ML25289A3272025-11-0707 November 2025 Ltr to Stephanie A. Bryan Poach Band of Creek Indians Re Crn CP DSEIS Project stage: Other 2025-11-06
[Table View] |
Text
July 25, 2025 Scott Hunnewell Vice President, New Nuclear Program Tennessee Valley Authority 1101 Market Street Chattanooga, TN 37402
SUBJECT:
CLINCH RIVER NUCLEAR SITE, UNIT 1, CONSTRUCTION PERMIT APPLICATION REVIEW SCHEDULE AND RESOURCE ESTIMATE (CAC/DOCKET/EPID(S): 001912/050-000615/L-2025-CPS-0001 [through 0017];
L-2025-PMP-0006; & L-2025-LNE-0000)
Dear Mr. Hunnewell:
This letter provides a summary of the review schedule and resource estimate for the detailed review of the Clinch River Nuclear Site (CRNS), Unit 1, construction permit (CP) application (Agencywide Documents Access and Management System (ADAMS) Accession Nos.
ML25118A209 and ML25140A062). By letter dated July 9, 2025, the U.S. Nuclear Regulatory Commission (NRC) staff sent Tennessee Valley Authority (TVA) a letter accepting the CRNS CP application for detailed review (ML25182A151). A notice of the acceptance for docketing was published in the Federal Register on July 15, 2025 (90 FR 31709). The tables below provide key milestones for both the safety review and the environmental review.
Safety Review Milestones Estimated Completion Dates Draft Safety Evaluation1 February 2026 Advance Safety Evaluation Report2 October 2026 Final Safety Evaluation Report November 2026 Notes:
- 1. Safety Evaluation sections drafted and information gaps identified.
- 2. Advanced Safety Evaluation Report without open items.
Environmental Review Milestones Estimated Completion Dates Draft Supplemental Environmental Impact Statement December 2025 Final Supplemental Environmental Impact Statement April 2026 The schedule reflects the NRC staffs best estimate of the level of effort needed for its review and the NRC staffs understanding of TVAs deployment timeline for CRNS Unit 1. The schedule was developed, in part, considering: (1) the complexity of the technical and regulatory issues associated with the design; (2) the completeness and quality of the application; (3) the effectiveness of pre-application, readiness review, and acceptance review engagements; and (4) the availability of the NRC staffs resources and prioritization with concurrent workload. This
schedule does not include the hearing process, which follows the completion of the safety evaluation and environmental review.
The schedule is also based, in part, on TVAs commitment to provide timely responses to requests for additional information. The applicant is also expected to provide support determined necessary by the NRC staff in a timely and organized manner during technical audits. To achieve this schedule, the NRC staff intends to engage TVA frequently during the application review to assess progress and address emerging technical issues. Delays in the NRC staffs receipt of necessary information could result in changes to the review schedule. In the event that potential delays arise in its support of the schedule, the NRC requests that TVA inform the NRC staff in writing, as early as possible.
Based on pre-application activities and the information provided in TVAs CNRS, Unit 1 CP application submittal, the NRC staff estimates that it will need approximately 25,000, staff hours and $1.4 million in contractor support to complete the safety and environmental reviews of the application. Hearing activities are not included in this resource estimate.
If you have any questions, please contact Allen Fetter at 301-415-8556 or via email at allen.fetter@nrc.gov; and Stacy Joseph at 301-415-3256 or via email at stacy.joseph@nrc.gov.
Sincerely,
/RA/
Allen Fetter, Senior Project Manager New Reactor Licensing and Infrastructure Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Project No./Docket No.: 99902056/05000615 cc: GovDelivery
Letter: ML25205A005 via* email NRR-106 OFFICE DNRL/NLIB:PM DNRL/NLIB:LA REFS/EPMB:PM REFS/EPMB3 DNRL/NLIB:
(A) BC DNRL/NLIB:PM NAME AFetter SGreen*
MNagel*
DBarnhurst*
MJardaneh*
AFetter DATE 07/23/2025 07/24/2025 07/24/2025 07/24/2025 07/24/2025 07/25/2025