Letter Sequence Request |
|---|
EPID:L-2024-CRS-0000, Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule (Open) |
Results
Other: DCL-23-118, License Renewal Application, ML24088A238, ML24136A162, ML24198A105, ML24205A066, ML24205A067, ML24235A203, ML24262A246, ML24281A106, ML24302A148, ML24302A153, ML24302A154, ML24317A038, ML24317A039, ML24338A147, ML25093A060, ML25113A183, ML25113A184, ML25136A355, ML25160A123, ML25160A125, ML25161A264
|
MONTHYEARDCL-23-038, Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule2023-05-15015 May 2023 Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule Project stage: Request ML23257A3022023-09-14014 September 2023 San Luis Obispo Mothers for Peace and Friends of the Earth Corrected Request for Hearing on NRC Staff Decision Effectively Amending Diablo Canyon 1 License, Request for Emergency Order Requiring Shutdown, and Errata Project stage: Request DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application Project stage: Other ML24065A4342024-03-0505 March 2024 Exhibit 2 to Hearing Request Project stage: Request ML24067A0662024-03-0707 March 2024 Petition by San Luis Obispo Mothers for Peace, Friends of the Earth and Environmental Working Group for Shutdown of Diablo Canyon Nuclear Power Plant Due to Unacceptable Risk of Seismic Core Damage Accident Project stage: Request ML24088A2382024-03-28028 March 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 OEDO-24-00083 - Screen-in e-mail L-2024-CRS-0000 Project stage: Other ML24136A1622024-05-15015 May 2024 OEDO-24-00083 (E-Mail) 10 CFR 2.206 - Diablo Canyon Power Plant, Unit Nos. 1 and 2 Seismic - Initial Assessment Project stage: Other ML24162A0792024-06-0707 June 2024 OEDO-24-00083 - 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic CDF - Supplemental Declaration 6-7-2024 - Project stage: Supplement ML24198A1052024-07-17017 July 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic CDF - Petitioner Presentation 7-16-2024 - L-2024-CRS-0000 OEDO-24-00083 Project stage: Other ML24218A1642024-07-17017 July 2024 OEDO-24-00083 - 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic CDF - 7-17-2024 Petitioner Public Meeting Transcript - Project stage: Meeting ML24235A2032024-08-22022 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Final Determination e-mail - EPID L-2024-CRS-0000 Project stage: Other ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - Project stage: Other ML24205A0672024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - FRN Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - (EPID L-2024-CRS-0000) - Federal Register Notice Project stage: Other ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - Project stage: Other ML24281A1062024-10-0202 October 2024 NRR E-mail Capture - (External_Sender) Public Letter to Petition Review Board Regarding the Diablo Canyon Seismic Core Damage Frequency 10 CFR 2.206 Petition - OEDO-24-00083 Project stage: Other DCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 Project stage: Request ML24305A1872024-10-31031 October 2024 OEDO-24-00083 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic CDF - Petition Supplement 10-30-2024 Project stage: Supplement ML24338A1472024-11-27027 November 2024 NRR E-mail Capture - Status Update to Petitioner - Diablo Canyon Seismic Core Damage Frequency 10 CFR 2.206 Petition - OEDO-24-00083 Project stage: Other ML24317A0382024-12-0505 December 2024 OEDO-24-00083 - 2.206 Petition Regarding Seismic Core Damage Frequency for Diablo Canyon Nuclear Power Plant, Units 1 and 2, Supplemental Acknowledgment Letter (EPID L-2024-CRS-0000) (Letter) Project stage: Other ML24317A0392024-12-0505 December 2024 OEDO-24-00083 - 2.206 Petition Regarding Seismic Core Damage Frequency for Diablo Canyon Nuclear Power Plant, Units 1 and 2, Supplemental Acknowledgment Letter (EPID L-2024-CRS-0000) (FRN) Project stage: Other ML25093A0602025-04-10010 April 2025 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Proposed Directors Decision - L-2024-CRS-0000 OEDO-24-00083 - Attachment Project stage: Other ML24302A1542025-04-10010 April 2025 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Proposed Directors Decision Letter to Licensee - L-2024-CRS-0000 OEDO-24-00083 Project stage: Other ML24302A1532025-04-10010 April 2025 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Proposed Directors Decision Letter to Petitioners - L-2024-CRS-0000 OEDO-24-00083 Project stage: Other ML24302A1482025-04-10010 April 2025 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Proposed Directors Decision - L-2024-CRS-0000 OEDO-24-00083 Project stage: Other ML25107A2562025-04-16016 April 2025 Request for Extension of Time to Comment on Proposed Director’S Decision Regarding Seismic Core Damage Frequency for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (EPID L-2024-CRS-0000) (Redacted) Project stage: Request ML25113A1842025-04-17017 April 2025 Seismic Core Damage 2.206 Petition - Approval of Comment Period Extension Request to May 15, 2025 - Email to Petitioners Project stage: Other ML25113A1832025-04-17017 April 2025 Seismic Core Damage 2.206 Petition - Approval of Comment Period Extension Request to May 15, 2025 - Email to Licensee Project stage: Other ML25136A3552025-05-15015 May 2025 Comments on Proposed Directors Decision Regarding Seismic Core Damage Frequency for Diablo Canyon Nuclear Power Plant, Units 1 and 2 Project stage: Other ML25161A2642025-06-26026 June 2025 OEDO-24-00083 - Directors Decision Regarding Seismic Core Damage Frequency for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (EPID L-2024-CRS-0000) - Attachment Project stage: Other ML25160A1252025-06-26026 June 2025 OEDO-24-00083 - Directors Decision Regarding Seismic Core Damage Frequency for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (EPID L-2024-CRS-0000) - Directors Decision Project stage: Other ML25160A1232025-06-30030 June 2025 OEDO-24-00083 - Directors Decision Regarding Seismic Core Damage Frequency for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (EPID L-2024-CRS-0000) - Federal Register Notice Project stage: Other 2024-05-15
[Table View] |
Request for Extension of Time to Comment on Proposed Director’S Decision Regarding Seismic Core Damage Frequency for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (EPID L-2024-CRS-0000) (Redacted)| ML25107A256 |
| Person / Time |
|---|
| Site: |
Diablo Canyon  |
|---|
| Issue date: |
04/16/2025 |
|---|
| From: |
Curran D, Leary C, Templeton H Environmental Working Group, Friends of the Earth, Harmon, Curran, Harmon, Curran, Spielberg & Eisenberg, LLP, San Luis Obispo Mothers for Peace |
|---|
| To: |
Dennis Galvin NRC/NRR/DORL/LPL4 |
|---|
| References |
|---|
| EPID L-2024-CRS-0000, OEDO-24-00083 |
| Download: ML25107A256 (1) |
|
Text
April 16, 2025 Dennis Galvin, Project Manager / Agency 2.206 Petition Coordinator Office of Nuclear Reactor Regulation Division of Operating Reactor Licensing Plant Licensing Branch IV U.S. Nuclear Regulatory Commission Washington, D.C. 20555 By email to: dennis.galvin@nrc.gov
SUBJECT:
Request for extension of time to comment on Proposed Directors Decision Regarding Seismic Core Damage Frequency for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (EPID L-2024-CRS-0000)
Dear Mr. Galvin:
On behalf of Petitioners San Luis Obispo Mothers for Peace (SLOMFP), Friends of the Earth (FoE), and Environmental Working Group (EWG), we are writing to request an extension of time to submit comments on the Proposed Directors Decision Regarding Seismic Core Damage Frequency for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (EPID L-2024-CRS-0000)
(April 10, 2025) (Proposed Decision). Because the Proposed Decision was e-mailed to us on April 11, 2025, you informed us that the deadline for our comments is April 25, 2025. As provided by MD 8.11, Handbook Section V.E.2, Petitioners respectfully request a 20-day extension until May 15, 2025.
Our request for an extension is based on the following circumstances:
First, given the complexity of the issues, the size of the record, and the significant number of technical errors and omissions in the Proposed Decision, Petitioners respectfully submit that the two weeks provided by your cover letter does not provide us with an adequate or meaningful opportunity to prepare comments on the Proposed Decision. The issues are complex, as demonstrated by the fact that the PRB has been reviewing Petitioners enforcement petition for more than a year.1 The evidentiary record is also lengthy and complex, presented in multiple submissions by Petitioners and their expert, Dr. Peter Bird, as well as a meeting with the Petition Review Board (PRB); and a presentation by PG&E.2 In addition, in their initial review of the Proposed Decision, Petitioners have found that the PRB appears to misunderstand or completely ignore a significant number of Dr. Birds key concerns and evidence.
1 See Proposed Decision at 1 (citing March 12, 2024 referral memorandum from the Secretary of the Commission).
2 See Proposed Decision at 1-3 (citing Petitioners seismic shutdown petition of March 4, 2025; supplemental submissions by Petitioners on June 7, 2024 and October 31, 2024; oral and written presentations by Petitioners at a meeting with the PRB on July 17, 2024; and a written submission by PG&E on October 24, 2025).