ML25059A002

From kanterella
Jump to navigation Jump to search

Supplemental Information Enclosure
ML25059A002
Person / Time
Site: Callaway Ameren icon.png
Issue date: 02/28/2025
From: Mahesh Chawla
NRC/NRR/DORL/LPL4
To: Diya F
Union Electric Co
Chawla M
References
EPID L-2024-LLR-0084
Download: ML25059A002 (1)


Text

Enclosure 1 to 10 CFR 50.55a Request IWE-02 ULNRC-06930 Page 1 of 4 Proposed Alternative in accordance with 10 CFR 50.55a (z)(2) -

Complying with Requirement Would Result in Hardship or Unusual Difficulty Without a Compensating Increase in the Level of Quality and Safety

1. ASME Code Component Affected:

Component:

Containment Liner

==

Description:==

Instrument Tunnel Sump (Incore Pit) Liner Component Number:

SUMPLF07DRWIT

2. Applicable Code Edition and Addenda

ASME Boiler and Pressure Vessel Code (BPVC),Section XI, Rules for Inservice Inspection of Nuclear Power Plant Components, 2007 Edition through 2008 Addenda.

3. Applicable Code Requirement

IWA-4422, Defect Evaluation and Examination IWA-4422.2.2, Defect Removal Followed by Welding or Brazing, paragraph (a) states the following:

Surface examination of the defect removal area is required prior to welding, except as provided below.

(1) A surface examination is not required when the defect is eliminated by removing the full cross-section of the weld or base material.

(2) When surface examination of the excavation cannot be performed or will not provide meaningful results, surface examination of the excavation is not required. The acceptability of any remaining portion of the defect may be established by evaluation in accordance with IWA-4422.1(b) in lieu of the surface examination. Alternative NDE methods may be used to characterize any remaining portion of the defect.

(3) If final volumetric examination will be performed on the completed repair, the final volumetric examination method is the same as the method used to detect the defect, and the volume to be examined includes the location of the original defect, surface examination of the defect removal area is not required.

4. Reason for Request

Pursuant to 10 CFR 50.55a, "Codes and standards," paragraph (z)(2), an alternative to the ASME BPVC Section XI, IWA-4422.2.2(a) surface examination requirement is proposed. The basis of the request is that complying with the IWA-4422.2.2(a) requirement would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.

On October 20, 2023, during Callaway's refueling outage (RFO), inservice inspection (ISI) on the Instrument Tunnel Sump (Incore Pit) was performed (Reference 1) in accordance with Callaway's Containment Pressure Boundary ISI Program procedure (Reference 2). During this inspection, Quality Control (QC) inspectors identified localized pits on the liner plate wall and floor. This condition was captured in Callaway's Corrective Action Program (Reference 3), and a job package was generated to repair the identified pits (Reference 4). Excavation was performed to get all indications (i.e., corroded, pitted, and eroded areas) to smooth base metal. Subsequently, a pre-weld visual

to 10 CFR 50.55a Request IWE-02 ULNRC-06930 Page 2 of 4 examination of the defect removal areas was performed. However, an IWA-4422.2.2(a) pre-weld surface examination of the defect removal area was not performed before the start of weld repairs on the liner. This condition was not identified until the conduct of an internal audit in the Fall of 2024 (Reference 5).

In accordance with IWA-4422.2.2(a), Callaway is required to perform a pre-weld surface examination prior to welding repairs. To restore compliance with IWA-4422.2.2(a), Callaway would have to perform the missed pre-weld surface examinations on the Instrument Tunnel Sump liner defect removal areas, which would require an unplanned plant shutdown and re-excavation of the base metal repairs (BMRs), perform the missed pre-weld surface exams, and complete new BMRs and post-weld exams and tests on the liner. This relief request is proposing to postpose a plant shutdown until Callaway's next scheduled RFO, which is scheduled to begin on March 29, 2025, and then perform ultrasonic tests (UTs), in lieu of BMR rework and pre-weld surface exams, at the locations on the Instrument Tunnel Sump liner where welds were completed in the Fall of 2023.

The technical justification for the proposed alternative is discussed in the next section of this relief request.

5. Proposed Alternative and Basis for Use

As an alternative, Ameren Missouri proposes performing angle beam UTs at all locations where welds were completed in the Fall of 2023 on the Instrument Tunnel Sump liner during Callaway's next scheduled RFO, which is scheduled to begin on March 29, 2025. The ultrasonic acceptance standards per ASME Section III, Division 1, Subsection NE-5330, 1974 Summer 1975 Edition will be used for the UT exams. This alternative would be done in lieu of the surface examination requirements prescribed in subparagraph Section XI IWA-4422.2.2(a). The basis for the proposed alternative is that the activities necessary to restore compliance with IWA-4422.2.2(a) (i.e., unplanned shutdown, BMR re-excavation, pre-and post-weld exams) would result in hardship or unusual difficulty without a compensating level of quality or safety.

Justification:

A. Instrument Tunnel Sump Design Information The Instrument Tunnel Sump is a collection point for reactor coolant leakage in containment and is open to containment atmospheric pressure and temperature. Sump level instrumentation is capable of detecting reactor coolant system leakage.

The liner plate of the Instrument Tunnel Sump is ASME Section XI, 1/4" thick carbon steel (SA-285),

and the metal liner of a Class CC component (IWE). As a containment liner, the primary function of the Instrument Tunnel Sump liner plate is to ensure that the containment structure is leak tight. Behind the containment liner is the post-tensioned concrete containment structure. The concrete structure supports all structural loads, and no credit is taken for the liner for the pressure design of the containment structure.

Due to the post-tensioning of the concrete containment structure, the liner plate is under compression.

As such, the liner is able to perform its leak tight design function with only a few mils of thickness due to the strain of the liner being directly related to the strain in the concrete structure. In particular, the Instrument Tunnel Sump liner is located on the base slab of the containment concrete structure which is several feet thick. This section of the liner is not in an area where tight rebar lattices exist that might hinder the placement of concrete which could result in small voids in the containment structure.

It is noted, however, that Callaway calculated the minimum wall thickness required for the containment liner for conditions of generalized and localized thinning by conservatively assuming different size voids in the concrete containment structure immediately behind the liner plate

to 10 CFR 50.55a Request IWE-02 ULNRC-06930 Page 3 of 4 (Reference 6). This calculation concluded that a liner wall thickness of 1/8" (or 0.125") is allowed for areas of localized defects or thinning that are less than 5" in diameter.

B. Instrument Tunnel Sump Liner Inspection and Examinations During the IWE inspection of the Instrument Tunnel Sump liner in the Fall of 2023, QC inspectors identified (25) twenty-five localized pits on the liner wall and floor. Using a pit-gauge, the measurements of the pits ranged from 0.0625" to 0.1875" in depth and 0.250" to 1.125" in diameter (Reference 7). The minimum wall criterion of 1/8" was not met for (23) twenty-three of these localized pits. This condition was captured in Callaway's Corrective Action Program (Reference 3), and a job package was generated to repair the pits (Reference 4).

Excavation on the defects (i.e., pitting from corrosion) was performed to get all indications to base metal so that all corroded, pitted, and eroded areas were removed. A pit depth gage was utilized before and after excavation, and each pit was measured to be less than 5" in diameter. Pre-weld visual examinations of the defect removal areas were performed after excavation. These examinations verified that all excavations were to base metal with no through-wall pitting observed.

These examinations provided reasonable assurance that no unidentified flaws were left prior to performing the weld build-up. Engineering personnel also performed a sound check in and around the identified localized pits and did not detect any hollow cavities behind the liner, based on the low-frequency sounds produced and lack of high pitch echoing.

The BMRs on the liner plate were completed by qualified welders, and the weld filler material used was in accordance with Callaway's welding program procedure (Reference 8). Following the BMRs, QC inspectors performed visual (VT-1) and magnetic particle (MT) surface examinations per QC examination procedures (Reference 9 and 10). These post-weld examinations provided evidence that there were no surface flaws around any of the weld build-up locations and that the surface of the liner is intact (defect free). With the satisfactory completion of the post-weld VT-1 and MT examinations, there is reasonable assurance that the containment liner plate is intact and able to perform its leak tight function.

C. Hardship or Unusual Difficulty To restore compliance with ASME Section XI, IWA-4422.2.2(a) and perform the pre-weld surface examination on the Instrument Tunnel Sump pits identified in the Fall of 2023, Callaway would first be required to shut down the plant. In particular, Callaway would need to shut down the plant to at least MODE 5, Cold Shutdown, in order to remove reactor vessel incore instrumentation and access the Instrument Tunnel Sump. Thus, restoring compliance with IWA-4422.2.2(a) would first necessitate an unplanned shutdown.

In general, a plant shutdown is complex in nature and involves a significant amount of time to schedule, plan, and execute. Accordingly, executing an unplanned shutdown involves greater risks to plant personnel and equipment. Elevated risks include a higher potential for human performance errors, plant transients (i.e., reactivity, pressure, temperature), and risk management challenges, potentially resulting in challenges to plant and personnel safety. Finally, it is noted that less than two months remain before the start of Callaway's next scheduled RFO. Consequently, there is a very low probability of risk to the health and safety of the public in the short time between now and when compliance with ASME Section XI, IWA-4422.2.2(a) is restored.

Secondly, to restore compliance with IWA-4422.2.2(a), the BMRs completed in the Fall of 2023 on the liner would require re-excavation. However, re-excavation introduces the risk of creating new weld defects, causing further damage to the liner, or removing additional liner material and breaching the liner wall at those locations.

In conclusion, performing angle beam UTs during Callaway's next scheduled RFO (in the Spring of 2025) at all locations where BMRs were completed in the Fall of 2023 on the Instrument Tunnel Sump

to 10 CFR 50.55a Request IWE-02 ULNRC-06930 Page 4 of 4 liner will provide reasonable assurance that no defects exist on the liner at the BMR locations. The ultrasonic acceptance standards per ASME Section III, Division 1, Subsection NE-5330, 1974 Summer 1975 Edition will be used for the UT exams. This proposed alternative would be done in lieu of the surface examination requirements prescribed in IWA-4422.2.2(a). Further, the activities necessary to immediately restore compliance with IWA-4422.2.2(a) (i.e., unplanned shutdown, BMRs re-excavation, and pre-and post-weld exams) would result in hardship or unusual difficulty without a compensating level of quality or safety. It should be noted that, if an indication is detected on the liner from the result of a UT exam, the indication will be evaluated for acceptability in accordance with the Construction Code or Section XI. Also, if an indication is determined to be a defect, the defect will be removed and a BMR will be performed as applicable per ASME Section XI IWA-4000.

6. Duration of Proposed Alternative

The relief request will become effective following NRC authorization of the proposed alternative discussed in the relief request and will remain in effect until Callaway's end of plant life or until such a time when base metal repairs on the Instrument Tunnel Sump liner are needed at the previously repaired locations.

7.

References:

1. Job 20513454.000, "Containment Pressure Boundary Inspection of Incore Sump"
2. ESP-ZZ-01016, "ASME Section XI IWE Containment Pressure Boundary Inspection"
3. CR 202307749, "IWE Zone 31 Incore Tunnel Sump (SUMPLF07DRWIT) Inspection Results"
4. Job 20003148.496, "Base Metal Weld Repair of Sump Liner"
5. CR 202406120, " Job 20003148.496 Contains Multiple Instances of Non-Compliance with APA-ZZ-00662 and ASME Section XI"
6. Calculation ZZ-475, "Evaluate the Minimum Wall Thickness of the Containment Liner Required to for Conditions of Generalized and Localized Thinning"
7. Job 20513454.500, "General Visual Inspection Report"
8. APA-ZZ-00661, "Administration of Welding"
9. QCP-ZZ-05040, "Visual Examination to ASME VT-1"
10. QCP-ZZ-05010, "Magnetic Particle Examination"