MONTHYEARPNP 2023-030, License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2023-12-14014 December 2023 License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations Project stage: Request PNP 2024-001, License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations2024-02-0909 February 2024 License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations Project stage: Request PNP 2024-006, Notification of Changes in Accordance with 10 CFR 50.82(a)(7)2024-04-0909 April 2024 Notification of Changes in Accordance with 10 CFR 50.82(a)(7) Project stage: Request PNP 2024-005, License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations2024-05-0101 May 2024 License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations Project stage: Request PNP 2024-023, Pre-Submittal Meeting Presentation - License Amendment Request to Approve the Biasi Critical Heat Flux (CHF) Correlation for Use with the Palisades Main Steam Line Break (MSLB) Analysis2024-05-0909 May 2024 Pre-Submittal Meeting Presentation - License Amendment Request to Approve the Biasi Critical Heat Flux (CHF) Correlation for Use with the Palisades Main Steam Line Break (MSLB) Analysis Project stage: Meeting PMNS20240636, Pre-Submittal Meeting with Holtec Decommissioning International, LLC, to Discuss a License Amendment Request to Approve the Biasi Critical Heat Flux Correlation for Use with the Main Steam Line Break Analysis for the Palisades Nuclear P2024-05-13013 May 2024 Pre-Submittal Meeting with Holtec Decommissioning International, LLC, to Discuss a License Amendment Request to Approve the Biasi Critical Heat Flux Correlation for Use with the Main Steam Line Break Analysis for the Palisades Nuclear Plant Project stage: Meeting PNP 2024-003, License Amendment Request to Approve the Biasi Critical Heat Flux (CHF) Correlation for Use with the Palisades Main Steam Line Break (MSLB) Analysis2024-05-24024 May 2024 License Amendment Request to Approve the Biasi Critical Heat Flux (CHF) Correlation for Use with the Palisades Main Steam Line Break (MSLB) Analysis Project stage: Request ML24169A4342024-06-18018 June 2024 Acceptance of Requested Licensing Action Amendment Request to Approve the Biasi Critical Heat Flux Correlation for Use with the Palisades Main Steam Line Break Analysis Project stage: Acceptance Review ML24149A0022024-06-24024 June 2024 Federal Register Notice - Noi to Conduct Scoping and Develop an Environmental Assessment for the Palisades Nuclear Plant Reauthorization to Power Operation Project stage: Request ML24212A0592024-08-0606 August 2024 May 15, 2024, Summary of Meeting with Holtec Decommissioning International,Llc Regarding LAR to Approve Biasi Critical Heat Flux Correlation for Use with Main Steam Line Break Analysis to Support Potential Reauthorization of Power Operation Project stage: Meeting ML24219A4202024-09-12012 September 2024 Change in Estimated Hours and Review Schedule for Licensing Actions Submitted to Support Resumption of Power Operations (Epids L-2023-LLE-0025, L-2023-LLM-0005, L-2023-LLA-0174, L-2024-LLA-0013, L-2024-LLA-0060, L-2024-LLA-0071) Project stage: Other PMNS20241197, Closed Meeting with the Nuclear Regulatory Commission Staff and Holtec Decommissioning International, LLC (HDI) on the Biasi Critical Heat Flux Correlation for Use with the Palisades Main Steam Line Break Analysis2024-09-19019 September 2024 Closed Meeting with the Nuclear Regulatory Commission Staff and Holtec Decommissioning International, LLC (HDI) on the Biasi Critical Heat Flux Correlation for Use with the Palisades Main Steam Line Break Analysis Project stage: Request ML24303A1162024-11-0606 November 2024 Summary of Meeting with Holtec Decommissioning International, LLC Regarding LAR Request to Approve the Biasi Critical Heat Flux Correlation for Use with the Main Steam Line Break Analysis to Support Potential Project stage: Meeting ML25107A0302025-04-17017 April 2025 EVESR License Amendment Request to Accept VBWR In-Situ Radioactive Material Acceptance Letter (L-2024-LLA-0071) Project stage: Acceptance Review ML25153A1942025-06-0404 June 2025 Request for Withholding Information from Public Disclosure for Palisades Nuclear Plant Project stage: Withholding Request Acceptance ML25156A0452025-07-24024 July 2025 Issuance of Amendment No. 279 Biasi Critical Heat Flux Correlation for Use with the Post Scram Main Steam Line Break Analysis Project stage: Approval ML25199A0862025-08-19019 August 2025 EVESR Safety Evaluation Report Project stage: Approval ML25199A0872025-08-19019 August 2025 EVESR License Amendment No. 8 and Technical Specifications Project stage: Other ML25199A0852025-08-19019 August 2025 EVESR Issuance Letter Project stage: Other 2024-06-18
[Table View] |
Text
November 6, 2024 LICENSEE:
Holtec Decommissioning International, LLC FACILITIES: Palisades Nuclear Plant
SUBJECT:
SUMMARY
OF OCTOBER 2, 2024, MEETING WITH HOLTEC DECOMMISSIONING INTERNATIONAL, LLC REGARDING LICENSE AMENDMENT REQUEST TO APPROVE THE BIASI CRITICAL HEAT FLUX CORRELATION FOR USE WITH THE MAIN STEAM LINE BREAK ANALYSIS TO SUPPORT POTENTIAL REAUTHORIZATION OF POWER OPERATIONS AT PALISADES NUCLEAR PLANT (EPID L-2024-LLA-0071)
On October 2, 2024, a closed meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Holtec Decommissioning International, LLC (Holtec, the licensee) via webinar. The purpose of this meeting was for the NRC staff to discuss with Holtec representatives questions regarding the NRC staff's review of the Main Steam Line Break Analysis (MSLB) for Palisades Nuclear Plant (Palisades) to support potential restart. The NRC staff is currently reviewing Holtecs request for approval of the BIASI Critical Heat Flux (CHF) Correlation for use with the MSLB analysis at the Palisades. In its request, Holtec would adopt the Framatome topical report (TR) EMF-2310 (P)(A), Revision 1, Supplement 2P-A, Revision 0, SRP [Standard Review Plan] Chapter 15 Non-Loss of Coolant Accident Methodology for Pressurized Water Reactors (Agencywide Documents Access and Management System (ADAMS) at Accession No. ML23109A092) to perform the MSLB analysis.
The meeting notice and agenda dated September 19, 2024, is available in ADAMS at Accession No. ML24263A063. A list of attendees is provided as an Enclosure.
The NRC staffs questions focused on the following discussion points:
NRC staff would like to confirm whether the same assumptions about the applicability of the fuel types used in the development of the BIASI correlation to Palisades fuel have been previously made with approved CHF correlations used at Palisades.
Multiple assumptions are made in the TR about fuel assemblies however, the NRC staff is interested in the rationale for how the BIASI correlation applies to the Palisades fuel. The NRC staff is interested in knowing whether specific testing has ever been done or is this assumption of application to Palisades a general assumption.
The TR supporting the request contains a brief description and explanation of the CHF correlation. The NRC staff is interested in how CHF correlations has been used at Palisades.
During the discussions with the NRC staff, Holtec and Framatome representatives addressed the NRC staffs questions.
Please direct any inquiries to me at 301-415-6695, or via email at Ngola.Otto@nrc.gov.
Sincerely,
/RA/
Ngola Otto, Project Manager Licensing Project Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosure:
List of Attendees cc: Listserv
Enclosure LIST OF ATTENDEES OCTOBER 2, 2024, MEETING WITH HOLTEC DECOMMISSIONING INTERNATIONAL LLC REGARDING LICENSE AMENDMENT REQUEST TO APPROVE THE BIASI CRITICAL HEAT FLUX CORRELATION FOR USE WITH THE MAIN STEAM LINE BREAK ANALYSIS TO SUPORT POTENTIAL REAUTHORIZATION OF POWER OPERATIONS AT PALISADES NUCLEAR PLANT NRC
Participants:
Ngola Otto, Project Manager, Office of Nuclear Reactor Regulation (NRR), Division of Operating Reactor Licensing Kevin Heller, Nuclear Engineer, Division of Safety Systems (DSS), Nuclear Methods and Fuel Analysis Branch (SFNB)
Joshua Kaizer, DSS, SFNB Robert Beaton, Senior Nuclear Engineer, DSS, Nuclear Systems Performance Branch Clint Ashley, Safety and Plant Systems Engineer, DSS, Technical Specifications Branch Holtec Decommissioning International, LLC:
Jean Fleming, Vice President of Licensing, Regulatory Affairs and PSA James Miksa, Regulatory Assurance Manager for Palisades Michael Schultheis Gregory Baustian, Palisades Licensing Kate Chenier, Palisades Design Engineering & Analysis Manager Rebecca Levack, Palisades Reactor Engineering Joseph Jerz, Engineering Director Framatome Morris Byram, Framatome Licensing and Regulatory Affairs Mihnea Anghelescu, Framatome Engineering Dan Forderkonz, Framatome Project Manager Alex Surdam, Framatome Engineering Brandon Williams, Framatome Engineering
Package: ML24303A129 Meeting Notice: ML24263A063 Meeting Summary: ML24303A116 NRC-001 OFFICE NRR/DORL/LLPB/PM NRR/DORL/LPL3/LA NRR/DORL/LPL3/BC(A) NRR/DORL/LLPB/PM NAME NOtto SRohrer RKuntz NOtto DATE 10/30/2024 10/30/2024 11/06/2024 11/06/2024