MONTHYEARML19255E7911997-05-31031 May 1997 Enclosure 1 - Ecological Assessment of the Low Level Waste Depository, Andrews County, Tx Project stage: Other ML19255E7952004-10-25025 October 2004 Enclosure 2 - Habitat Characterization and Rare Species Survey for the Proposed Low Level Waste Repository, Andrews County, Tx Project stage: Other ML19337B5182007-03-16016 March 2007 Enclosure 10 - Applicable Sections of LLRW License Project stage: Other ML19255E7982007-03-16016 March 2007 Enclosure 3 - Supplemental Survey to Ecological Assessment of the Low Level Waste Depository, Andrews County, Texas Project stage: Supplement ML19217A2112007-04-30030 April 2007 Enclosure 1 - Report on Mapping of a Trench Through Pedogenic Calcrete (Caliche) Across a Drainage and Possible Lineament, Waste Control Specialists Disposal Site, Andrews County, Tx (Public) Project stage: Other ML19255E8002008-07-0303 July 2008 Enclosure 4 - Environmental Assessment Report Prepared for Application for Renewal of Radioactive Material License R04971 Waste Control Specialists LLC Andrews County, Texas Project stage: Request ML19217A2142008-07-28028 July 2008 Enclosure 4 - Report on Activities to Satisfy Byproduct RML Conditions 41A, 41C, and 43, July 2008 (Public) Project stage: Other ML19217A2132011-02-22022 February 2011 Enclosure 3 - Oag Water Levels: Empirical and Modeled Relationships Between Precipitation and Infiltration, 2011 (Public) Project stage: Other ML18100A1852013-04-11011 April 2013 Enclosure 6 - Procedure 12751-MNGP-OPS-01, Revision 0, Spent Fuel Cask Welding: 61BT/BTH NUHOMS Canisters Project stage: Other ML18100A1882013-04-11011 April 2013 Enclosure 7 - Procedure 12751-MNGP-QP-9.201, Revision 0, Visual Weld Examination Project stage: Other ML18100A1912014-01-30030 January 2014 Enclosure 9 - Structural Integrity Associates, Inc. Report 130415.402, Revision 0, Review of Trivis Inc. Welding Procedures Used for Field Welds on the Transnuclear NUHOMS 61BTH Type 1 & 2 Transportable Canister for BWR Fuel Project stage: Other ML18100A1902014-05-22022 May 2014 Enclosure 8 - Structural Integrity Associates, Inc. Report 130415.403, Revision 2, Assessment of Monticello Spent Fuel Canister Closure Plate Welds Based on Welding Video Records Project stage: Other ML18011A1582017-12-22022 December 2017 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Safeguards Related Requests for Supplemental Information Project stage: Supplement ML17249A1572018-01-11011 January 2018, 16 January 2018 Package: Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Request ML17249A1592018-01-16016 January 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Approval ML18022A1522018-01-16016 January 2018 Enclosure 1: Meeting Attendees (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18022A1532018-01-16016 January 2018 Enclosure 2: Agenda (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18022A1542018-01-16016 January 2018 Enclosure 3: Handout-PG&E Presentation on Humboldt Bay ISFSI LRA (Memo to A. Hsia Summary of December 12, 2017, Meeting) Project stage: Meeting ML18022A1512018-01-16016 January 2018 Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay Independent Spent Fuel Storage Installation License Project stage: Meeting ML18018A0192018-01-17017 January 2018 Enclosurequest for Additional Information (Ltr to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040-Accepted for Review) Project stage: RAI ML18018A0182018-01-17017 January 2018 Letter to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040 - Accepted for Review Project stage: Other ML18018B2972018-01-19019 January 2018 Federal Registered Notice: Correction of Certificate of Compliance No. 1004, Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A6122018-01-19019 January 2018 Letter to K. Manzione Amendment No. 4 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System-Request for Additional Information Project stage: RAI ML18022A0782018-01-22022 January 2018 Enclosure 1: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 11, Revision 1 Enclosure 1 Project stage: Other ML18022A0762018-01-22022 January 2018 Package: Correction to Title of Figure 1-15 in Technical Specifications for Certificate of Compliance 1004 Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A0772018-01-22022 January 2018 Letter to J. Bondre Correction to Tn Americas LLC Technical Specifications for Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 to Standardized NUHOMS Certificate of Compliance No. 1004 for Spent Fuel Storage Casks Project stage: Other ML18022A0792018-01-22022 January 2018 Enclosure 2: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 13, Revision 1 Project stage: Other ML18024A2732018-01-24024 January 2018 Letter to D. G. Stoddard U.S. NRC Approval of Virginia Electric and Power Company Request for Withholding Information from Public Disclosure for North Anna Power Station ISFSI (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008 Project stage: Withholding Request Acceptance ML17311A4502018-01-31031 January 2018 ISFSI License Renewal Final Environmental Assessment Project stage: Other ML18031A4572018-01-31031 January 2018 Submittal Date for Response to NRCs Requests for Additional Information (Rais) for License Amendment Request 1032-4 to HI-STORM FW CoC No. 1032 (CAC No. 001028) Project stage: Request ML18036A2222018-02-0101 February 2018 International - Transmittal of HI-STORM Umax License Amendment Request No. 3 - Administrative RAI Response Project stage: Request ML17298A1352018-02-0202 February 2018 Safety Evaluation Report (Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML17298A1342018-02-0202 February 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML18031A2242018-02-0606 February 2018 Enclosure 1: Preamble-SNM-2507 License Renewal Order (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2282018-02-0606 February 2018 Enclosure 2: Safety Evaluation Report (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2252018-02-0606 February 2018 Enclosurenewed License SNM-2507 (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2222018-02-0606 February 2018 Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008) Project stage: Approval ML18031A2272018-02-0606 February 2018 Enclosurenewed License SNM-2507 Technical Specifications (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2312018-02-0808 February 2018 Federal Register Notice - Notice of Issuance for License Renewal (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18053A2332018-02-15015 February 2018 Enclosure 4: CoC 1042 Amendment 1 Proposed Technical Specifications, Revision 0 Project stage: Request ML18053A2342018-02-15015 February 2018 Enclosure 6: Proposed Amendment 1, Revision 0 Changes to the NUHOMS Eos System Updated Final Safety Analysis Report, Chapters 1 to 14 Project stage: Request ML18053A2222018-02-15015 February 2018 Application for Amendment 1 to the NUHOMS Eos System, Revision O (Docket No. 72-1042) Project stage: Request ML18057A2172018-02-23023 February 2018 Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update Project stage: RAI ML18058A0242018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation) Project stage: RAI ML18058A0232018-02-23023 February 2018 Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation Project stage: RAI ML18058A6082018-02-23023 February 2018 HI-2177593, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Underground CISF - Financial Assurance & Project Life Cycle Cost Estimates Project stage: Request ML18057A2182018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update) Project stage: RAI ML18058A0562018-02-23023 February 2018 Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update Project stage: RAI ML18058A6072018-02-23023 February 2018 HI-2177565, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Cis Facility - Decommissioning Cost Estimate and Funding Plan Project stage: Request ML18058A0572018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update) Project stage: RAI 2018-01-11
[Table View] |
Text
Public Version TN Americas CoC 1004 Amendment 19 Pre-Application Meeting September 2024
2 Agenda Purpose of Meeting Scope of Amendment Structural Analysis Summary Thermal Analysis Summary Shielding Analysis Summary Criticality Analysis Summary Other Scope Items Schedule Questions / Open Discussion TN Americas CoC Amd 19 Pre-Application Meeting
3 Purpose of Meeting
- To present TN Americas proposed methodology for performing structural, thermal, shielding, and criticality analysis for BWR fuel assemblies loaded into the newly designed NUHOMS 61BTH Type 3 DSC.
- Briefly discuss other scope items.
- Provide an opportunity to receive NRC feedback and facilitate planning prior to submittal of Amendment No. 19 to CoC 1004.
- Achieve clear, common understanding of the path forward for Amendment No. 19 regarding scope and schedule.
TN Americas CoC Amd 19 Pre-Application Meeting
4 Primary Scope Develop a new basket for the NUHOMS 61BTH (Type 3) which will satisfy all requirements for the NUHOMS 61BTH system as specified in the Technical Specifications (TS) for CoC 1004. These requirements include but are not limited to the following items:
- A new bounding HLZC for the Type 3 that will allow a maximum head load up to 33.6 kW enveloping all previous HLZCs for the Type 2
- Capability of loading up to 4 damaged and/or failed fuel assemblies per DSC
- Maximum burnup of 62 GWd/MTU and maximum initial enrichment of 5.0 wt%
TN Americas CoC Amd 19 Pre-Application Meeting
5 Primary Scope The new NUHOMS 61BTH Type 3 basket implements the EOS-style design [
]
- This is the same basket style that was used for the NUHOMS EOS-37PTH and EOS-89BTH (CoC 1042) as well as the NUHOMS 24PTH Type 3 (Amendment 18 of CoC 1004). [
]
]
- The Type 3 DSC shell will be based on the existing Type 2 DSC shell with only minor modifications in order to accommodate the new Type 3 basket. All major dimensions including length and diameter will remain unchanged.
TN Americas CoC Amd 19 Pre-Application Meeting
6 Primary Scope TN Americas CoC Amd 19 Pre-Application Meeting
7 Structural Summary Methodology Structural evaluation is based on the approved methodologies for NUHOMS 24PTH Type 3 DSC basket from CoC 1004 Amendment 18 as well as for NUHOMS EOS-37PTH and EOS-89BTH from CoC 1042
[
]
Bounding normal/off-normal loads: Dead weight + Handling (basket in horizontal position) + Thermal Accident loads: 75g side drop Criteria:
ASME Boiler and Pressure Vessel Code,Section III, Division 1, Subsection NG Strain criteria: Steel grid plates under accident conditions TN Americas CoC Amd 19 Pre-Application Meeting
8 Structural Summary The structural evaluation of the 61BTH Type 3 considers the following inputs:
Bounding BWR fuel weight assembly Bounding thermal load conditions: storage and transfer Structural Results (preliminary)
Basket stresses and strains meet the criteria for both normal/off-normal and accident loading conditions TN Americas CoC Amd 19 Pre-Application Meeting
9 Thermal Summary TN Americas CoC Amd 19 Pre-Application Meeting The 61BTH Type 3 basket design includes various features to improve the thermal performance such as:
[
]
[
]
[
]
[
]
Thermal performance of the 61BTH Type 3 basket assembly is evaluated under the storage and transfer conditions HLZC#14 (33.6kW) is the bounding heat load configuration for thermal evaluation due to its FA storage arrangement and heat load Bounding storage condition is the normal storage condition in HSM-H with wind Bounding transfer condition is the off-normal transfer condition in OS197 TC
10 TN Americas CoC Amd 19 Pre-Application Meeting Thermal Summary Methodology Storage evaluation, as well as transfer evaluation, are based on reviewed and accepted models and analyses for 24PTH DSC in HSM-H and OS197, respectively, from CoC 1004 Amendment 18 Coupled DSC/HSM-H and DSC/TC models in ANSYS Fluent Grid convergence index (GCI) study has been provided Thermal Results (preliminary)
With bounding heat load of 33.6 kW, the specified time limit for transfer operation is 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> Maximum fuel cladding temperatures are within the temperature limits in the current UFSAR under all operating conditions Maximum internal pressures are within the pressure limits in the current UFSAR under all operating conditions
11 TN Americas CoC Amd 19 Pre-Application Meeting Shielding Summary The shielding HLZC, UFSAR Table T.5-1a, introduced in Amendment 17 bounds all the 13 HLZCs and new HLZC 14 for 61BTH DSCs therefore no further shielding analysis is performed HLZC 14 - 0.48 kW Zone1 and 0.6 kW Zone 2 UFSAR Table T.5-1a
12 Criticality Summary Fresh Fuel Assumption Fresh fuel assumption (reviewed and approved method through past CoC 1004 Amendments and CoC 1042 Amendments)
Criticality analysis performed for bounding fuel GE 10x10 in 61BTH Type 3 Gadolinium Credit Fresh fuel assumption with credit to fuel rods containing gadolinium oxide (Gd2O3)
[
]
[
]
TN Americas CoC Amd 19 Pre-Application Meeting
13 Criticality Summary Overview of the gadolinium credit method
[
]
[
]
[
]
Computer code SCALE 6.1.3 and ENDF/B-VII nuclear data library New benchmark including UO2-Gd2O2 critical experiments TN Americas CoC Amd 19 Pre-Application Meeting
14 Criticality Results(Preliminary)
Fresh fuel assumption - 61BTH Type 3 GE 10x10 up to 4.9 wt%
[
]
[
]
[
]
[
]
TN Americas CoC Amd 19 Pre-Application Meeting
15 Other Scope Items Add an ASME code alternative for NB/NG-4323 to Technical Specifications Table C-12 for welder qualification.
The alternative will state that in lieu of this requirement, a full UT evaluation of the joint may be performed to ensure adequacy of the weld.
TN Americas CoC Amd 19 Pre-Application Meeting
16 Submittal Schedule Application Submittal - November 2024 Requested Approval - November 2026 TN Americas CoC Amd 19 Pre-Application Meeting
17 Questions/ Open Discussion TN Americas CoC Amd 19 Pre-Application Meeting