Lessons Learned from the U.S. NRC Staffs Review of the ARITA Topical Report ANP-10339P, ARITA - ARTEMIS/RELAP Integrated Transient Analysis Methodology December 14, 2023 1
Agenda Topic
- of Slides Introduction 1
Review History and Timeline 2
Example Lessons-Learned Categories 1
Examples of Lessons Learned and Best Practices 1
Recommendations from Framatome / Discussion 1
Lessons Learned Schedule 1
Presentation Total 7
2
Introduction
- ARITA is a complex methodology for analyzing a wide array of SRP Chapter 15 events (non-LOCA, no rod ejection).
- Multiple challenges were encountered during the review effort.
- Review schedule required extension on multiple occasions.
- NRC is initiating a lessons learned assessment of the ARITA review.
- Framatome also requested to provide input for the lessons-learned assessment.
3
Review History 4
FRAMATOME NRC ANP-10339P Submitted Aug 2018 Acceptance Review Complete Nov 2018 Acceptance Review Supplement Mar 2019 Onsite Audit Sept 2019 Batch 1 RAIs (13)
Issued Dec 2019 Prospective L&Cs First Discussed Dec 2020
Response
to 13 RAIs Mar 2020
Response
to 37 RAIs Jul 2020
Response
to 16 RAIs Dec 2020
Response
to 26 RAIs May 2021 Updated Topical Report / Final RAI Response Jun 2022 Batch 2 RAIs (79)
Issued Apr 2020 Draft SE Apr 2023 2018 2019 2020 2021 2022 2023 19 Audits & Meetings to Resolve RAIs Nov 2020 - April 2022 Acceptance Supplement Detailed Review RAI Resolution Draft SE ACRS SC Jun 2023
Review Schedule and Timeline Dates 5
Milestone/Activity Planned Dates Actual Dates Submittal 8/31/2018 Acceptance Letter 12/18/2018 Acceptance Supplement 3/14/2019 RAI Round 1 [RAI 1-13]
11/15/2019 12/10/2019 Response to RAI Round 1 1/15/2020 3/31/2020 RAI Round 2 [RAI 14-92]
11/15/2019 4/14/2020 Responses to RAI Round 2 5/29/2020; 7/31/2020 7/31/2020 - 6/2/2021 Audits & Meetings 11/12/2020 - 4/28/2022 Final & Combined RAI Response 6/30/2022 Draft SE 7/31/20201 4/17/2023 Final SE 8/31/20212 10/16/2023 1 Original Draft SE date, adjusted to 10/14/22; 1/16/23; 3/31/23 2 Original Final SE date, adjusted to 12/31/21; 5/31/22; 2/28/23; 6/30/23
Example Lessons-Learned Categories
- Staff is considering lessons learned and best practices for several different areas of the review
- Topical Report Review Process
- Expanding a Risk-Informed Review Strategy
- Managing Schedules and Resources
- Resolving Technical Concerns 6
Examples of Lessons Learned and Best Practices
- Lessons Learned:
- NRC staff and vendor should take advantage of preapplication readiness review
- NRC staff should more strictly adhere to submittal content and quality criteria in the acceptance review process
- NRC staff should strive for early identification and timely resolution of technical issues
- Best Practices:
- Using virtual and in-person regulatory audits
- Developing a detailed RAI-tracking list, documenting RAI status
- Framatome preparing topic-specific presentations for audits and meetings 7
Recommendations from Framatome and Discussion 8
Lessons Learned Schedule
- NRC draft results completion by: (Tentative) January 17, 2024 9