KP-NRC-2310-004 Response to Hermes 2 General Audit Question 1.5-1 (Non-Proprietary)
Page1of4
Hermes2AuditQuestionNumber:1.51 Onpage12oftheHermes1safetyevaluation(SE)(AgencywideDocumentAccessandManagement System(ADAMS)AccessionNo.ML23158A265),theNRCstaffidentifiedseveralsupplementstothe Hermes1constructionpermit(CP)applicationthatprovideadditionalinformationonthatdocket beyondthelatestversionsofthePreliminarySafetyAnalysisReportandreferencedtechnical reports.PleaseidentifywhichoftheseHermes1applicationsupplementsareapplicabletoand incorporatedbyreferenceintotheHermes2CPapplication.
KairosPowerResponse:
ThefollowingsupplementstotheHermesconstructionpermitapplication(CPA)identifiedinthe HermesSE(Reference1)areprovidedbelowwiththeirapplicabilitytotheHermes2CPA:
TransmittalofResponsestoNRCQuestions2.31and2.32ontheHermesPreliminary SafetyAnalysisReport,datedFebruary3,2022(Reference2)
ThissupplementprovidedrawmeteorologicaldataandARCON96inputandoutput filesfortheHermesReactor.Theresponsetoquestion2.32identifiedaformatting errorinthemeteorologicaldataandanerrorinthechronologicalorderthefiles werelistedinfortheARCON96run.Theseerrorswerecorrectedandtheupdated sitespecific/QvaluesweresubmittedtotheNRCbyletterdatedMarch1,2022 (Reference12).
TherawmeteorologicaldataandtheARCON96inputfilescontainedinthis supplementareapplicabletoHermes2.Theupdatedsitespecific/Qvalues submittedtotheNRCbyletterdatedMarch1,2022arealsoapplicabletoHermes2.
Thissupplementandtheupdatedsitespecific/QvaluessubmittedtotheNRCby letterdatedMarch1,2022followingcorrectionoftheerrorsidentifiedinthe supplementisapplicabletotheHermes2CPA.Nochangesarerequiredtothe Hermes2PSARbecausetheupdatedvaluesprovidedintheMarch1,2022letter havebeenincorporatedintoHermes2PSARTables13.21and13.22.
KairosPowerResponsetoNRCQuestions2.41,2.42,and2.43forPSARSection2.4on HermesConstructionPermitApplication,datedFebruary8,2022(Reference3)
ThissupplementprovideddescriptionofhowthefloodelevationshowninPSAR Table2.42wasdeveloped,statednodamsafetyupdateswereidentifiedforNorris orMeltonHilldamssince2014,andincludedthesubmissionsofflooding evaluationsreferencedintheHermesPSAR.
ThissupplementisapplicabletotheHermes2CPAwithoneclarification.Inthe responsetoquestion2.41,HermesEnvironmentalReportFigure3.42,FEMAFlood Hazards,isreferencedasprovidingthecurrentlyavailableFEMAmapthatindicates thattheestimated100yrand500yrfloodplainsremainwellbelowthesite footprint.FortheHermes2EnvironmentalReport,theFEMAFloodHazardsare providedinFigure3.21.
KairosPowerResponsetoNRCQuestions2.51,2.52,2.53,and2.54forPSARSection2.5 onHermesConstructionPermitApplication,datedFebruary9,2022(Reference4)
Thissupplementprovided:
o AresponsethatthePSARreflectsanassumptionthattheClinchRiverEarlySite Permitapplicationearthquakecatalog(endingin2013)isrepresentativeofthe seismicactivitytobeexpectedattheHermessite,
Page2of4 o Adescriptionofthemethodfordeterminingthatfoundationrockshowsnosignsof karsticdissolution, o AnewPSARFigure2.52thatincludestheMascotDolomiteshowninPSARFigure 2.51,and o AnewPSARFigure2.53showingthedipinterfaceconsistentwiththeElverton Quadrangle.
ThissupplementisapplicabletotheHermes2CPAwithoneclarification.The approximatedepthsofweatheredrock,thetopofsoundrock,andtheplanned excavationdepthfortheHermes2reactorlocationsmaybedifferentfromthe approximatedepthsspecifiedfortheHermesreactorlocation.Nochangesarerequired totheHermes2PSARbecausethechangestoFigures2.52and2.53describedinthis submittalhavealreadybeenincorporated.
KairosPowerTransmittalofReponsestoNRCRequestsforConfirmationofInformationfor HermesPreliminarySafetyAnalysisReportSection9.1,datedAugust19,2022(Reference5)
Thissupplementprovidedconfirmatoryinformationthattheapplicationforan operatinglicensewillshowtheselectedcoolantchemistrysamplinglocationstobe wellmixed,representativesamplesofthecoolant,theinertgassystemwillbe capableofmeasuringboththeairandmoisturecontentofthecovergas,the entiretyoftheinertgassystemcanbeperiodicallyleakchecked,andtheinertgas systemisnotneededtocontrolthehotcelltemperaturereferencedinthePebble HandlingandStorageSystemMalfunctionEvent.
ThissupplementisapplicabletotheHermes2CPA.
KairosPowerResponsetoNRCRequestforAdditionalInformation348and339,dated August31,2022.(Reference6)
Thissupplementprovidedresponsestorequestsforadditionalinformationfor questionsregardingtheReactorControlandShutdownSystemandthenatural circulationflowpath.
ThissupplementisapplicabletotheHermes2CPA.Nochangesarerequiredtothe Hermes2PSARbecausethePSARmarkupsincludedwiththeresponsetothisRAI havebeenincorporatedintotheHermes2PSAR.
KairosPowerResponsetoNRCRequestforAdditionalInformation350,datedSeptember1, 2022(Reference7)
Thissupplementprovidedresponsestorequestsforadditionalinformationfor questionsregardingairingress.
ThissupplementisapplicabletotheHermes2CPA.Nochangesarerequiredtothe Hermes2PSARbecausethePSARmarkupsincludedwiththeresponsetothisRAI havebeenincorporatedintotheHermes2PSAR.
KairosPowerTransmittalofResponsetoNRCQuestiononDHRSTestingfromPSARSection 6.3AuditonHermesPreliminarySafetyAnalysisReport,datedSeptember1,2022 (Reference8)
ThissupplementprovidedaresponsetoNRCauditquestionregardingDecayHeat RemovalSystemtesting.
ThissupplementisapplicabletotheHermes2CPA.
Page3of4 KairosPowerAdditionalInformationRelatedtoConstructionPermitApplication-PSAR Chapter1,datedNovember15.2022(Reference9)
ThissupplementprovidedacopyofaletterfromtheUSDepartmentofEnergyto KairosPowerregardingcontractdiscussionsforthemanagementofspentnuclear fuelandhighlevelwaste.
ThelettercontainedinthissupplementisonlyapplicabletotheHermesreactor.A separateHermes2supplementwillbeprovidedatalaterdate.
KairosPowerTransmittalofReponsestoNRCQuestiononHermesPreliminarySafety AnalysisReport,datedDecember8,2022(Reference10)
ThissupplementprovidedaresponsetoanNRCauditquestionregardingthe scheduleforcompletingresearchanddevelopmentactivitieslistedinHermesPSAR Section1.3.9.ResearchanddevelopmentactivitieslistedinPSARSection1.3.9will becompletedpriortothecompletionofconstruction.ForHermes,thelatest projecteddateforcompletionisDecember2026.
Thedateforanticipatedcompletionofconstructionprovidedinthissupplementis notapplicabletoHermes2.However,Theresearchanddevelopmentactivitieslisted inHermes2PSARSection1.3.9willbecompletedpriortothecompletionof constructionoftheHermes2facility.AsstatedinEnclosure1toletterSubmittalof thePreliminarySafetyAnalysisReportfortheHermes2KairosPowerFluorideSalt Cooled,HighTemperatureNonPowerReactor(Hermes2),Revision0,datedJuly 14,2023(Reference13),thelatestprojectedcompletiondateforthefirstunitisJuly 2027.
KairosPowerTransmittalofChangestoPreliminarySafetyAnalysisReportChapter6and ResponsetoNRCQuestiononDHRSTesting,KPNRC2212003,datedDecember19,2022 (Reference11)
ThissupplementprovidedaresponsetoafollowupNRCauditquestionon additionalDecayHeatRemovalSystemperformancephenomenatesting.
ThissupplementisapplicabletotheHermes2CPA.Nochangesarerequiredtothe Hermes2PSARbecausethePSARmarkupsincludedwiththissupplementhavebeen incorporatedintotheHermes2PSAR.
ImpactonLicensingDocument:
ThisresponsehasnoimpactonthecontentofHermes2PSAR.
References:
- 1. SafetyEvaluation,NuclearRegulatoryCommission,SafetyEvaluationRelatedtotheKairos PowerLLCConstructionPermitApplicationfortheHermesTestReactor,June2023 (ML23158A268)
- 2. Letter,KairosPowerLLCtoDocumentControlDesk,TransmittalofResponsestoNRC Questions2.31and2.32ontheHermesPreliminarySafetyAnalysisReport,February3, 2022(ML22041A337)
- 3. Letter,KairosPowerLLCtoDocumentControlDesk,ResponsetoNRCQuestions2.41,2.4 2,and2.43forPSARSection2.4onHermesConstructionPermitApplication,February8, 2022(ML22040A141)
- 4. Letter,KairosPowerLLCtoDocumentControlDesk,ResponsetoNRCQuestions2.51,2.5 2,2.53,and2.54forPSARSection2.5onHermesConstructionPermitApplication, February9,2022(ML22040A336)
Page4of4
- 5. Letter,KairosPowerLLCtoDocumentControlDesk,TransmittalofReponsestoNRC RequestsforConfirmationofInformationHermesPreliminarySafetyAnalysisReport, Section9.1,August19,2022(ML22231B228)
- 6. Letter,KairosPowerLLCtoDocumentControlDesk,ResponsetoNRCRequestfor AdditionalInformation348and339,August31,2022(ML22243A247)
- 7. Letter,KairosPowerLLCtoDocumentControlDesk,ResponsetoNRCRequestfor AdditionalInformation350,September1,2022(ML22252A149)
- 8. Letter,KairosPowerLLCtoDocumentControlDesk,TransmittalofResponsetoNRC QuestiononDHRSTestingfromPSARSection6.3AuditonHermesPreliminarySafety AnalysisReport,September1,2022(ML22244A235)
- 9. Letter,KairosPowerLLCtoDocumentControlDesk,AdditionalInformationRelatedto ConstructionPermitApplication-PSARChapter1,November15,2022(ML23019A360)
- 10. Letter,KairosPowerLLCtoDocumentControlDesk,TransmittalofReponsestoNRC QuestiononHermesPreliminarySafetyAnalysisReport,December8,2022(ML22342B282)
- 11. Letter,KairosPowerLLCtoDocumentControlDesk,TransmittalofChangestoPreliminary SafetyAnalysisReportChapter6andResponsetoNRCQuestiononDHRSTesting, December19,2022(ML22353A625)
- 12. Letter,KairosPowerLLCtoDocumentControlDesk,TransmittalofChangestoMaximum HypotheticalAccidentDoseResultsinHermesConstructionPermitApplication,March1, 2022(ML22060A272)
- 13. Letter,KairosPowerLLCtoDocumentControlDesk,SubmittalofthePreliminarySafety AnalysisReportfortheHermes2KairosPowerFluorideSaltCooled,HighTemperatureNon PowerReactor(Hermes2),Revision0,July14,2023(ML23195A122)