L-2023-142, Florida Power & Light - Submission of Periodic Reports
| ML23290A081 | |
| Person / Time | |
|---|---|
| Site: | Turkey Point |
| Issue date: | 10/16/2023 |
| From: | Strand D Florida Power & Light Co |
| To: | Office of Nuclear Reactor Regulation, Document Control Desk |
| References | |
| L-2023-142 | |
| Download: ML23290A081 (1) | |
Text
October 16, 2023 U.S. Nuclear Regulato1y Commission Attention: Document Control Desk 11545 Rockville Pike One \\v'hite Flint North Rockville, IvID 20852-2746 Turkey Point Units 6 and 7 Dockets52-040 and 52-041 Combined License Nos. NPF-104 and NPF-105 SUBMISSION OF PERIODIC REPORTS
References:
L-2023-142 10CFR 52.3 10CFR 50.59 10 CFR 52.97(c) 10CFR 52 Appendix D, X.B
- 1.
FPL Letter L-2019-074 dated April 9, 2019, License Conditions 2.D.(11) Schedules - Initial Submittal
- 2. FPL Letter L-2019-176 dated September 25, 2019, Tier 1 and Updated Final Safety Analysis Report Annual Submittal
- 3.
FPL Letter L-2022-167 dated October 13, 2022, Submission of Periodic Reports (ADAMS Accession No. ML22286A052)
- 4. FPL Letter L-2023-054 dated April 12, 2023, Submission of Periodic Reports (ADAMS Accession No. ML23102A150)
The purpose of this letter is to submit periodic reports for Turkey Point Units 6 & 7 (PTN 6 & 7) as required by NRC regulations and/ or license conditions as a Part 52 combined license (COL) holder. The following reports are addressed by this letter, updated from the previous reporting period (References 1 and 3):
- Semi-Annual Departures Report
- Semi-Annual Changes, Tests, and Experiments Report
- Semi-Annual Update of the Operational Programs Implementation Schedule
- Annual Update of the Tier 1 Material and Updated Final Safety Analysis Report (UFSAR)
Semi-Annual Departures Report and Semi-Annual Changes, Tests, and Experiments Report - For PTN 6 & 7, in accordance with the requirements of 10 CFR 50.59(d)(2) and 10 CFR 52, Appendix D, paragraphs X.B.1 and X.B.3.b, during the period April 1, 2023 through September 30, 2023:
- No changes, tests or experiments were implemented pursuant to 10 CFR 50.59(c).
- No plant-specific departures were implemented under 10 CFR 52, Appendix D, Section VIII.
Florida Power & Light Company 15430 Endeavor Drive, Jupiter, Florida 33478
Document Control Desk L-2023-142 Page 2 Semi-Annual Update of the Operational Programs Implementation Schedule Pursuant to the PTN 6
& 7 COLs Section 2.D.(11), the schedule for implementation of operational programs is to be updated eveiy six months. Because there are no changes to FPL's constmction decision, the schedule p1*ovided in Refei-ence 1 is reaffirmed.
Annual Update of the Tier 1 Material and UFSAR-For PTN 6 & 7, in accordance with the requirements of 10 CFR 52, Appendix D, paragraphs X.B.2 and X.B.3.b, during the period of September 1, 2022 through August 31, 2023:
- No changes were implemented to the Tier 1 Material and UFSAR.
Therefore, the previously submitted Tier 1 Material and UFSAR (Enclosures 1 and 2 of Reference 2) remain applicable.
If you have any questions, or need additional information, please contact Mike Davis at 319-851-7032.
I declare under penalty of perjuiy that the foregoing is tme and correct.
Executed on the 16th day of October 2023.
Sincerely, Dianne Strand General Manager, Regulatoiy Affairs Florida Power & Light Company cc:
USNRC Regional Administrator, Region II USNRC PTN 6 & 7 Project Manager, NRR/DNRL USNRC Senior Resident Inspector, Turkey Point Nuclear Plant