L-2022-167, Submittal of Periodic Reports
| ML22286A052 | |
| Person / Time | |
|---|---|
| Site: | Turkey Point |
| Issue date: | 10/13/2022 |
| From: | Dean Curtland Florida Power & Light Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| L-2022-167 | |
| Download: ML22286A052 (2) | |
Text
Florida Power & Light Company 15430 Endeavor Drive, Jupiter, Florida 33478 October 13, 2022 L-2022-167 10CFR 52.3 10CFR 50.59 10 CFR 52.97(c) 10CFR 52 Appendix D, X.B U.S. Nuclear Regulatory Commission Attention: Document Control Desk 11545 Rockville Pike One White Flint North Rockville, MD 20852-2746 Turkey Point Units 6 and 7 Dockets52-040 and 52-041 Combined License Nos. NPF-104 and NPF-105 SUBMISSION OF PERIODIC REPORTS
References:
- 1. FPL Letter L-2022-053 dated April 13, 2022, Submission of Periodic Reports (ADAMS Accession No. ML22103A033)
- 2. FPL Letter L-2019-074 dated April 9, 2019, License Conditions 2.D.(11) Schedules - Initial Submittal
- 3. FPL Letter L-2019-176 dated September 25, 2019, Tier 1 and Updated Final Safety Analysis Report Annual Submittal The purpose of this letter is to submit periodic reports for Turkey Point Units 6 & 7 (PTN 6 & 7) as required by NRC regulations and/or license conditions as a Part 52 combined license (COL) holder. The following reports are addressed by this letter, updated from the previous reporting period (References 1 and 3):
Semi-Annual Departures Report Semi-Annual Changes, Tests, and Experiments Report Semi-Annual Update of the Operational Programs Implementation Schedule Annual Update of the Tier 1 Material and Updated Final Safety Analysis Report (UFSAR)
Semi-Annual Departures Report and Semi-Annual Changes, Tests, and Experiments Report - For PTN 6 & 7, in accordance with the requirements of 10 CFR 50.59(d)(2) and 10 CFR 52, Appendix D, paragraphs X.B.1 and X.B.3.b, during the period April 1, 2022 through September 30, 2022:
No changes, tests or experiments were implemented pursuant to 10 CFR 50.59(c).
No plant-specific departures were implemented under 10 CFR 52, Appendix D, Section VIII.
Semi-Annual Update of the Operational Programs Implementation Schedule - Pursuant to the PTN 6
& 7 COLs Section 2.D.(11), the schedule for implementation of operational programs is to be updated every
Document Control Desk L-2022-167 Page 2 six months. Because there are no changes to FPLs construction decision, the schedule provided in Reference 2 is reaffirmed.
Annual Update of the Tier 1 Material and UFSAR - For PTN 6 & 7, in accordance with the requirements of 10 CFR 52, Appendix D, paragraphs X.B.2 and X.B.3.b, during the period of September 1, 2021 through August 31, 2022:
No changes were implemented to the Tier 1 Material and UFSAR.
Therefore, the previously submitted Tier 1 Material and UFSAR (Enclosures 1 and 2 of Reference 3) remain applicable.
If you have any questions, or need additional information, please contact me at 561-803-7900.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on the 13th day of October 2022.
Sincerely, Dean Curtland Vice President, Nuclear Florida Power & Light Company cc:
USNRC Regional Administrator, Region II USNRC PTN 6 & 7 Project Manager, NRR/DNRL USNRC Senior Resident Inspector, Turkey Point Nuclear Plant